Engineering Resource Management using Theory of Constraints - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Engineering Resource Management using Theory of Constraints

Description:

First program: running 4-5 months late; with Concerto, it finished 36 days earlier! ... Concerto delivered value within first 4 weeks by highlighting bottlenecks which ... – PowerPoint PPT presentation

Number of Views:118
Avg rating:3.0/5.0
Slides: 17
Provided by: scpd3
Category:

less

Transcript and Presenter's Notes

Title: Engineering Resource Management using Theory of Constraints


1
Engineering Resource Management using Theory of
Constraints
CONFIDENTIAL
Presentation to SOCE, San Diego December, 2001
2
Why a breakthrough is essential What is the core
problem How it can be solved case studies
3
ENGINEERING ORGANIZATIONS ARE UNDER TREMENDOUS
PRESSURE
4
Why a breakthrough is essential What is the core
problem How it can be solved case studies
5
HOW MUCH PERCENTAGE GAIN IN CYCLE TIME SHOULD WE
EXPECT
10
10
10
10
10
6
UNCERTAINTY SHARED RESOURCES CHAOS
7
RESULT WASTED CAPACITY UNPREDICTABLE AND LONG
LEAD TIMES
Long lead times Project delays Firefighting Multit
asking
8
MORE COMMUNICATION ONLY CREATES INFORMATION
OVERLOAD
More data More reports More emails . .


9
Why a breakthrough is essential What is the core
problem How it can be solved case studies
10
PIPELINE OPTIMIZATION CONSTRAINTS-BASED
SCHEDULING
  • Balance capacity everywhere
  • Stretched project schedules
  • Low capacity utilization
  • Schedule bottlenecks first
  • Compressed project schedules
  • High capacity utilization

11
CONTINUOUS FLOW EXECUTION BUFFER MANAGEMENT
Transient overload
Capacity
Capacity
  • Use buffers to isolate critical work
  • Critical work does not stop
  • Stable priorities
  • Treat all load as same
  • Continual interruptions to flow
  • Unstable priorities

12
IMPACT ON BOTTOM-LINE
13
EXAMPLES OF VALUE DELIVERY
  • 4,000 people, 400 programs, 4 countries
  • Time-to-market reduction 20-30
  • On time delivery close to 100
  • 3,000 people, 50 product and technology programs
  • First program running 4-5 months late with
    Concerto, it finished 36 days earlier!
  • Historical Seagate moment competition dropped
    out
  • Return in 6 months Revenue 11M GM 5 M
  • 1,000 people, 150 programs
  • Time-to-market reduction 30
  • On time delivery close to 100, a record
  • Concerto used for operation reviews by CEO of
    this 1B company
  • 100 people, 20 programs
  • Time-to-market reduction 20
  • We are now able to meet required delivery
    dates- says Avi Domoshevizki, CEO

14
MORE EXAMPLES OF VALUE DELIVERY
  • Managing 200 NPD projects simultaneously
  • Substantial improvement in on-time delivery (from
    20 to 80)
  • Over 100 IT professionals working on 75-100
    projects
  • Excellent reception from users on simplifying
    management
  • Complex engineer-to-order products
  • Average lead time down from 9 months to 6.5
    months
  • On-time delivery up from 50 to 90
  • Hybrid mix of defense electronics and avionics
    products
  • Key challenge in retrofitting and systems
    integration
  • On-time delivery up from lt60 to greater than 90
  • Throughput up by 20
  • Very complex products, requiring integration of
    multiple modules
  • Concerto delivered value within first 4 weeks by
    highlighting bottlenecks which were not obvious
    before

Israeli Defense Forces
15
CONTACT INFORMATION
Presenter Sanjeev Gupta sgupta_at_speedtomarket.com
408-271-6574 Further Reading The Goal, Dr.
Eliyahu M. Goldratt Critical Chain, Dr. Eliyahu
M. Goldratt Managing The Design Factory, Donald.
G. Reinertsen
16
CURRENT SOLUTIONS CAN PROVIDE ONLY MARGINAL
BENEFITS
Automate engineering
  • Has reached a point of diminishing returns
  • Local improvements do not always translate to
    global gains

Automate administration
  • Does not impact the core process
  • Eats into engineering capacity
Write a Comment
User Comments (0)
About PowerShow.com