Title: Setup Reduction Workshop


1
Setup Reduction Workshop
  • June, 2009
  • Rick Bohan

2
Agile Manufacturing Ideal
  • Make exactly what customers want,
  • exactly when they want it
  • In exactly the right quantities
  • Without waste

3
Why Reduce Setups?
Competitive Advantage
4
The Benefits of Quick Change
  • Flexibility
  • Quicker Delivery
  • Better Quality
  • Lot-size can be reduced.
  • Help to reduce inventory.
  • Increase capacity on bottleneck equipment.
  • Help to eliminate setup scrap.

5
The Benefits To Workers
  • Safer Setups and Changeovers
  • Less Frustration
  • Less Workplace Clutter
  • More Consistency

6
The amount of time taken to change a machine from
the last good part of a production lot to the
first good part of the next production lot.Clock
time! Not labor time!
Setup Reduction
7
Typical Setup Process
  • Preparation, checking materials 30
  • Exchanging tooling 5
  • Measurements and settings 15
  • Trial runs and adjustments 50

8
Two Kinds of Setup Steps
  • Internal Must be done with machinery off.
  • External Can be done while machinery is running.

9
Setup Time Reduction
External Setup Steps
Present Setup
Lots Less Time and Hassle!
Internal Setup Steps
Streamline Internal Setup Steps
10
The Three Stages of Reducing Changeovers
  • Stage 1 Separating Internal and External Steps.
  • Stage 2 Moving External Steps Out of the
    Changeover.
  • Stage 3 Streamline All Aspects of Changeover

11
Stage 1Separate Internal and External
  • What are all the steps that can be done before or
    after the setup?

12
Stage 2Convert Internal to External
  • Get and prepare tools and tooling before the
    setup.
  • Get materials and supplies ready before the setup
  • Make adjustments quickly before starting the
    machine
  • Put tools, tooling, etc. away after the setup
  • Standardize all this

13
Stage 3 Streamline All Other Aspects
  • Use more people.
  • Develop Function Checklists Check to make sure
    everything works.
  • Use quick-release fasteners instead of bolts and
    nuts.
  • Use locating pins and holes to eliminate
    adjustments.
  • Use standardized tools and tooling whenever
    possible.
  • Apply 5S and Visual Factory. Make indexes,
    adjustments, marks very visible.
  • Use checklists to avoid omission.
  • Use designated carts to help organize tools.

14
How We Will Analyze Setups
  • Videotape or observe the setup
  • Review video or observation sheet and describe
    the steps
  • Analyze each step Internal or external? Move
    internal to external.
  • Streamline everything else.