Title: Denver International Airport
1Denver International Airport
2Before I Begin
It is important to realize that a disasters
magnitude cannot be measured by body count alone.
The Denver International Airport qualifies as a
disaster because of the economic and social
ramifications. While this disaster may not have
cost anyone their lives, the sixteen-month delay
caused by the failure of the baggage
transportation made the airport the laughingstock
of the engineering community, costing
stockholders both their pride and their money.
Denver International Airport is practically a
text book lesson on the necessity of careful
planning, and the dangers of streamlining the
design of any project.
3Information about Denver International Airport
and its construction.
- It was approved for construction in 1989, because
its predecessor, Stapleton was starting to get
too small for the growing city, and was first
scheduled to open on October 31, 1993 . - It was the first major airport to be built in the
United States in over 20 years. - The Denver international Airport is comprised of
three terminals, and several runways, and is
built on 53 square miles of land. (Thats twice
the size of Manhattan Island!)
4The Foundation of Failure.
- Problems first arose at the Denver International
Airport when it came time to implement a baggage
handling system. - DIA planning officials had anticipated each of
the individual airlines planning to use the
airport to provide their own baggage systems
however, as of 1991, United Airlines, was the
only just beginning to negotiate a contract. - As a result the DIA officials renegotiated the
contract, to have the system being designed for
United service the entire airport
5About the Development Firm
- The Company that United had contracted was Dallas
based engineering firm BAE Systems Inc. one of
the leaders of the industry. - The baggage handling system that United had
contracted was fully automated a radical design
which, when completed, would only be the second
of its kind in the world, the first being DIAs
sister airport in Munich Germany. - Because of this, BAE had been reluctant to take
the original contract, and when the contract was
renegotiated, they were forced to build one three
times the original's size.
6Major Problems Facing BAE
- Design Scope -The baggage system which BAE needed
to deliver was on such a massive scale, making
the design quite challenging. - Difficulty Several factors created by DIA and
United Airlines made the already daunting
challenge nearly impossible - Time BAE had only 17 months to complete the
system
7The Ridiculous Scope of the Project.
- As stated earlier, Denver International Airport
is enormous, for BAE this meant massive amounts
of machinery needed to be installed. - This meant that glitches in the system could be
nearly impossible to pinpoint.
- List of components.
- 20 miles of track
- 6 miles of conveyer belts
- 56 laser arrays that read bar coded tags
- 400 frequency readers
- 3,100 standard size baggage Telecars
- 450 6.5 ft by 4 ft oversize cars
- 55 separate computers
8Additional Design Problems caused by the Airlines
- As difficult as designing the system was,
airlines planning to use the airport made it even
more difficult. - They did this by demanding thousands of major and
minor modifications to the system. - The largest modification was United Airlines
request to remove one of the two loops of track
that serviced their section of the airport.
9The Absurd Timeframe
- BAE Systems was able to begin work on the baggage
system in April of 1992, less than 17 months
before the airports scheduled opening October
31, 1993.
- This is a sharp contrast to DIAs sister airport
in Munich. German technical advisors told their
Denver counterparts that they had spent two
entire years testing the system. In addition,
they had the system running 24 hours a day for
six months before the airport opened
10Critical Errors in Design and construction.
- The decision to build the system came so late in
the construction process - Lack of communication between BAE and their
German Counterparts - Lack of communication within BAE
11The Decision that Came too Late.
- The decision to commission the baggage system so
late in the building process had a second adverse
consequence. - Aside from creating a ridiculous deadline, it
also meant that most of the construction to the
building was already done, so BAE had to build
around the existing architecture, even though it
should have been the other way around. - Since the building was designed to accommodate a
conventional baggage system, with long narrow
hallways and sharp turns, the design was
particularly difficult.
12The Mistake of Ignoring Experienced Help.
- Another critical failures in the project was made
by BAE systems, this mistake was that they paid
little attention to advise from the engineers
that worked on the Munich baggage system - Because of this foolish mistake, BAE engineers
had to practically design the entire system from
scratch, when they could have saved time, money,
and effort by basing their system on the already
existing, and working German system.
13The Million Dollar Jigsaw puzzle
- Perhaps the most foolish mistake on anyones part
during the entire project was the utter lack of
communication between the different design teams
working on the project. - Simply put, after being ordered to create one of
the worlds most complex machines, the designers
made all of its components separately, with
little or no understanding of how the system
functioned as a whole, like a giant jigsaw puzzle.
14The Coup de Grace.
- While all of the previous blunders contributed to
the failure of the system, the worst mistake was
still yet to come. It was a decision so terrible,
so foolish, so absolutely idiotic that it would
put to shame every single person who worked on
the project.
15The decision to broadcast the preliminary test of
the revolutionary new baggage system on
national television
16- What camera crews depicted was truly a disaster
carts jammed together, damaged luggage
everywhere, some bags literally split in half,
and the tattered remains of clothing strewn about
causing subsequent carts to derail. Finally,
adding insult to injury, half the luggage that
survived the ordeal ended up at the wrong
terminal. - These result came after the airports opening was
delayed not once, but twice.
17Aftermath of the test.
- Denvers mayor, Wellington Webb, announced the
third opening delay. - Denver called in a German engineering firm Denver
called in a German engineering firm Logplan, who
had worked on the Munich Airport.
18Logplans Observations and suggested solutions
- The system was too complex in its design.
- The scope of the design was far too large.
- The system did not have a failsafe.
- Recommended simplifying the design
- Suggested that system be divided into three
parts, one for each terminal. - They Implemented a manual tug and cart system as
backup
19The Grand Opening.
The Grand Opening.
- After a fourth delay, Denver International
Airport finally opened on February, 28 1995. - However the automated system only serviced
outbound flights in concourse . - The manual backup system serviced the other two
terminals
20The Bottom Line.
- The delays cost the city of Denver thirty three
million dollars a month in interest. - In total, delays postponed the airports opening
by sixteen months that equates to put the airport
being 1.3 billion dollars over budget!
21The Results of the Delay on Airline Confidence
- Airlines loss of faith in DIA was reflected in
their contracts. - American would only agree to a month-to-month
lease. - Continental downsized from twenty gates, to four.
- Southwest shunned DIA entirely.
22Who Paid the Price.
- It was ultimately the travelers who would pay for
this engineering blunder. - DIAs costs per passenger was 16.50 compared to
the 8 national average. - This meant that fairs increased, one example is
United Airlines, who raised fairs by an average
of forty dollars.
23What can be Learned From DIA.
- Need for careful methodic planning.
- Had the baggage system been decided upon before
planners moved onto construction, it could have
been integrated into the architectural design,
greatly simplifying the project. - The importance of communication.
- If the parties involved paid more attention to
their German counterparts, designers would have
known that more time was needed to debug the
system. - Had there been more communication between the
different design teams, there would have been a
better understanding of the complexity of the
system, and many of the design flaws could have
been corrected before it was assembled.