Title: Inner Triplet Cryogenics and Heat Transfer
1Inner Triplet Cryogenics and Heat Transfer
- LARP Collaboration Meeting Berkeley, CA
- April 25-28, 2006
2IR Cryogenics Studies Outline
- Task goals and milestones
- Task status toward these goals and milestones
- Plans for the remainder of FY06
- FY06 task budget status
- Preliminary FY07 technical plan and milestones
- Preliminary FY07 task budget request
3IR Cryo FY06 Task Goal
- Task goal To support an LHC luminosity upgrade,
investigate and compare 2 K inner triplet
cryogenic systems and coil temperatures for
single-bore quadrupole-first designs. Analytical
studies will also be conducted to investigate IR
quadrupole cryostat quench protection issues
related to stored energy, pipe sizes, and
material thicknesses.
4IR Cryo FY06 Task Milestones
- FY06 Q1 Establish and document a design
temperature profile for an upgraded IR. - Study possible LHC cryo system modifications to
determine how much additional temperature drop
can be gained for the IR. - Based on these results, arrive at a design heat
load. Iteration with magnet designers and
analysts may be necessary. - Portion the temperature drop appropriately within
the IR in preparation for parametric studies.
5IR Cryo Studies FY06 Task Milestones
- FY06 Q2 IR quad heat transfer parametric
studies using the design temperature profile,
including - Conductor cooling
- Heat exchanger design
- Pipe sizing
6IR Cryo Studies FY06 Milestones
- FY06 Q3
- IR quad cryostat quench protection studies
- Estimate maximum quadrupole quench pressures
based on sizes of cooling channels and piping - Calculate required material thicknesses based on
maximum quench pressure - IR triplet heat transfer parametric studies
- Expand on IR quadrupole parametric studies to
investigate heat transfer issues in the inner
triplet.
7IR Cryo Studies FY06 Milestones
- FY06 Q4 IR triplet quench protection studies
- Expand on IR quadrupole parametric studies to
investigate quench protection issues in the inner
triplet.
8IR Cryo Studies FY06 Q1 Milestone
- With input from CERN cryo personnel, an upgraded
IR design temperature profile was documented
(LARP-doc-100) (milestone completed). This
temperature profile - Assumes the inner triplet must be kept in He II
with a heat load of 1.2 kW (Mokhov and Rakhno). - Assumes a cold compressor upgrade, from 15 mbar
to 12 mbar. This makes available an additional
60 mK of temperature drop.
9IR Cryo Studies FY06 Q1 Milestone
- Assumes first stage cold compressors are moved
closer to the IRs, reducing the pressure-induced
temperature drops. - Allocates the largest DTs to potential
bottlenecks, keeping in mind the most
advantageous temperature range for He II heat
transport (1.8-2.0 K). - Maximum He II conductivity at approx. 1.8-2.0 K.
- Cold mass cooling channel sizes are limited.
- Crossover pipes from cold mass to HX are
potential bottlenecks due to high heat fluxes. - HX is a potential bottleneck, especially if only
a fraction of the wall is wetted for He II heat
transfer. This effect will depend on the final
HX configuration.
10IR Cryo Studies FY06 Q1 Milestone
11IR Cryo Studies FY06 Q2 Milestone
- From heat deposition calculations (Mokhov and
Rakhno), the Q1 non-IP end is the limiting
location for the inner triplet cryo.
12IR Cryo Studies FY06 Q2 Milestone
- Based on the design temperature profile,
parametric studies have been performed for
several cold mass characteristics - HX crossover pipe
- Longitudinal cooling channels in the cold mass
- Radial cooling channels in the yoke and collar
- Beam pipe annulus
13IR Cryo Studies FY06 Q2 Milestone
- Additional HX crossover pipes between the cold
masses and the heat exchanger are required to
minimize He II conduction lengths and heat flux
per pipe. - Seven HX crossover pipes are envisioned one
pipe at each end of every cold mass with the
exception of one pipe between Q2a and Q2b.
14IR Cryo Studies FY06 Q2 Milestone
- Comparison of current and upgraded Q1-Q2a
interconnects.
15IR Cryo Studies FY06 Q2 Milestone
- Calculated size of each HX crossover pipe.
16IR Cryo Studies FY06 Q2 Milestone
- Typical results of cold mass parametric study (Q1
non-IP end).
17IR Cryo Studies FY06 Q2 Milestone
- HX conceptual design is a shell and tube heat
exchanger (pressurized He II in tubes) and a
separate pumping line.
18IR Cryo Studies Addl FY06 Q2 Work
- Cryogenics of not only the inner triplet must be
considered when the luminosity is upgraded, but
also the cryogenics of the entire LHC. - Updated machine heat load estimates for
short-bunch and long-bunch luminosity upgrade
scenarios are being generated.
19IR Cryo Studies FY06 Q2 Milestone
- Milestone is not yet achieved.
- Documentation of parametric studies in progress.
- Documentation of machine heat load studies in
progress. - Documentation of HX conceptual design in
progress. - Detailed HX calculations and documentation
required, as is documentation of the estimated
coil temperature.
20IR Cryo Studies Remaining Milestones
- Work associated with the FY06 Q3 and Q4
milestones is not yet underway. - It is expected that the FY06 Q2 (quad heat
transfer studies) and FY06 Q3 milestones (triplet
heat transfer studies, quad quench protection)
will be completed in FY06. The FY06 Q4 milestone
(triplet quench protection) will likely not be
completed in FY06.
21IR Cryo Studies FY06 Budget
- Task labor budget 67k
- BNL 20k
- FNAL 47k
- At the end of FY06 Q2
- BNL has spent 21 of its labor budget
- FNAL has spent 38 of its labor budget
22IR Cryo Studies FY07 Plans
- Possible FY07 milestones
- FY07 Q1-Q2
- Triplet quench protection studies.
- Heat transfer parametric studies of other 2 K
systems, such as double-bore or dipole-first. - FY07 Q3-Q4
- Heat exchanger and internal absorber design
studies. - Heat transfer parametric studies of 4 K systems.
- Proposal for HX/absorber experimental work.
23IR Cryo Studies FY07 Budget
- Requested budget is identical to that of FY06.
24Temperature vs. longitudinal position at the Q1
non-IP end for a range of collar radial cooling
channel sizes.