Title: Measurement
1Measurement Verification Section
- Part 1 MV Overview
- MV in the Five Phases
- Part 2 Risk Assessment
- Risk Assessment and Allocation
- Part 3 FEMP M V Methods
- Methods and Applications
- Part 4 M V Plan Review
- Checklist
- Part 5 M V Case Studies
- Application of lessons
2Part 1 MV Overview
- Purpose of MV
- MV in the five phases
- Contractor responsibilities
- Owner responsibilities
3Purpose of MV
Purpose of MV
- Performance Contracting is an arrangement where
the exact benefits are only known afterwards - There is an element of risk related to the
uncertainty of the delivered benefit - MV quantifies the savings
- MV allocates risk between parties
- MV supports the guaranteed savings
4Savings
Purpose of MV
- ESPC can recognize two types of savings
- Energy Cost Savings
- Energy-Related Cost Savings
5Energy Cost Savings
Purpose of MV
- Reductions in energy use
- Reductions in peak demand
- Reductions in energy rates
- Shifting time-of-use to lower-cost periods
- Converting to less expensive fuels
- Self-generation (and cogeneration / CHP)
- Reduced water and other utility use
6Energy-Related Cost Savings
Purpose of MV
- Energy-related cost savings are primarily due to
reduced OM expenses - Parts labor costs
- Emergency repair costs
- Equipment replacement costs
- Cost savings must come from existing budgets or
it will be difficult to pay the ESCO!
7Super ESPC is Guaranteed Savings
Actual saving will fluctuate, but should always
be greater than the guaranteed amount
Actual Estimated Guaranteed
Savings
1 2 3 4 5 6 7 8 9 10 11 12 13
14 Contract Year
8Why You Need MV
Purpose of MV
- Savings are guaranteed, but actual savings
fluctuate every year - MV demonstrates guarantee is met
- MV identifies problems
- MV verifies continued success of projects
- What you dont measure, you cant manage (Jack
Welch, former GE CEO)
9MV During the Five Phases
10Phase 1 Planning
- What are project motivators?
- Improved comfort, better performance
- Reduced energy costs
- Reduced OM costs
- What does MV need to accomplish?
- Monitor equipment performance
- Find additional savings
- Improve OM
- Enforce guaranteed savings
11Owner Responsibilities
- Define project goals in terms of
- Necessary performance improvements
- Energy cost savings
- Energy-related cost savings
- Define MV requirements
- Total energy cost savings
- Equipment performance
- Long-term verification
- These need to be included in the RFP!
12Phase 2 Project Development
- Contractor Responsibilities
- Complete Risk Responsibility Matrix
- Develop MV Overview in Initial Proposal
- Explain and justify overview
- How will risks responsibilities be assigned?
- How will contractor prove performance?
- What will be measured?
- What will not?
13Responsibility Matrix
- The Risk Responsibility Matrix describes how
the contractor will address risk factors that
affect savings and project economics. These are
broadly characterized as - Financial and Economic
- Facility Usage and Operations
- Equipment Performance
- RR Matrix drives MV Overview
14MV Overview
- The MV Overview (a.k.a. Initial MV Plan) is
submitted as part of Initial Proposal. It is not
a complete plan, but - Describes intended approach
- Purposely lacks detail
- The MV Overview allows the Owner and the
contractor to develop a satisfactory MV Plan - The MV Overview drives the Detailed Energy Survey
15Owner Responsibilities
- Owner Responsibilities
- Discuss planned physical or operational site
changes with contractor - Provide energy use and rates to contractor
- Review RR Matrix, MV Overview and assumptions
- Provide critical comments and feedback
- Engage Project Facilitator and third-party support
16Phase 3 Negotiation and Award
- Contractor Responsibilities
- Modify Risk Responsibility Matrix
- Perform Detailed Energy Survey and document
baseline information - Finalize Site-Specific MV Plan
- Develop ECM Commissioning Approach
17Detailed Energy Survey
- MV Plan drives Detailed Energy Survey (DES)
activities - The Detailed Energy Survey defines the baseline
of the facility, which consists of - Energy use and cost history
- Equipment list and measured performance
- Factors that influence energy use
- Operations and maintenance costs
- If this information is not documented, it is
lost. It cannot be determined after
installation.
18Site-Specific MV Plan
- RR Matrix drives MV Plan
- The Site-Specific MV Plan includes
- What will be done (and when)
- How will performance be verified
- Who will conduct these activities (and when)
- How will savings be calculated
- How will baseline be adjusted to account for
varying conditions - OM reporting requirements for Owner
19Commissioning Approach
- ECM Commissioning (Cx) approach is not a complete
plan - Describes (generally) how each ECM will be
commissioned prior to acceptance
20Owner Responsibilities
- Review MV Plan and Cx Approach
- Provide critical comments and feedback
- Approve Site-Specific MV Plan and Cx Approach
- Participate in and witness DES activities
- Review DES baseline information
- Engage Project Facilitator and third-party
support
21Phase 4 Implementation
- Contractor Responsibilities
- Submit Commissioning Plan
- Commission measures
- Submit Commissioning Report and
Post-Installation Report
22Commissioning Plan Report
- Commissioning (Cx) is the process of ensuring
that systems are installed, tested, and capable
of meeting design intent - The Commissioning Plan defines start-up
procedures and functional performance tests for
each piece of equipment as well overall systems - The Commissioning Report documents the
commissioning activities and any issues that were
discovered and resolved
23Post-Installation Report
- The contractor submits the Post-Installation
Report after the project has been installed. It
includes - Project description
- List of installed equipment (as built)
- Performance measurements
- Expected savings for the first year
24Owner Responsibilities
- Witness MV and commissioning activities. Be
involved! - Approve Commissioning and Post-Installation
reports - Engage Project Facilitator support
25Phase 5 Performance Close-Out
- Contractor Responsibilities
- Provide agreed-upon performance-period services
- Perform required operations maintenance
- Submit Annual Reports
- Take corrective action (if needed)
- Annual savings reconciliation (if needed)
26Annual Reports
- The contractor submits Annual Reports to
demonstrate that savings have occurred. They
should include - Project description
- Performance measurements this year
- Realized savings for the year
- Comparison to the guaranteed amounts
- Reports should also contain
- Problems that need Owner attention
- Operations maintenance and repair replacement
activities conducted -
27Owner Responsibilities
- Contract administration
- Perform agreed-upon operations maintenance
- Submit proof of preventive maintenance
- Witness verification activities
- Review approve Annual Reports
- End of contract term
28Review and Discussion
- Actual savings from Super ESPC are only known
after project implementation - Savings guarantees are only as good as the MV
supporting them - The Owner sets the MV goals the ESCO implements
the plan
29Review Questions
- Why is MV needed?
- Who is responsible for MV?
- How are MV and commissioning different?
Click hereto go to MV Part 2