Title: Presentation of Progress Under Rural Development Programmes
1Presentation of Progress Under Rural
Development Programmes
2Major Schemes
- NREGA
- PMGSY
- SGSY
- Rural Drinking Water
- Indira Awas Yojana
- Rashtriya Swasthya Bima Yojana
- Mahamaya Awas Yojana
- Mahamaya Sarvjan Awas Yojana
- Ambedkar Vishesh Rozgar Yojana
- Vidhan Mandal Kshetriya Vikas Nidhi
- Biogas
- Community Halls In SC/ST Dominant Villages.
3Funding Pattern
4Funding Pattern
5Progress At A Glance Till Dec.-08
6Status Of Central Share Released Till 15-1-09
7NREGA
8(No Transcript)
9NREGS PROGRESS
Note Progress During 2006-07 and 2007-08
includes progress under SGRY also.
10NREGS PROGRESS
Note Progress During 2006-07 and 2007-08
includes progress under SGRY also.
11Reasons for higher Achievements New Initiatives
- Transfer of funds (from district) directly to
Gram Panchayats. - Better monitoring of fund flows and physical
progress through M.I.S./ field visits. - Eleven Schemes for work on the fields of
individual beneficiaries.
12New Works Suggested
- To help districts/blocks/GPs in formulation of
Annual Action Plan and selection of works under
NREGS following 11 G.O.s containing detail
instructions and model estimates have also been
issued on 31-10-2008- - Pisciculture Projects.
- Plantation of Medicinal Plants.
- Water Conservation Projects.
- Strengthening of infrastructure facilities for
livelihood. - Sericulture Projects.
- Watershed Management Projects.
- Plantation of Jatropha, and Karanj Plants.
- Land Development Projects.
- Horticulture Projects.
- Irrigation Projects.
- "Hariyali" Projects (Gully Plugging/Boulders,
Plantation Fodder)
13 Reasons for higher Achievements New
Initiatives (Contd.)
- .
- Bundelkhand Plantations an excellent
opportunity and work avenues for wage earners. - Rationalization of SoR.
- Institutionalized system of social audit.
- Training of staff.
- At village level creating a cadre of mates
through training.
14New Initiatives
- Nomination of D.Ms. as D.P.Cs
- Appointment of dedicated staff for NREGA through
Service Providers underway.
15Disciplinary Action Taken Against Departmental
Officers For Financial Irregularities/ Laxity In
Duties (During 15-05-2007 To 31-12-2008)
16Cont
- Better grievance redressal Launch of Helpline
Call Centre was visited by the Secretary,
Ministry of Rural Development, GoI - this
initiative has been appreciated by the GoI. - State level help line nos.
- 95522-2231017
- 95522- 4055999
- Mobile-9793230999
- Total Calls Received till 31-12-2008 - 9574
17Sectoral Breakup of Works Under NREGS During
2008-09 ( Figures in brackets are of Previous
Year)
Land Dev. (5 last year )
Ponds Const. (19 last year)
Irrigation (3 last year)
M I Works (3 last year)
Roads ( 46 last year)
Drought Proofing (4 last year)
Water Conservation (15 last year)
Flood Control (5 last year)
18Issues
- Slow and inadequate release of funds by Central
Govt.
19PRADHAN MANTRI GRAM SADAK YOJANA
20Objectives of PMGSY
- AS ORIGINALY STIPULATED
- To provide all weather connectivity to all 1000
population habitations by year 2005. - To provide all weather connectivity to all
500-999 population habitations by year 2007. - UNDER BHARAT NIRMAN
- To saturate all 1000 population habitations with
all weather roads by the year 2009. - To Upgrade/ Renew through routes Length by the
year 2009
20
21Salient Features of PMGSY
- PMGSY initiated in the year- 2000-01
- 100 Centrally Sponsored Scheme.
- Supplemental Assistance(through Govt Of India)
From the World Bank in Chosen Districts (35 in
Tranche -1 23 in Tranche -2,13 in Tranche-3). - Only village roads and Other District Roads in
the PMGSY ambit-Major District Roads, State
Highways and National Highways not covered in
PMGSY
21
22Implementation Of Scheme
- Rural Development Department is Administrative
Agency. - Uttar Pradesh Rural Road Development Agency
created for monitoring the scheme- an essential
condition by Govt. Of India to channelize the
flow of funds to state. - UPRRDA headed by Commissioner , Rural Development
designated as Chief Executive Officer. - State Public Works Department (PWD) executing
agency in forty district, Rural Engineering
Services (RES) in remaining thirty districts. - Payment of centage charges _at_6.875 of works
executed permitted to autonomous Government
Agencies viz. UPRNN, UP Bridge corporation, NPCC,
NBCC etc. New agencies asked to prepare fresh
DPRs in identified districts. - Principal Secretary ,Rural Development is
chairman, Executive Committee comprising of
Principal Secretary , PWD and Principal
Secretary, RES amongst others.
22
23YEAR WISE PROGRESS OVERVIEW
24PHASEWISE CUMULATIVE FINANCIAL PROGRESS
25HABITATION SATURATION STATUS Contd..
26YEAR WISE BREAKUP OF PROPOSED TARGETS UNDER
BHARAT NIRMAN PROGRAMME (AS PER CNCPL DATA)
- Total unconnected Habitations of
1000population 10898 - (At the start of
PMGSY)- - Habitations linked/Sanctioned till 31st July 08-
10777 - PMGSY- 7406
- Other schemes- 3371
- No. of habitations remained Unconnected/Unsanction
ed on 08th Jan,09- 121 - (A) Year Wise Targets (New Connectivity )
27(B) Upgradation of Through Routes
- Total Length of Through Routes (Kms.) - 28523
- Target for upgradation(Kms.)- 17114(60 of the
Total)
28SATURATION STATUS
- All the 1000 population habitations have been
connected in 25 districts. - Another 24 districts have only 1-5 habitations of
1000 population category to be linked with
roads. - 121 no of 1000 population habitations could not
be taken up because of major bridge requirement
or River Belt or Forest Land or Land Dispute. - PIUs asked to prepare DPRs for these 121
Habitations also identifying the requirement of
Long Bridges . - Land dispute cases to be resolved through help of
District administration.
29Action plan year 2008-09
- Spill-over of previous year 3546 crores
- New Sanctiones (Phase 7--11th June,08) 0237
crores - New Sanctiones (Phase 7--22nd Dec,08) 0802
crores - Total sanctioned works in hand 4585 crores
- Public Works Department has set a target of 1500
crores for 2008-09 . - Rural Engineering Services likely to achieve 1000
crores in 2008-09.
30PROPOSALS FOR PHASE EIGHT SANCTION EXPECTED
SHORTLY
31- New Initiatives
- Release Of CCL Streamlined- Release and Demand of
CCL are made on Line CCL release on the same
day. - CCL demand computed against pending bills.
Parking of unutilized funds with PIUs minimized. - Payment of centage charges _at_6.875 of works
executed permitted to autonomous Government
Agencies viz. UPRNN, UP Bridge corporation, NPCC,
NBCC etc. - Induction of new agencies expected to improve the
performance. - Training of staff for adoption of e-payment
procedure of contractors bills undertaken.
31
32Quality Monitoring Under PMGSY
- Three tier quality control.
- First tier is the Superintending Engineers and
Chief Engineers of the executing agencies. - Second Tier is State Quality Monitors(SQMs) who
are retired Superintending Engineers and Chief
Engineers experienced in Road construction. In
case of World Bank funded projects, Technical
Examiner(TE) Ms SMEC India Limited engaged for
this purpose. - Third tier comprises of National Quality Monitors
(NQMs) chosen by Govt of India who are
essentially from outside the state. - Observations of SQMs or NQMs have to be acted
upon and Action Taken Reports (ATRs) submitted by
PIUs.
32
33SGSY
34S.G.S.Y.
35S.G.S.Y. (Progress)
36S.G.S.Y.- Sector-wise Progress Till Dec.-08
37Sector-wise Coverage of Beneficiaries Under SGSY
Till Dec.-08
Secondary Sector -12
Tertiary Sector-10
Primary Sector-78
38New Initiatives taken Under SGSY Training Cum
Skill Development Placement
- Objective to train one member of each BPL
family. - 40 reputed Organization already selected for
providing training for example- Larsen Tubro,
NIIT, Federal Security and Fire Services, G4s
Security service etc. - Selection of more reputed Organization under
progress. - Major trades identified for training and
capacity building-
- Water shed development.
- Nursery raising, Horticulture,
- Gardening.
- Food processing.
- Advance agriculture
- practices.
- I.T.
- B.P.O
- Security Services
- House Keeping Cookery.
- Construction sector.
- Management.
- Health Education Sector.
- Para Veterinary.
- Media Management.
- Digital Cartography.
- Beautician .
- Boring Handpump repair.
- Mobile repairing
39Cont
- 280 Saras Haat will be established this year.
- Proposal is also under consideration to dovetail
SHGs products with Mid-Day Meal scheme.
40Indira Awas Yojana
41Mahamaya Awas Yojana
42Mahamaya Sarvjan Awas Yojana
43ISSUES
- Annual coverage IAY - 2.54 lakh
- MAY - 0.85 lakh
- MSAY -
0.25 lakh - Grand Total - 3.64
lakh - GOI may be requested to have special allocation
to the State under IAY to cover all the 43.71
lakh homeless BPL families in time bound manner.
44Rural Water Supply
45Physical Progress ( no.)
46Thanks