Title: Monthly Status Report ePayroll


1
Monthly Status Reporte-Payroll
  • Ona Elliott, Project Manager
  • 256-544-7342
  • Month Ending March 2004

2
Table of Contents
  • Summary Status
  • Accomplishments
  • Activities in Progress
  • Project Key Schedule/Activities Metrics
  • Cost Estimate
  • Top 5 Issues
  • Backup

3
Summary Status
Interface Priority Categories - (1) critical
for payroll processing, (2) critical for business
operations, and (3) necessary but not critical
for business continuity
4

Accomplishments
  • Training
  • All centers have completed FPPS security training
  • 75 complete with all Servicing Personnel Office
    (SPO) and Requesting Office (RO) training
  • NASA Environments
  • Completed development of WEBTADs time and
    attendance interface
  • Completed delivery to DOI of time and attendance
    interface with ongoing deliveries occurring every
    pay period
  • DOI/NBC Environments
  • DOI/NBC has provided NASA with a preliminary
    Labor Cost file
  • DOI/NBC has successfully completed a pay calc
    with NASA time and attendance data
  • Communications
  • February 23, 2004 Meeting With e-Payroll
    Steering Committee
  • Obtained agreement to proceed with e-Payroll
    implementation and formally move from Project
    Formulation to Project Execution with a Go-Live
    date of August 8, 2004
  • Established Authority to Proceed (ATP)
    checkpoints at key milestones in the project
    schedule
  • Established plan to engage with CIO and Program
    Management to establish a plan of resolution for
    adequate and timely funding of NASAs e-Payroll
    implementation.


5
Activities In Progress
  • Data Conversion Activities
  • NPPS to FPPS Data Conversion and Clean-up
  • Production ready Data Mapping and Clean-up 90
    complete
  • NPPS Historical Data Conversion (FPPS Data Mart)
  • 6 years of Payroll data and all HR data
    (approximately 20 years) to be converted
  • Data mapping for NPPS history files approximately
    95 complete
  • Development for historical data conversion 90
    complete
  • Interface and Reports Development
  • 37 Interface Control Documents (ICDs) Under
    Development
  • ICDs document NPPS to FPPS Data mart mapping for
    Agency, Common, and Center interface development
    activities
  • ICDs approximately 95 complete
  • Received buy in for all developments for ICDs
    that have been completed and agreement on August
    Implementation
  • Targeted for completion by end of March 2004
  • 37 Agency Report Control Documents (RCDs) Under
    Development
  • IPO will provide standard RCDs to be used to
    capture reporting requirements
  • RCDs approximately 65 complete
  • Targeted for completion by end of April 2004

6
Activities In Progress (cont.)
  • Simulated Parallel Test One Preparation
  • Scheduled one-day workshop for functional test
    planning (03/17/04)
  • Scheduling one-on-one sessions with Centers for
    review of labor cost file produced from parallel
    test
  • Quality Management
  • IVV Requirement Reviews
  • Scheduled to be complete April 30, 2004
  • Established onsite review contact within
    e-Payroll management office
  • Non-Advocate Review
  • Review is preliminary scheduled for April 2004
  • Project documentation has been provided to
    SMO/NAR contact

7
Project Key Schedule Activities Metrics
8
e-Payroll Cost Estimate
9
Key e-Payroll Issues
10
Reference / Backup
BACKUP
11
e-Payroll Budget Information
12
e-Payroll Budget Information (cont.)
13
e-Payroll Budget Information (cont.)
  • Total Agency Cost 8,441K
  • Estimated Cost To Date (2,339K)
  • Amount Received To Date 2,479K
  • ----------
  • Balance 5,962K
  • Project Reserve Funding Allocation
  • Possible Increase in DOI estimates for CR
    development
  • Post Implementation Activities
  • Implementation Contingency Plans