TNUoS Charges Onshore Methodology Potential application offshore

1 / 28
About This Presentation
Title:

TNUoS Charges Onshore Methodology Potential application offshore

Description:

A guide to the governance, principles and mechanics behind Transmission Use ... Physical characteristics of typical' (BEMA figures) 132kV, 800mm2, 203MW, 60km ... – PowerPoint PPT presentation

Number of Views:135
Avg rating:3.0/5.0
Slides: 29
Provided by: patric213

less

Transcript and Presenter's Notes

Title: TNUoS Charges Onshore Methodology Potential application offshore


1
TNUoS Charges- Onshore Methodology- Potential
application offshore
  • January 2007

2
Objectives
  • A guide to the governance, principles and
    mechanics behind Transmission Use of System
    charging
  • National Grids Transmission Licence obligations
  • Overview of TNUoS tariffs onshore
  • Principles
  • Locational element
  • Residual element
  • Design Variation Discount proposal
  • Calculation of illustrative example of tariffs

3
Transmission Licence conditions
  • The Transmission Licence places legal obligations
    upon the licence holders
  • C5 - TNUoS charges must meet the relevant
    licence objectives
  • Facilitating competition
  • Reflect costs incurred
  • Take account of developments in the transmission
    business
  • Methodology modification process
  • C7 - Prohibits discrimination between classes of
    User
  • CUSC 3.9 - Requires Users to pay TNUoS charges in
    accordance with the Statement of Use of System
    Charges

4
Principles of TNUoS Charges
  • Method of recovering cost of building, operating
    and maintaining the electricity transmission
    network
  • Allowed revenue determined by Transmission Owner
    price controls every five years
  • Efficient, economic signals are provided to Users
    when services are priced to reflect the
    incremental cost of supplying them
  • Charges reflect the impact users at different
    locations have on TO costs from a unit increase/
    decrease in their network use
  • System is designed to comply with the System
    Security and Quality of Supply Standard
  • Based upon peak demand

5
Charging Objectives
  • In addition to Licence Condition C5, further
    objectives of the charging methodology include
    the provision of
  • Transparency
  • Simplicity
  • Predictability
  • Stability
  • Reproducibility

6
Transport Model
7
DCLF
  • TNUoS tariff has two elements
  • Locationally varying element
  • derived from ICRP DCLF
  • Non locationally varying element
  • residual revenue recovery
  • ICRP DCLF Investment Cost Related Pricing DC
    Load Flow model

8
DCLF ICRP Transport Model
  • Calculates marginal costs of investment in the
    transmission system which would be required as a
    consequence of an increase in demand or
    generation at each node
  • Measures investment costs in terms of MWkm,
    i.e. if 1 MW was injected on the system at a node
    what would be the net change in units of
    transmission system kilometres

9
Transport Model Inputs
  • Demand is modelled at winter peak values
    (consistent with SQSS and therefore investment)
  • Contracted generation is scaled to match demand
  • Transmission circuit data
  • Type (OHL/ Cable)
  • Voltage
  • Length
  • Impedance and reactance
  • Expansion factors

10
Expansion Factors
  • A voltage and cable/OHL specific coefficient
    representing relative costs of all conductor
    mediums as compared to 400kV OHL
  • Offshore Expansion Factors yet to be defined
  • Typically based on averaged on historic data and
    a broad range of projects dont exist for
    offshore
  • E.g. England Wales
  • 400kV OHL - 1.00
  • 275kV OHL - 1.74
  • 132kv Cable - 27.85

11
DCLF Transport Model Output
  • Marginal cost for each node is found by running a
    DC Load Flow model and the total MWkm of GB
    transmission system (winter peak) is found
  • 1MW is added at each node, and removed from the
    slack node
  • The differential in total MWkm is found
  • Can be both positive and negative

12
Tariff Model
13
Demand Generation Zones
  • Demand zones represent the boundaries of the DNO
    networks
  • Generation zoned following the criteria
  • Maximum tariff spread of /- 1/kW
  • Geographically and electrically proximate
  • Minimum number of zones possible
  • Reviewed at price control other than in
    exceptional circumstances
  • Where possible, minimal zonal boundary changes
    should be made
  • For each demand and generation zone, the
    flow-weighted average for marginal kms is found

14
Tariff calculation
  • Zonal marginal km converted to an initial tariff
    by multiplying by Expansion Constant and
    Locational Security Factor
  • The Expansion Constant is the annuitised value of
    the infrastructure required to transport 1MW over
    1km
  • Derived from the projected cost of 400kV OHL at
    the beginning of each price control
  • Using manufacturers budgetary prices, contracts
    let, lead tenders
  • Uses a range of OHL types, weighted by recent
    usage
  • Maintenance
  • Inflated annually by RPI (10.07 2006/07)

15
Global Locational Security Factor
  • A network compliant with SQSS security standards
    is secure against all feasible double and single
    circuit faults
  • A copy of the DCLF transport model is used that,
    in addition, simulates all such faults
  • The worse case fault is found for each node to
    determine the maximum increase in marginal cost
  • The Locational Security Factor is the best fit
    ratio of total secured marginal kms and unsecured
    marginal kms
  • Reviewed at each price control
  • Currently 1.8 (2001 2006)

16
Calculation of Locational Security Factor
17
Tariff Calculations Re-referencing
  • To ensure that the correct ratio of recovery is
    made from generation and demand, all zones are
    adjusted or re-referenced
  • The Authority has determined this as 7327
    (demand generation)
  • A single additive constant is calculated which is
    then added to all zonal marginal km
  • Differentials between zones are maintained

18
Tariff Calculations Residual tariff
  • To ensure that the correct total permitted TNUoS
    revenue is recovered a residual tariff is added
    to all demand and generation zones (7327 ratio)
  • Demand 12.463/kW
  • Generation 3.531/kW
  • Whilst this adjusts the total revenue recovered
    from demand and generation, the cost-reflective
    differentials between zones are maintained

19
TNUoS Methodology Modification Proposal
SQSS design variations amendment
20
GB SQSS and Current TNUoS Methodology
  • GB SQSS includes criteria for variations to
    connection designs higher or lower than the
    specified standard
  • Providing this does not
  • reduce the security of the MITS below the minimum
    planning criteria specified in the standard
  • impact on other customers in terms of investment,
    operational costs or security and quality of
    supply
  • compromise Transmission Licence obligations
  • Customers must accept uncompensated access
    restrictions in order to avoid additional
    operational costs to other customers
  • Current TNUoS charging methodology does not
    provide a mechanism by which investment savings
    are passed through

21
Modification Proposal
  • Consists of both
  • Substation discount
  • Locational discount
  • Conclusions report submitted 18th November
  • Impact assessment initiated by Authority
  • Responses by 26th Jan
  • Decision by Feb 16th
  • For implementation with 2007/08 tariffs

22
Substation Discount
  • To reflect the savings associated with the
    reduced substation asset requirements for on
    shore single circuit connection design
  • Propose the following discounts to the residual
    tariff

23
Circuit Discount
  • Provides an economic signal equal to the cost
    saving of an entire second circuit
  • Circuit discount (/kW)
  • Circuit marginal length (km) Exp constant
    (/MWkm) 1000

24
Tariff Illustrative Examples
25
Indicative tariff examples
  • Indicative charges for 3 offshore locations with
    2 connection options each
  • The Wash
  • Lincolnshire
  • Thames Estuary
  • All connected by a 60km, 132kV AC submarine cable
  • Assumptions
  • Proposed offshore SQSS accepted
  • Charging methodology onshore is applied offshore
  • No onshore connection circuits
  • SQSS Design Variation Amendment non-veto and
    applied to offshore generation connections
  • 2007/08 tariff levels

26
Determining Expansion Factors
  • Physical characteristics of typical (BEMA
    figures)
  • 132kV, 800mm2, 203MW, 60km
  • 500k/km (310k supply 190k lay and bury)
  • Unit cost 500k/203 2460/MWkm
  • Using an 8.43 annuity factor 207.6/MWkm /yr
  • 400kV OHL Expansion Constant 10.07
  • Expansion Factor 207.6/10.07 20.6

27
Determining Design Variation Discount
  • Substation Discount
  • 132kV 1.05/kW
  • Circuit Discount
  • Circuit marginal length expansion constant /
    1000
  • (20.6 60) 10.07 / 1000
  • 12.45/kW
  • Total Discount
  • 12.45 1.05 13.50/kW

28
Example
Write a Comment
User Comments (0)