PMG Agenda November 16, 2000 - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

PMG Agenda November 16, 2000

Description:

QC Data on all available ( not perfect, but all light ... Gas Chromatograph being brought up. Forward Muon detectors. Installing & reading out part of it ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 12
Provided by: harry174
Category:

less

Transcript and Presenter's Notes

Title: PMG Agenda November 16, 2000


1
PMG AgendaNovember 16, 2000
  • Overview (Weerts)
  • Detector status
  • Reportable milestones
  • Summary

TODAY
SMT-S going on truck
SMT-S going between cryostats
2
Status Overview SMT
  • Silicon
  • Production
  • DONE
  • South silicon detector (SMT-S)
  • Move Installation today
  • North silicon (SMT-N)
  • All barrels and disks complete
  • Assembly in support cylinder starting
  • Start cabling before Thanksgiving
  • Ready for DAB at beginning Dec 12
  • H-disks ( need 4)
  • 3 H disks ready
  • 10 test
  • Continuing to be useful/ learning
  • Sparsification problems.
  • Put H disk in

3
(No Transcript)
4
Fiber Tracker Status - Waveguides
  • Waveguide Production and QC continue
  • Installation
  • South
  • All installed
  • Replacements done
  • Different fixes tried
  • QC Data on all available ( not perfect, but all
    light transmissions within 10)
  • Lesson minimize handling of waveguides
  • North Started
  • Installed CPS North started on CFT
  • First QC data look good
  • QC in real-time with installation

5
Fiber Tracker Status
  • VLPC Cassettes
  • Continues
  • Electronics availability a problem
  • WG QC vs. Cassette Charact.

Goal (99) done by Feb 15, 2001
6
Status Overview
  • Central Muons (94 PDTs)
  • Commissioning continues
  • Completing electronics installation
  • Reading out part of each layer L1 trigger
  • Gas Chromatograph being brought up
  • Forward Muon detectors
  • Installing reading out part of it

Installation status
Trusses (north south) moving into collision
hall this week.
7
Status Overview
  • Trigger DAQ
  • Commissioning is still okay, but..
  • Final hardware arrival is a worry
  • L2 VME-Alpha boards still a concern. NO working
    board yet. Now have 25. Not good
  • Three approaches
  • Fix existing boards _at_ FNAL, UIC UoM
  • Another production run ( company visit two weeks
    ago). Have parts for 17 boards.
  • New design completely..
  • L3 board production concern vendor visit
  • Technical manpower an issue Varelas, Johns _at_FNAL
    starting December
  • Online
  • In use at low rate, not on critical path
  • Commissioning workshop going on today goal is
    to read out crate of every detector.

8
Status Overview Electronics
  • Electronics
  • Calorimeter
  • Preamp installation/commissioning underway (10k
    installed, 12 PS ready, cooling installed)
  • BLS has vendor delays
  • Motherboard 1250/500/165
  • need/bare/stuffed
  • Daughter cards 5000/3750/950
  • Daughter card 300/week vendor (end Jan. 01
    complete)
  • CC is cold and filled with liquid
  • Read out 4500 channels last night ( 2 of 4 CC
    quadrants) about 10 of all channels
  • Muon
  • Done

9
Status Overview Electronics
  • Tracking Electronics
  • Si Interface Card
  • 160 pc production order released
  • 15 boards in hand
  • 2 tested so far no significant problems
  • Testing _at_ KSU and FNAL
  • Analog Front End boards
  • Released production start for PCB
  • Noise with MCM at 30fC, need 5fC
  • Goal is to release production on Nov 29 and have
    boards in December
  • MCM going
  • Produced 100 projected rate 25/day Need
    1900.
  • Company wants more money holding boards hostage
    with Business section price increase 70K
  • Adapter card
  • 34 with new design at FNAL
  • Power supplies
  • VICOR current schedule Dec-Jan
  • Some power supplies coming in earlier ( still
    January)

Re-arrange this
10
Installation
  • Progressing well.
  • Shield wall is down
  • Trusses (north south) are ready for move into
    collision hall (complete this week)
  • B layer muons to be installed
  • SMT-S going in as we speak
  • Mechanical installation going well

11
Summary
  • Concerns
  • NOT Silicon anymore
  • Installation lots of activity/m2 are careful
  • Electronics delays are THE concern for realistic
    commissioning
  • Vendor delays, parts availability
  • Willing to spend to fix if possible
  • Trigger falling clearly behind
Write a Comment
User Comments (0)
About PowerShow.com