Designing a Bulk Sodium Hypochlorite System - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Designing a Bulk Sodium Hypochlorite System

Description:

Eliminate Problems from Any Bleach Gassing. Eliminate Calcium Carbonate Buildup ... Information Sources for Bleach. Chlorine Institute Pamphlet 96. AWWA ... – PowerPoint PPT presentation

Number of Views:1532
Avg rating:3.0/5.0
Slides: 33
Provided by: patrick61
Category:

less

Transcript and Presenter's Notes

Title: Designing a Bulk Sodium Hypochlorite System


1
Designing a Bulk Sodium Hypochlorite System
  • Presented by Patrick H. Allman III
  • General Manager
  • Odyssey Manufacturing Co.

2
Disinfection Options June 1999
3
Disinfection Options June 2003
4
Disinfection Options June 2005
5
Sodium Hypochlorite
  • Bleach
  • Liquid Bleach
  • Liquid Chlorine
  • Soda Bleach Liquor
  • Chlorine

6
CHEMICAL FORMULA
  • NaOCl

7
Manufacturing Process
  • 2NaOH Cl2 NaOCl H20 Heat

8
Properties of Sodium Hypochlorite
  • Mildly Corrosive
  • Has Free Sodium Hydroxide (Caustic Soda)
  • pH12.5 to 13
  • Pale Yellow Solution, 12.5 By Volume
  • Non-Flammable
  • Incompatible with Many Other Chemicals
  • Relatively Short Shelf Life - Contaminants, Heat
    And UV Cause Decomposition

9
Contrary to Whites Handbook of Chlorination
  • One Gallon of 120 GPL or 12 Trade Percent
  • Equals
  • 1 lb of Cl gas

10
BLEACH DEGRADATION
  • Primary
  • 3NaOCl 2NaCl NaClO3 (Sodium Chlorate)
  • Secondary
  • 2NaOCl 2NaCl O2 (Gassing)
  • Factors
  • Heat
  • UV (e.g., Sunlight)
  • Impurities (Primarily Heavy Metals)
  • Strength (Rate K (OCl-2

11
(No Transcript)
12
(No Transcript)
13
Sodium Hypochlorite Degradation Average
Manufacturer _at_ 70 Degrees F
  • Time of Manufacture - 12.5 Trade Percent
  • 2 Days Later 12.43 Trade Percent
  • 7 Days Later 12.25 Trade Percent
  • 14 Days Later 12.01 Trade Percent
  • 21 Days Later 11.78 Trade Percent
  • 28 Days Later 11.55 Trade Percent
  • 35 Days Later 11.34 Trade Percent

14
Sodium Hypochlorite Degradation Average
Manufacturer _at_ 80 Degrees F
  • Time of Manufacture - 12.5 Trade Percent
  • 2 Days Later 12.34 Trade Percent
  • 7 Days Later 11.96 Trade Percent
  • 14 Days Later 11.47 Trade Percent
  • 21 Days Later 11.01 Trade Percent
  • 28 Days Later 10.59 Trade Percent
  • 35 Days Later 10.21 Trade Percent

15
Use of Pilot or Temporary Systems
  • To Maintain Continuous Disinfection During
    Conversion Construction
  • To size pumps and bulk storage tanks
  • To Determine Finished Water Quality
  • To Test different types of Equipment
  • Familiarize Operations Personnel with Sodium
    Hypochlorite
  • Verify Operations in Unusual Situations

16
Sodium Hypochlorite System Design
  • Delivery
  • Bulk Storage
  • Chemical Feed Equipment
  • Piping

17
Delivery to End-User
  • Bulk Delivery in 5,000-gallon tanker truck
  • Poured from Small Delivery 26 Flat-Bed Truck
    w/installed HDLPE totes or tanks
  • 300-gallon totes (forklift)
  • 55 gallon drums
  • 15, 30 gallon totes
  • 2.5 gallon jugs

18
Bulk Delivery by Tanker Truck
FRP Tanker Trailer
19
Bulk Delivery Site Should Have . . .
  • 2 Supported Male Connection w/Cap
  • Bag Filter 1 micron
  • Safety Shower/Eye Wash/Running Water
  • Security/Lights
  • Hook Up Protection / Labeled Lines
  • Proper Venting for Blow Off
  • Catch Bucket
  • Accessible Roadway and Turn Around

20
Fill Line
  • Air Pressure 15 to 25 psi
  • Trucks Carry Up to 60 Hose
  • Long Length Consider Upsizing to 3
  • Length Proportional to Offload Time
  • Maximum Length 200
  • Proper supports 45 Degree Down
  • Keep Line Vented

21
Bulk Storage Tanks
  • Location Covered vs. Non-Covered / Other
    Chemicals On-site
  • Air Conditioning Storage Spaces
  • Dilution of Stored Material Use Soft Water
  • Type (FRP vs. Bulk)
  • Size or Volume and Number (10 to 40 days)
  • Use of Day Tanks (F.S. 62-555)
  • Measuring Daily Usage (F.S. 62-555)
  • Tie Downs

22
Storage Tank Fittings
  • Vents (2 or 3) Use Vinyl Bug Screen
  • Drains Minimize of Tank Penetrations
  • Fill Line Fill from Top not Side or Bottom
  • Overflow Line Maximize Use of Tank
  • Sight glasses Type/Operational Necessity
  • Tanks Squat - Flexible Connection at Bottom
  • Feed Line - Pulling Out of the Top or Bottom
  • Bottom Fittings Types/Titanium is only
    acceptable Metal
  • Gaskets Viton Only No EPDM

23
Containment
  • Requirements Florida Statues/RQ
  • HDLPE Tubs
  • Poured Wall / Concrete Block Wall
  • Coatings
  • Wall Penetrations

24
Types of Piping
  • Schedule 80 PVC Most Commonly Used
  • Schedule 80 CPVC Plasticization
  • Schedule 40 Should Not Be Used
  • Kynar Expensive/Workmanship Issues
  • Carbon Steel Lined with Teflon or Kynar
    Typically used in Power Plants Beware of Sizing
    Issues

25
PVC Applications Socket Welding vs. Threaded
Connections
  • Minimize the Use of Threaded Connections
  • Use Stainless Steel Re-inforced Fittings on
    Threaded Joints When Possible Pump Discharge
    Fittings
  • If you must use a threaded connection, two wraps
    of Teflon Tape only
  • Use proper glue procedure 45-Degree Bevel,
    Debur, Clean/Prime, and Glue Each End.
  • Use proper Glue
  • IPS WELDON CPVC 724 24 to 48 hrs setup time
    (grey)
  • IPS EZ WELDON WET R DRY PVC 725 10 minutes
    under low pressure (blue)

26
Valves
  • Use the same model of Valve throughout the entire
    project Standardize!
  • True Union with Viton o-rings No EPDM
  • Bleed Hole for Pressure Buildup
  • Socket Weld Ends, No Threaded Connections

27
Piping to Chemical Feed Equipment
  • Purpose Minimize Off-Gassing
  • Pipe Sizing Optimize velocity
  • Minimize Length Maximum 50
  • Stack Vents/Sightglasses Carry Off Gases
  • Minimize Bends Keep Gases in Solution
  • Use of Flexible Piping/Tubing
  • Eliminate High Spots Piping Pitch
  • Use of Strainers Catch PVC shavings

28
Chemical Feed Equipment
  • Eductors vs. Positive Displacement Pumps
  • PD Pumps Peristaltic vs. Diaphragm
  • Pump Skids vs. Wall /Floor Mounting
  • Height of Equipment Suction Lift Issues
  • Degasification Valves When To Use
  • Vapor Lock Issues Bleed Valve or Vent
  • Control Issues Flow Meters / 4-20 ma
  • 99 of Most Operational Problems Come from
    Over-sizing Pumps!

29
Chemical Injection Piping
  • Proper Sizing of Pipe Minimize Off-gassing and
    Provide Precision Control of Feed Rate
  • Backpressure Valves at End of Pipe Improve Feed
    Rate Control
  • Maximum Length of Injection Point 500
  • Turnover Time Less than 4 hours
  • Use of Solution or Carry Water
  • Design of Injection Points
  • Mixing Issues
  • Minimizing Calcification/Scaling

30
Water Quality Issues
  • pH Boost - Typically .3 to .4 Units (.1 with
    OSG)
  • THMs Typically slight reduction (from Chlorine
    Gas)
  • Bromates Can Be Problematic with Ozone and Some
    Salt Sources (OSG) Ensure Quality Supplier
  • Chlorates May Be Regulated in the Future
    Ensure Quality Supplier
  • Chlorides/Sodium Ensure Quality Supplier
  • Alga Control Bulk Strength as effective as
    Chlorine Gas
  • Chloramine Formation May be slightly more
    effective than Chlorine Gas because of pH shift

31
SYSTEM DESIGN SUMMARY
  • Proper Engineering Design Essential To
  • Eliminate Problems from Any Bleach Gassing
  • Eliminate Calcium Carbonate Buildup
  • Minimize Product Degradation
  • Improve Life of Equipment
  • Minimize Maintenance
  • Ensure No Startup Problems
  • Eliminate Problems from Using a Corrosive
    Material

32
Information Sources for Bleach
  • Chlorine Institute Pamphlet 96
  • AWWA Standard B300-99
  • ANSI/NSF Standard 60
  • AWWA Reference Library
  • Material Safety Data Sheet (MSDS)
  • Sodium Hypochlorite Manufacturer
  • Equipment Fabricators (e.g. Pump Skids)
Write a Comment
User Comments (0)
About PowerShow.com