Bushing power transformer - PowerPoint PPT Presentation

About This Presentation
Title:

Bushing power transformer

Description:

Bushing power transformer – PowerPoint PPT presentation

Number of Views:3344
Slides: 44
Provided by: intiw

less

Transcript and Presenter's Notes

Title: Bushing power transformer


1
PRESENTATION ON BUSHINGS
2
Topics to be covered
  • What is a bushing
  • Types of bushings
  • Salient design features
  • Testing of bushings
  • Factors affecting bushings
  • Causes for failure of bushings
  • Dos and donts on bushings

3
Bushing
  • Bushing is defined as a structure carrying one or
    several conductors through a partition such as a
    wall or tank etc. and insulating it or them
    therefrom
  • A bushing has to provide
  • Electrical insulation to the conductor for the
    working voltage and for various over voltages,
    which occur in service.
  • Mechanical support against various Mechanical
    forces.

4
TYPES OF BUSHINGS 1.1 Application i) Alternator
bushing ii) Transformer bushing iii) Bushings
for switch gear iv) Wall bushing or roof
bushing v) Cable end and joint box bushing 1.2
Application i) Indoor type ii) Outdoor type
5
TYPES OF BUSHINGS
  • 2.1 Type of Bushing
  • i) Stem type
  • ii) Pull-through type
  • 2.2 Type of Bushings
  • i) Condenser core type
  • ii) Non-condenser core type (Hollow
    Porcelain type)
  • iii) Gas filled bushing
  • iv) Solid Bushing
  • Solid Ceramic Bushing
  • Epoxy Bushing

6
  • TYPES OF BUSHINGS
  • 3. Type of insulation used in manufacturing
    Condenser Bushing
  • i) Synthetic Resin Bonded Paper (SRBP)
  • Oil filled
  • Compound filled
  • ii) Oil Impregnated Paper (OIP)
  • iii) Resin impregnated Paper (RIP)

7
(No Transcript)
8
(No Transcript)
9
800 kV OIP Condenser Bushing
10
MAJOR PARTS OF BUSHING
Top Cap
Top Porcelain
Flange
Bottom Porcelain
11
Major Parts of Bushing
12
CREEPAGE DISTANCE
  • The shortest distance along the contour of
    the external insulating surface between the
    metal parts which normally have the operating
    voltage between them.
  • Lightly polluted atmosphere
  • Medium polluted atmosphere
  • Heavily polluted atmosphere
  • Very heavily polluted atmosphere

13

14
Nominal Specific Creepage Distance
Level I Light 16 mm/kV
Level II Medium 20 mm/kV
Level III Heavy 25 mm/kV
Level IV Very Heavy 31 mm/kV
15
Salient Design features
  • Electrostatic Field Controlled design of
    Condenser Core by Computer
  • Suitable for Operation under heavily polluted
    atmosphere
  • Reliable, relatively easy erection and
    practically maintenance free.
  • Better Dielectric Strength and Partial Discharge
    free up to Working Voltage
  • Space for mounting of Ring Type Current
    Transformer

16
Salient Design Features(Contd)
  • Self Earthing Test Tap for measurement of Tan
    Delta and Capacitance at site.
  • Environmental friendly.
  • Bushings for special applications can be designed
    and supplied to suit clients specifications.

17
Manufacturing Requriements
  • Dust free pressurized winding chamber
  • Winding Machines
  • Oil Treatment Plants for oil processing
  • Process Plants for Vacuum Impregnation at very
    fine Vacuum (0.005-0.001mm of Mercury)

18
(No Transcript)
19
(No Transcript)
20
Bushing under Type Test
21
Bushing under Testing in UHV Lab.
22
Testing Facilities (Contd)
  • Routine Tests on Bushings are conducted in a
    separate electro-magnetically shielded Test
    Laboratory which is provided with
  • 2.0 Million-Volt, 60 kJ Impulse Generator
  • Schering bridge
  • Standard capacitors
  • PD measuring equipment
  • Facility for conducting Cantilever Load Test

23
(No Transcript)
24
Bushing under Routine Test
25
Factors affecting performance of Bushing
  • Atmospheric condition like pollution, humidity,
    and ambient temperature.
  • Temperature rise of joints.
  • Internal Corona
  • Thermal instability
  • Loss of oil
  • Altitude

26
Causes of failure in Bushings
  • Insulation failure
  • Ingress of moisture
  • Leakage of oil
  • Internal discharges
  • Disconnection of earthing link of test tap
  • Hair crack in porcelain
  • Looseness of joint in the current carrying path
  • Failure due to high voltage such as lightning,
    switching etc.

27
Tan Delta Measurement
  • Tan Delta is the dielectric loss angle.
  • Limiting Value for OIP Bushing 0.007(Max.)
  • For measuring tan delta at site Schering Bridge
    is required.
  • New Bushing yet to be installed
  • Bushing already in service

28
Significance of Tan Delta Measurement
  • It reveals increased dielectric losses (I2R) with
    other source of heating may eventually lead to
    thermal runaway
  • High level of partial discharges are reflected
    in tan delta
  • Source of heating include dielectric losses,
    ambient temperature and load fluctuations

29
Factors affecting Tan Delta Measurement
  • Ambient conditions
  • Temperature of transformer oil around the lower
    end of bushing
  • Pollution level at site
  • Induction effect of the neighboring lines

30
Guidelines for measurement of Tan Delta at site
  • Position of bushing should be vertical
  • If mounted on transformer, remove top terminal
    connections
  • Clean the porcelain with a non-fluffy cloth
  • Check for oil level and any leakage
  • Short the bushings of other phases which are not
    under test
  • Avoid measurement on a rainy season or when
    humidity is more than 70

31
Guidelines for measurement of Tan Delta at site
  • Note temperature and correct it at 20ÂșC
  • The bushing should be tested in Ungrounded
    Specimen Test (UST)mode.
  • The bridge should be placed on a vibration free
    base.
  • Test tap should be clean and dry
  • Connecting leads should be shielded
  • Make sure the bare connector on the HV lead
    extends away from the bushing porcelain

32
Analysis of Results
  • 1) High Tan delta (between0.007 and 0.01)
  • Ingress of moisture in bushing insulation
  • 2)Very High Tan delta (Beyond 0.01)
  • High humidity, Strong ageing of insulation
  • 3) Low Tan delta
  • Weak Potential connection
  • 4) High Capacitance
  • This indicates Partial Breakdown.

33
Analysis of Results
  • Variation in Capacitance
  • With in 5 - Bushing Acceptable
  • With in 5 to 10 - Monitor Bushing closely
  • More than 10 - Inform BHARAT HEAVY ELECTRICALS
    LIMITED or Replace Bushing

34
Modifications made in design
  • Bushing sealing is improved by increasing the
    compression load
  • Hydraulic tightening introduced
  • Cork gaskets replaced by rubber gaskets
  • Design of top dome of 72.5 kV improved to protect
    ingress of rain water and better dissipation of
    heat
  • Self Earthing Test Tap

35
DOs AND DO NOTs FOR BUSHINGS DOs 1. Check the
packing externally for possible damage before
un packing. 2. Unpack with care to avoid any
direct blow on the bushing or porcelain
insulator. 3. Store the bushing in a shed or
covered with tarpoline to protect it from
moisture and rains. If removed from the crate
keep it indoors with lower end protective
intact. 4. Handle the bushing with manila rope
slings without any undue force on porcelain
insulators.
36
DOs AND DO NOTs FOR BUSHINGS DOs 5. Clean the
porcelain insulator thoroughly before taking any
measurement or mounting the bushing on the
transformer. Check for any foreign body adhered
to the bottom porcelain. 6. Check the oil
level by making the bushing vertical 7. Check
for leakage of oil from any of the gasket joints.
Each bushing is tested with the oil immersed in
oil tank and so some traces of oil can be found
which is actually not leakage. 8. Check tan
delta and capacitance ( if possible on mounted
bushing without making any connections ). 9.
Maintain the log book of records of periodical
checks.
37
DOs AND DO NOTs FOR BUSHINGS DO NOTs 1. DO NOT
unpack the bushing from crate unless required
to be mounted on the transformer. 2. DO NOT use
metal slings on porcelain and avoid un due jerks
while handling. 3. DO NOT store the bushing
outdoors with out any protective covering 4. DO
NOT measure IR value and tan delta with out
thoroughly cleaning the porcelain and oil end
portion.
38
DOs AND DO NOTs FOR BUSHINGS DO NOTs....... 5.
DO NOT fill oil in the bushing without specific
instructions from BHEL . 6. DO NOT climb the
porcelain to tighten the top terminal. Use
elevators or seperate ladder for this purpose. 7.
DO NOT dismantle or attempt to repair the
bushing in case the defect or mechanism is not
clear.
39
Bushing
  • BHEL started manufacturing of Bushings with
    Synthetic Resin Bonded Paper technology in 1962
  • Oil Impregnated Paper(OIP) bushings were
    developed in BHEL in 1982.
  • Commercial Production of OIP Bushings started in
    1984 up to 420 kV rating.
  • 525 kV Bushing manufactured and commercialized in
    1997
  • BHEL has already developed 800 kV Bushing
    (Prototype) .

40
Bushing
  • More than 25,000 Bushings manufactured by BHEL
    are in service in India and abroad for
    applications like Transformer, Traction,
    Switchgear, Cable box, Substations and
    Laboratories.

41
Testing Facilities
  • Type Tests
  • Type tests are done in Ultra High Voltage (UHV)
    Laboratory which is one of the largest
    electro-magnetically shielded laboratories in the
    world.
  • The Laboratory offers very low background level
    during PD and RIV measurements.
  • It is equipped with following facilities
  • 4 Million Volt Impulse Generator
  • 1.5 Million Volt Cascade Test Transformer
  • 1.2 Million Volts DC Generator

42
Testing Facilities (Contd)
  • 40 MVA 3-phase Motor-Generator set
  • Standard capacitors
  • Calibration and Recording Equipment
  • A pollution test chamber is also attached to this
    for conducting Wet and Pollution Tests

With these facilities all Type Tests to IEC 137,
IS 2099, BS 223 and ANSI can be done within BHEL
43
Quality Aspects
  • BHEL Bhopal is ISO 9001 and 14001 certified
    Company
  • Testing system in accordance with National
    Accreditation Board for Labs. (NABL) recognized
    by APLAC.
  • Bushings are manufactured in line with agreed
    Quality Plan with the purchaser or BHEL standard
    Quality Plan
  • Raw materials are accepted only after sample
    testing at BHEL Lab and comparing the properties
    with Plant Specifications.
  • Process is controlled to achieve tan delta less
    than 0.5 against 0.7 as specified in standards
  • All castings are routine tested before assembly.

44
Thank You
45
(No Transcript)
46
(No Transcript)
47
Equipotential condensers
Write a Comment
User Comments (0)
About PowerShow.com