Title: Bushing power transformer
1PRESENTATION ON BUSHINGS
2Topics to be covered
- What is a bushing
- Types of bushings
- Salient design features
- Testing of bushings
- Factors affecting bushings
- Causes for failure of bushings
- Dos and donts on bushings
3Bushing
- Bushing is defined as a structure carrying one or
several conductors through a partition such as a
wall or tank etc. and insulating it or them
therefrom - A bushing has to provide
- Electrical insulation to the conductor for the
working voltage and for various over voltages,
which occur in service. - Mechanical support against various Mechanical
forces.
4TYPES OF BUSHINGS 1.1 Application i) Alternator
bushing ii) Transformer bushing iii) Bushings
for switch gear iv) Wall bushing or roof
bushing v) Cable end and joint box bushing 1.2
Application i) Indoor type ii) Outdoor type
5TYPES OF BUSHINGS
- 2.1 Type of Bushing
- i) Stem type
- ii) Pull-through type
- 2.2 Type of Bushings
- i) Condenser core type
- ii) Non-condenser core type (Hollow
Porcelain type) - iii) Gas filled bushing
- iv) Solid Bushing
- Solid Ceramic Bushing
- Epoxy Bushing
6- TYPES OF BUSHINGS
- 3. Type of insulation used in manufacturing
Condenser Bushing - i) Synthetic Resin Bonded Paper (SRBP)
- Oil filled
- Compound filled
- ii) Oil Impregnated Paper (OIP)
- iii) Resin impregnated Paper (RIP)
7(No Transcript)
8(No Transcript)
9800 kV OIP Condenser Bushing
10MAJOR PARTS OF BUSHING
Top Cap
Top Porcelain
Flange
Bottom Porcelain
11Major Parts of Bushing
12CREEPAGE DISTANCE
- The shortest distance along the contour of
the external insulating surface between the
metal parts which normally have the operating
voltage between them. - Lightly polluted atmosphere
- Medium polluted atmosphere
- Heavily polluted atmosphere
- Very heavily polluted atmosphere
13 14Nominal Specific Creepage Distance
Level I Light 16 mm/kV
Level II Medium 20 mm/kV
Level III Heavy 25 mm/kV
Level IV Very Heavy 31 mm/kV
15Salient Design features
- Electrostatic Field Controlled design of
Condenser Core by Computer - Suitable for Operation under heavily polluted
atmosphere - Reliable, relatively easy erection and
practically maintenance free. - Better Dielectric Strength and Partial Discharge
free up to Working Voltage - Space for mounting of Ring Type Current
Transformer
16Salient Design Features(Contd)
- Self Earthing Test Tap for measurement of Tan
Delta and Capacitance at site. - Environmental friendly.
- Bushings for special applications can be designed
and supplied to suit clients specifications.
17Manufacturing Requriements
- Dust free pressurized winding chamber
- Winding Machines
- Oil Treatment Plants for oil processing
- Process Plants for Vacuum Impregnation at very
fine Vacuum (0.005-0.001mm of Mercury)
18(No Transcript)
19(No Transcript)
20Bushing under Type Test
21Bushing under Testing in UHV Lab.
22Testing Facilities (Contd)
- Routine Tests on Bushings are conducted in a
separate electro-magnetically shielded Test
Laboratory which is provided with - 2.0 Million-Volt, 60 kJ Impulse Generator
- Schering bridge
- Standard capacitors
- PD measuring equipment
- Facility for conducting Cantilever Load Test
23(No Transcript)
24Bushing under Routine Test
25Factors affecting performance of Bushing
- Atmospheric condition like pollution, humidity,
and ambient temperature. - Temperature rise of joints.
- Internal Corona
- Thermal instability
- Loss of oil
- Altitude
26Causes of failure in Bushings
- Insulation failure
- Ingress of moisture
- Leakage of oil
- Internal discharges
- Disconnection of earthing link of test tap
- Hair crack in porcelain
- Looseness of joint in the current carrying path
- Failure due to high voltage such as lightning,
switching etc.
27Tan Delta Measurement
- Tan Delta is the dielectric loss angle.
- Limiting Value for OIP Bushing 0.007(Max.)
- For measuring tan delta at site Schering Bridge
is required. - New Bushing yet to be installed
- Bushing already in service
28Significance of Tan Delta Measurement
- It reveals increased dielectric losses (I2R) with
other source of heating may eventually lead to
thermal runaway - High level of partial discharges are reflected
in tan delta - Source of heating include dielectric losses,
ambient temperature and load fluctuations
29Factors affecting Tan Delta Measurement
- Ambient conditions
- Temperature of transformer oil around the lower
end of bushing - Pollution level at site
- Induction effect of the neighboring lines
30Guidelines for measurement of Tan Delta at site
- Position of bushing should be vertical
- If mounted on transformer, remove top terminal
connections - Clean the porcelain with a non-fluffy cloth
- Check for oil level and any leakage
- Short the bushings of other phases which are not
under test - Avoid measurement on a rainy season or when
humidity is more than 70
31Guidelines for measurement of Tan Delta at site
- Note temperature and correct it at 20ÂșC
- The bushing should be tested in Ungrounded
Specimen Test (UST)mode. - The bridge should be placed on a vibration free
base. - Test tap should be clean and dry
- Connecting leads should be shielded
- Make sure the bare connector on the HV lead
extends away from the bushing porcelain
32Analysis of Results
- 1) High Tan delta (between0.007 and 0.01)
- Ingress of moisture in bushing insulation
- 2)Very High Tan delta (Beyond 0.01)
- High humidity, Strong ageing of insulation
- 3) Low Tan delta
- Weak Potential connection
- 4) High Capacitance
- This indicates Partial Breakdown.
33Analysis of Results
- Variation in Capacitance
- With in 5 - Bushing Acceptable
- With in 5 to 10 - Monitor Bushing closely
- More than 10 - Inform BHARAT HEAVY ELECTRICALS
LIMITED or Replace Bushing
34Modifications made in design
- Bushing sealing is improved by increasing the
compression load - Hydraulic tightening introduced
- Cork gaskets replaced by rubber gaskets
- Design of top dome of 72.5 kV improved to protect
ingress of rain water and better dissipation of
heat - Self Earthing Test Tap
35 DOs AND DO NOTs FOR BUSHINGS DOs 1. Check the
packing externally for possible damage before
un packing. 2. Unpack with care to avoid any
direct blow on the bushing or porcelain
insulator. 3. Store the bushing in a shed or
covered with tarpoline to protect it from
moisture and rains. If removed from the crate
keep it indoors with lower end protective
intact. 4. Handle the bushing with manila rope
slings without any undue force on porcelain
insulators.
36DOs AND DO NOTs FOR BUSHINGS DOs 5. Clean the
porcelain insulator thoroughly before taking any
measurement or mounting the bushing on the
transformer. Check for any foreign body adhered
to the bottom porcelain. 6. Check the oil
level by making the bushing vertical 7. Check
for leakage of oil from any of the gasket joints.
Each bushing is tested with the oil immersed in
oil tank and so some traces of oil can be found
which is actually not leakage. 8. Check tan
delta and capacitance ( if possible on mounted
bushing without making any connections ). 9.
Maintain the log book of records of periodical
checks.
37 DOs AND DO NOTs FOR BUSHINGS DO NOTs 1. DO NOT
unpack the bushing from crate unless required
to be mounted on the transformer. 2. DO NOT use
metal slings on porcelain and avoid un due jerks
while handling. 3. DO NOT store the bushing
outdoors with out any protective covering 4. DO
NOT measure IR value and tan delta with out
thoroughly cleaning the porcelain and oil end
portion.
38DOs AND DO NOTs FOR BUSHINGS DO NOTs....... 5.
DO NOT fill oil in the bushing without specific
instructions from BHEL . 6. DO NOT climb the
porcelain to tighten the top terminal. Use
elevators or seperate ladder for this purpose. 7.
DO NOT dismantle or attempt to repair the
bushing in case the defect or mechanism is not
clear.
39Bushing
- BHEL started manufacturing of Bushings with
Synthetic Resin Bonded Paper technology in 1962 - Oil Impregnated Paper(OIP) bushings were
developed in BHEL in 1982. - Commercial Production of OIP Bushings started in
1984 up to 420 kV rating. - 525 kV Bushing manufactured and commercialized in
1997 - BHEL has already developed 800 kV Bushing
(Prototype) .
40Bushing
- More than 25,000 Bushings manufactured by BHEL
are in service in India and abroad for
applications like Transformer, Traction,
Switchgear, Cable box, Substations and
Laboratories.
41Testing Facilities
- Type Tests
- Type tests are done in Ultra High Voltage (UHV)
Laboratory which is one of the largest
electro-magnetically shielded laboratories in the
world. - The Laboratory offers very low background level
during PD and RIV measurements. - It is equipped with following facilities
- 4 Million Volt Impulse Generator
- 1.5 Million Volt Cascade Test Transformer
- 1.2 Million Volts DC Generator
42Testing Facilities (Contd)
- 40 MVA 3-phase Motor-Generator set
- Standard capacitors
- Calibration and Recording Equipment
- A pollution test chamber is also attached to this
for conducting Wet and Pollution Tests
With these facilities all Type Tests to IEC 137,
IS 2099, BS 223 and ANSI can be done within BHEL
43Quality Aspects
- BHEL Bhopal is ISO 9001 and 14001 certified
Company - Testing system in accordance with National
Accreditation Board for Labs. (NABL) recognized
by APLAC. - Bushings are manufactured in line with agreed
Quality Plan with the purchaser or BHEL standard
Quality Plan - Raw materials are accepted only after sample
testing at BHEL Lab and comparing the properties
with Plant Specifications. - Process is controlled to achieve tan delta less
than 0.5 against 0.7 as specified in standards - All castings are routine tested before assembly.
44Thank You
45(No Transcript)
46(No Transcript)
47Equipotential condensers