Newpac rapid road trial - PowerPoint PPT Presentation

About This Presentation
Title:

Newpac rapid road trial

Description:

Yuleba Minerals Pty Ltd is and Australian company mining a high grade silica deposit in south west Queensland – PowerPoint PPT presentation

Number of Views:143
Slides: 21
Provided by: jesika01
Category: Other

less

Transcript and Presenter's Notes

Title: Newpac rapid road trial


1
Newpac Rapid Road Trial
2
Background
  • UGM in conjunction with Yuleba Minerals have been
    developing a cementitious road repair product
    call Rapid Road. The aim of the product is to
    allow the rapid and efficient repair of mine
    roadways. Rapid Road is a dry mix early set high
    strength concrete blend.

3
Trial
  • Newpac Colliery was seen as an ideal site to
    trial the material. Newpac Colliery has a varying
    floor thickness and in places floor breakthrough
    has caused some large bog holes.

4
  • The trial was carried out in the long wall 2 main
    gate drive heading. A bog hole as shown in figure
    1.1 was selected for the trial.

5
(No Transcript)
6
  • Friday 4/5/07 The bog hole was mucked out to
    remove as many silts and clay like material as
    was possible. Air pumps were set in the bog hole
    to remove the water in preparation for the
    installation of the rapid road.

7
  • Saturday 5/5/07 The water level in the bog hole
    had not changed and silts were again present in
    the water. Whilst these were far from ideal
    conditions to install the rapid road it was
    decided to proceed with the trial. The original
    plan had been to open each bulka bag and rake
    material on the floor while wetting the material
    to form a slab ranging from 150mm to 250mm thick.
    Surface trials _at_25 Deg C had given a working time
    of between 5 and 10 minutes.

8
  • The revised plan was to place the material into
    the water starting at one end of the bog hole and
    work back. It was decided to start at a water
    depth of approximately 200mm and work towards the
    centre of the bog hole.

9
(No Transcript)
10
  • The down side of this method was that we had to
    add enough material to fill the area until we had
    reached the top of the water. This was the only
    way we could ensure we had added enough material
    into the water, our concern being the muddy silts
    in the bog hole would adversely affect the final
    strength of rapid road.

11
(No Transcript)
12
  • The 16 bags (16 T) of material were stored in an
    area just out bye of the bog hole. A crew of 4
    people including the Eimco operator took
    approximately 3 ½ hours to install the 16 bags of
    material. The crew started by bringing one bag at
    a time and then changed to bringing the bags on a
    trailer and hanging the bags from roof bolts
    allowing the crew to split them as they worked
    there way along the heading (see fig 1.3).

13
(No Transcript)
14
  • The rapid road surface trials showed the material
    to be workable for 5-10 minutes. During the
    installation at Newpac the rapid road seemed to
    remain workable for up to an hour figure
    1.5(left) show the material after approximately
    30 minutes while figure 1.5(right) is after
    approximately 90 minutes.Originally 24T of rapid
    road had been delivered to site of this 8T was
    mistakenly used leaving 16T. While 16T would have
    been enough to fill the area if it had been pump,
    the 16T filled an area approximately 5 meters
    wide by 8.5 meters long and a further 30 bags
    (30T) would be needed to fill the remaining bog
    hole.

15
(No Transcript)
16
  • Tuesday 8/5/07 the site was inspected (figures6)
    to see how well the rapid road material had held
    up. On inspection the rapid road was intact and
    while the area had been subject to some vehicle
    traffic the rake marks were still clearly evident
    in the surface of the rapid road. This would
    indicate that although the rapid road was used in
    very adverse conditions and that silts and clays
    in the water would have degraded its ultimate
    strength the rapid road had still obtained a
    reasonable strength.

17
Conclusion
  • The testing confirmed that the current rapid road
    mix provides enough working time to place the
    material. The testing conditions were not ideal
    but did show that the rapid road formulation even
    when subject to significant silt contamination
    provides adequate strength.

18
  • While installing rapid road directly into water
    worked, to gauge the mix the rapid road was mixed
    until it reached the surface of the water and it
    would be difficult to mix it to a level under the
    waters surface. This meant that even though we
    were originally going to lay a slab up to 250mm
    thick we ended up with a slab in places 500mm
    thick. Thus considerable more material is
    required and roof height was lost in the process.

19
  • In future situations where the water cant be
    removed the crew and offsite engineering staff
    would propose first filling the area with crushed
    rock or iron stone up to a level approximately
    200mm bellow the desired finished surface then
    (providing the water level is bellow the desired
    floor level) apply the rapid road in accordance
    with the original installation guide to provide a
    finished slab approximately 200mm thick.

20
  • Yuleba is located in Southern Queensland (near
    Roma, Surat, Miles and Chinchilla) and services
    mines in NSW and QLD
  • Kerry Grover
  • Greg Moore
  • www.yulebaminerals.com.au
Write a Comment
User Comments (0)
About PowerShow.com