Title: CONSTRUCTION AND DESIGN OF MULTI STOREY BUILDING
1CONSTRUCTION AND DESIGN OF MULTISTOREY
BUILDING
2INTRODUCTION
3Projects Undertaken
- 1. Construction of residential building (escape)
- 1.1 Excavation, Layout and Foundation
- 1.2 Column layout, shuttering and casting
- 1.3 Slab, Beam shuttering and casting
- 1.4 Important Components
-
- 2. Introduction to bonded slab post tensioning
- 2.1 Post tensioning
- 2.2 benefits
- 2.3 Tendons and stressing
4Projects Undertaken
- 3. Design of building component
- 3.1 Formwork design
- 3.2 Staircase design
- 3.3 Deep Beams
- 3.4 Slabs
5PROJECT 1 CONSTRUCTION OF MULTISTOREY BUILDING
6Excavation, Layout and Foundation
- Excavation is a process of making trenches by
digging up of earth for the construction of
foundations and basements. - Excavation level at escape site is 219.825 mm
- Excavation is done by the JCB on the hourly basis
- After the excavation the surface is leveled
called surface dressing - Layout is done on the PCC poured over leveled
surface. - Column and foundation (raft ) steel is then laid
as per drawings.
7Points to take care-
- layout should be checked properly.
- Check any difference between architectural and
structural drawings regarding location of column. - After excavation check the stability of temporary
structures built near the excavated ground. - Before laying raft reinforcement, shuttering
wall which is mainly brick wall should be built
and should be filled with soil on other side. - Check the direction of chair bars in the raft
8EXCAVATION
9LAYOUT
10RAFT FOUNDATION
11COULMN CASTING
- On the raft the column layout is done.
- Layout for starter.
- The column ties and link bars are provided as
per column reinforcement drawings and general
specifications. - Displacement of main bars should be provided
with L bar - The plumb of formwork should be checked.
- Height of cast should be calculated accurately.
- Avoid caps as far as possible.
12LAYOUT , PEDESTAL STARTER
13LINKS TIES
14PLUMB FORMWORK, CASTING,CURING
15SLAB, BEAM SHUTTERING CASTING
- beam bottom is first laid on the column and then
slab formwork is laid - After the reinforcement, the slab is checked for
steel as per drawings and level required. - A camber of 5 mm in provided in the center of
slab. - Casting of slab should be discontinue at l/3 from
the support.
16SLAB STAGES
17IMPORTANT COMPONENTS
- Key in column
- Water bar
- Binding materials
- Expansion joint
18KEY IN COLUMN
- since the height of column is very large, hence
it is not possible to cast the column at one
time, to cast the column later the key is made at
the junction so that the proper bond between the
old concrete and new concrete is formed.
19KEY IN COLUMN
20EXPANSION JOINT
- Since concrete is subjected to volume change.
Provision must be made to cater for the volume
change by way of joint to relieve the stresses
produced. - Expansion joint is function of length
- Buildings longer than 45 m are generally provided
with one or more expansion joints. - Material used as expansion joint material is
armour board whose thickness is 25 mm.
21EXPANSION JOINT
- Expansion joint material, size is 25 mm
- Expansion joint in building
22WATER BAR
- Water bar is provided in the retaining wall o
that the moisture cant move from the soil to the
joint. Water bar is basically provided at the
constructions joints of retaining wall of two
different towers
23WATER BAR
24BINDING MATERIALS
- Since the thermal expansion of concrete is
different from that of masonry. The interface
between the concrete and the masonry is liable to
crack. To avoid this crack the chicken wire mesh
is used to avoid the crack and also provides the
better grip for Masonry with concrete. - Similarly when the drainage pipes are laid along
with the outer wall then again the connection
between the pipe and the wall has different
coefficient of temperature change hence they are
joint to the concrete by lead keys. - In the toilets and kitchen sunken portion the
joints in any case are packed by water proof and
non shrinkable material.
25BINDING MATERIALS
- Chicken wire mesh between brick masonry and
concrete - Connection of pipes with concrete
- Chicken wire mesh in conduits through concrete
26WATER PROOFING
- Water proofing has remained as an unsolved
complex problem - Use of plasticizers, super plasticizers,
air-entraining agents helps in reducing the
permeability of concrete by reducing the
requirement of mixing water, hence can be also be
regarded as waterproof material. - Some of approved water-proofing compound by the
company - are- pidilite, cico, fosroe, baushimine,
unitile. - Water-proofing cement paint- super snoweem
27WATER PROOFING
- Water proofing in sunken portion of kitchen and
bathroom - WP in sunken portion at ground level
- WP in retaining wall
28WATER PROOFING IN GARDEN AREA
- For water proofing in garden area the soil is
first leveled and then rammed to achieve the
maximum density - The PCC is then laid down mixed with tape Crete
(a water proofing compound) - After PCC the plaster of fibrous material is
done. - the bituminous sheets are laid by heating it with
the welder. On those sheets the drainage pipes
are laid down with suitable slope and these pipes
are covered with geo-fabric sheets. - Again the plaster is done. On the plaster the 40
mm aggregates are laid. - On the aggregate the geo-fabric sheets are laid
down on which the sand is placed on the sand
the soil ,along with fertilizers, is placed on
which the gardening is done for the non tower
area.
29WATER PROOFING IN GARDEN AREA
- Sandy soil
- PCC mixed with tape Crete (water proof compound)
- Texas (bitumen) sheet
- Drainage pipe
- 40 mm aggregate
- Geo-fabric sheet
- Sand
30PROJECT 2 BONDED SLAB POST TENSIONING
31INTRODUCTION/BENEFITS
- Post-tensioning is a method of reinforcing
(strengthening) concrete or other materials with
high-strength steel strands or bars, typically
referred to as tendons - allows longer clear spans, thinner slabs
- lower overall building height for the same
floor-to-floor height. - allows a high degree of flexibility in the column
layout, span lengths and ramp configurations
32POST TENSIONING
33PLACEMENT OF TENDONS
- Positioning and fixing of casting and block-outs
to the edge formwork or construction joint
formwork - The support bars shall be prepared in advance.
- Lay tendons according to tendon layout in
accordance with the drawings. - Fix tendons to correct profiles with support
bars and chairs and the tendons are made with
provisions for grouting using grout using grout
vents and grout hoses - Prepare installation report for every
installation as per the enclosed format. - tolerance of tendon profiles is recommended as
follows - vertical 5 mm (at lowest and highest points)
- Horizontal 100 mm
34PROJECT 3 DESIGN OF SHUTTERING
35 LOADS ON FALSEWORK
- Loads on Falsework are any combinations of the
following - Dead loads,
- Imposed loads,
- Environmental loads,
- Incidental loads during erection and operation,
and - Lateral pressure.
36DIFFERENT LOAD DATA
- Self load shall be determined by either actual
measurement or in accordance with IS 875 (Part
I) the unit weight of wet concrete including
reinforcement shall be taken as 26 kN/m².
However, in absence of the data, load may be
assumed as 500 N/M2 for the purpose of initial
calculations . - Loads during constructional operation shall
constitute the imposed loads see IS 875 (Part 2
) Where allowance has only to be made for access
and inspection purposes, a loading of 750 N/m²
should be adequate - The lateral pressure due to fresh concrete
depends on the temperature of concrete as placed,
the rate of placing of concrete and the concrete
mix proportion - Wind loads should be taken for design in
accordance with IS 875 (Part 3 ) subject to a
minimum horizontal load equal to 3 percent of the
vertical loads at critical level. - Snow loads should be assumed in accordance with
IS 875(4) . The maximum density of ice may be
assumed to be 900 kg/m³. -
37OUTPUT OF EXCEL SHEET(DOFW)