CONSTRUCTION AND DESIGN OF MULTI STOREY BUILDING - PowerPoint PPT Presentation

About This Presentation
Title:

CONSTRUCTION AND DESIGN OF MULTI STOREY BUILDING

Description:

complete description of multi storey building – PowerPoint PPT presentation

Number of Views:5333
Slides: 38
Provided by: msdhonicaptain83
Tags:

less

Transcript and Presenter's Notes

Title: CONSTRUCTION AND DESIGN OF MULTI STOREY BUILDING


1
CONSTRUCTION AND DESIGN OF MULTISTOREY
BUILDING

2
INTRODUCTION

3
Projects Undertaken
  • 1. Construction of residential building (escape)
  • 1.1 Excavation, Layout and Foundation
  • 1.2 Column layout, shuttering and casting
  • 1.3 Slab, Beam shuttering and casting
  • 1.4 Important Components
  • 2. Introduction to bonded slab post tensioning
  • 2.1 Post tensioning
  • 2.2 benefits
  • 2.3 Tendons and stressing

4
Projects Undertaken
  • 3. Design of building component
  • 3.1 Formwork design
  • 3.2 Staircase design
  • 3.3 Deep Beams
  • 3.4 Slabs

5
PROJECT 1 CONSTRUCTION OF MULTISTOREY BUILDING
6
Excavation, Layout and Foundation
  • Excavation is a process of making trenches by
    digging up of earth for the construction of
    foundations and basements.
  • Excavation level at escape site is 219.825 mm
  • Excavation is done by the JCB on the hourly basis
  • After the excavation the surface is leveled
    called surface dressing
  • Layout is done on the PCC poured over leveled
    surface.
  • Column and foundation (raft ) steel is then laid
    as per drawings.

7
Points to take care-
  • layout should be checked properly.
  • Check any difference between architectural and
    structural drawings regarding location of column.
  • After excavation check the stability of temporary
    structures built near the excavated ground.
  • Before laying raft reinforcement, shuttering
    wall which is mainly brick wall should be built
    and should be filled with soil on other side.
  • Check the direction of chair bars in the raft

8
EXCAVATION
9
LAYOUT
10
RAFT FOUNDATION
11
COULMN CASTING
  • On the raft the column layout is done.
  • Layout for starter.
  • The column ties and link bars are provided as
    per column reinforcement drawings and general
    specifications.
  • Displacement of main bars should be provided
    with L bar
  • The plumb of formwork should be checked.
  • Height of cast should be calculated accurately.
  • Avoid caps as far as possible.

12
LAYOUT , PEDESTAL STARTER
13
LINKS TIES
14
PLUMB FORMWORK, CASTING,CURING
15
SLAB, BEAM SHUTTERING CASTING
  • beam bottom is first laid on the column and then
    slab formwork is laid
  • After the reinforcement, the slab is checked for
    steel as per drawings and level required.
  • A camber of 5 mm in provided in the center of
    slab.
  • Casting of slab should be discontinue at l/3 from
    the support.

16
SLAB STAGES
17
IMPORTANT COMPONENTS
  • Key in column
  • Water bar
  • Binding materials
  • Expansion joint

18
KEY IN COLUMN
  • since the height of column is very large, hence
    it is not possible to cast the column at one
    time, to cast the column later the key is made at
    the junction so that the proper bond between the
    old concrete and new concrete is formed.

19
KEY IN COLUMN
20
EXPANSION JOINT
  • Since concrete is subjected to volume change.
    Provision must be made to cater for the volume
    change by way of joint to relieve the stresses
    produced.
  • Expansion joint is function of length
  • Buildings longer than 45 m are generally provided
    with one or more expansion joints.
  • Material used as expansion joint material is
    armour board whose thickness is 25 mm.

21
EXPANSION JOINT
  • Expansion joint material, size is 25 mm
  • Expansion joint in building

22
WATER BAR
  • Water bar is provided in the retaining wall o
    that the moisture cant move from the soil to the
    joint. Water bar is basically provided at the
    constructions joints of retaining wall of two
    different towers

23
WATER BAR
24
BINDING MATERIALS
  • Since the thermal expansion of concrete is
    different from that of masonry. The interface
    between the concrete and the masonry is liable to
    crack. To avoid this crack the chicken wire mesh
    is used to avoid the crack and also provides the
    better grip for Masonry with concrete.
  • Similarly when the drainage pipes are laid along
    with the outer wall then again the connection
    between the pipe and the wall has different
    coefficient of temperature change hence they are
    joint to the concrete by lead keys.
  • In the toilets and kitchen sunken portion the
    joints in any case are packed by water proof and
    non shrinkable material.

25
BINDING MATERIALS
  • Chicken wire mesh between brick masonry and
    concrete
  • Connection of pipes with concrete
  • Chicken wire mesh in conduits through concrete

26
WATER PROOFING
  • Water proofing has remained as an unsolved
    complex problem
  • Use of plasticizers, super plasticizers,
    air-entraining agents helps in reducing the
    permeability of concrete by reducing the
    requirement of mixing water, hence can be also be
    regarded as waterproof material.
  • Some of approved water-proofing compound by the
    company
  • are- pidilite, cico, fosroe, baushimine,
    unitile.
  • Water-proofing cement paint- super snoweem

27
WATER PROOFING
  • Water proofing in sunken portion of kitchen and
    bathroom
  • WP in sunken portion at ground level
  • WP in retaining wall

28
WATER PROOFING IN GARDEN AREA
  • For water proofing in garden area the soil is
    first leveled and then rammed to achieve the
    maximum density
  • The PCC is then laid down mixed with tape Crete
    (a water proofing compound)
  • After PCC the plaster of fibrous material is
    done.
  • the bituminous sheets are laid by heating it with
    the welder. On those sheets the drainage pipes
    are laid down with suitable slope and these pipes
    are covered with geo-fabric sheets.
  • Again the plaster is done. On the plaster the 40
    mm aggregates are laid.
  • On the aggregate the geo-fabric sheets are laid
    down on which the sand is placed on the sand
    the soil ,along with fertilizers, is placed on
    which the gardening is done for the non tower
    area.

29
WATER PROOFING IN GARDEN AREA
  • Sandy soil
  • PCC mixed with tape Crete (water proof compound)
  • Texas (bitumen) sheet
  • Drainage pipe
  • 40 mm aggregate
  • Geo-fabric sheet
  • Sand

30
PROJECT 2 BONDED SLAB POST TENSIONING
31
INTRODUCTION/BENEFITS
  • Post-tensioning is a method of reinforcing
    (strengthening) concrete or other materials with
    high-strength steel strands or bars, typically
    referred to as tendons
  • allows longer clear spans, thinner slabs
  • lower overall building height for the same
    floor-to-floor height.
  • allows a high degree of flexibility in the column
    layout, span lengths and ramp configurations

32
POST TENSIONING
33
PLACEMENT OF TENDONS
  • Positioning and fixing of casting and block-outs
    to the edge formwork or construction joint
    formwork
  • The support bars shall be prepared in advance.
  • Lay tendons according to tendon layout in
    accordance with the drawings.
  • Fix tendons to correct profiles with support
    bars and chairs and the tendons are made with
    provisions for grouting using grout using grout
    vents and grout hoses
  • Prepare installation report for every
    installation as per the enclosed format.
  • tolerance of tendon profiles is recommended as
    follows
  • vertical 5 mm (at lowest and highest points)
  • Horizontal 100 mm

34
PROJECT 3 DESIGN OF SHUTTERING
35
LOADS ON FALSEWORK
  • Loads on Falsework are any combinations of the
    following
  • Dead loads,
  • Imposed loads,
  • Environmental loads,
  • Incidental loads during erection and operation,
    and
  • Lateral pressure.

36
DIFFERENT LOAD DATA
  • Self load shall be determined by either actual
    measurement or in accordance with IS 875 (Part
    I) the unit weight of wet concrete including
    reinforcement shall be taken as 26 kN/m².
    However, in absence of the data, load may be
    assumed as 500 N/M2 for the purpose of initial
    calculations .
  • Loads during constructional operation shall
    constitute the imposed loads see IS 875 (Part 2
    ) Where allowance has only to be made for access
    and inspection purposes, a loading of 750 N/m²
    should be adequate
  • The lateral pressure due to fresh concrete
    depends on the temperature of concrete as placed,
    the rate of placing of concrete and the concrete
    mix proportion
  • Wind loads should be taken for design in
    accordance with IS 875 (Part 3 ) subject to a
    minimum horizontal load equal to 3 percent of the
    vertical loads at critical level.
  • Snow loads should be assumed in accordance with
    IS 875(4) . The maximum density of ice may be
    assumed to be 900 kg/m³.

37
OUTPUT OF EXCEL SHEET(DOFW)
Write a Comment
User Comments (0)
About PowerShow.com