Title: Long Correction Element Upgrade
1Long Correction Element Upgrade
- Racks Equipment Installation
- Kent Triplett
- May 4, 2007
2(No Transcript)
3TG-7 Test Racks VME Node BCP670 Camac SY 70
4HRM VME Node BCP670 at TG-7
5New Magnet Assembly at TG-7
6Finish Preparing Racks
- East Gallery Racks are in place, bolted together
- Initial rack prep and wiring almost complete
- Ransons Work
- Install 120V strips
- Run cabling, do connections outlets for 480V
- Cut holes in top sides of racks for cabling entry
- Install cable trays
- Ground rack to rack, racks to building
- Once electricians finish a location,
installations begin - Racks at Period 13 (mid East Gallery) still w/o
120VAC - Looking for FESS maintenance period for
opportunity to hook up regular rack power - Will also need 480V power panel outage to connect
neutrals for bulks
7Period 16 Correctors for 17, 18, 19, 20 Camac 8A
8Period 14 Correctors for 13, 14, 15, 16 Camac 7A
9Period 11 Correctors for 9, 10, 11, 12 Camac 6A
10Finish Preparing Racks
- Most West Gallery Racks are in place, bolted
together, except Period 24 - Period 24 racks are ready for the work, work
request submitted for 4 hour effort - Ransons folks are working on running electrical,
and preparing racks in West Gallery now - Will require some outages to supply 120V and 480
connections in this gallery
11Period 21 Correctors for 21, 22, 23, 24 Camac
1A
12Period 24 racks these will be relocated
13Period 24 racks all 4 racks will move here
for correctors 1, 2, 3,4 Camac 2A
14Racks at Period 24 will be relocated drawing
compliments C. Drennan
15Period 4 racks for correctors 5, 6, 7, 8
Camac 4A will need a new repeater here
16MiniBooNE Correctors
Bulk below supplies DC breakers w/ 180VDC then on
to regulators
17MiniBooNE Correctors
18TG-9 Example SY Correctors
19Immediate Issues
- Late start on rack cabling plan parts orders
- However, a plan has been devised,
- Cable routing and lengths have been determined
- Most parts have been ordered, some already
arrived - Get one set of cabling completed
- Will take about 95 hours of total effort!
- The worst part by far is the 37 pin D connectors!
- Install in test racks
20Initial Estimate To Complete Cabling _at_ 7 Locations
21Controls Equipment Availability
- Camac Crates Controllers
- In Stock, ready to install
- Will need to cable to repeaters for PIOX, PIOR,
BTR, TCLK (P16 done already) - Will need to upgrade a repeater at BTW for the
addition 4 hr downtime request - 473s The New Ramp Cards
- 10 full production ready to go, should have 36 -
40 within 4 5 weeks - Only 36 were requested, 4 spares exist, a few
prototypes exist - Including our test rack, we need 42
- Need to authorize Controls to produce at least 10
more - Just got a firmware driver upgrade, testing to
be done more later - 218s Bulk Control Status
- Ready to go
- 377 Timing cards
- Not specified, but we might want to include one
at each crate. Available - 183 cards or other?
- We might want a way to provide remote reset to
HRM, VME, investigate further
22Controls Equipment Availability
- TCLK fanout (McClure Box)
- One per location, will be available when we need
them - VME crates
- We have them
- Mike Kucera has all the cards that go in them
- Mike Kucera will arrange for ethernet hookups
- HRMs
- 6ea 128 channel HRMs currently exist, some need
madc board upgrade - Upgraded boards are in production (isolated
signal grounding from chassis) - We are using 127 channels worth of the HRM at
each location! - I reference I monitor I rms V monitor I
error for each regulator - 3 bulk signals 4 RTD signals
- Brand new for the accelerator complex, we need to
give the test rack HRM some traffic. Will be
easier to do this soon.