Title: ISBUC
1- The feasibility of implementing gasification
technology in the sugar industry - an Australian perspective
- P.A. Hobson
ISBUC Third meeting Mauritius 29 June 3
July 2009
2The feasibility of implementing gasification
technology in the sugar industry an Australian
perspective
- Gasification initial interest
- Drivers
- Preliminary studies
- Queensland Biomass Integrated Gasification
program - Development of the business plan
- Outcomes from the QBIG program
- Subsequent work
- Current directions
- Pre-processing of bagasse (torrefaction)
- Second generation biofuels
3Gasification some preliminary studies
- Early 1980s Tests commissioned on catalytic
gasification for methanol production (Battelle
Labs, US) - Renewable Energy (2000) Act
- Mandated 2 new renewable(9500 GWhe) capacity by
2010 continuing to 2020 - 40 per MWh penalty for not meeting renewable
power targets - Preliminary SRI study on integrating gasification
and factory operations (1998) - Two-fold increase in power generation relative to
conventional steam - Precursor to Queensland Biomass Integrated
Gasification project - Australian milling industry and Sugar Research
and Development Corporation
4Preliminary study- impact of factory process
steam (2 M tonne crop)
5Preliminary study- impact of additional fuel on
power generation efficiency
6Preliminary study- year round power generation
with additional fuel from trash(2 M tonne crop)
- Crushing season
- Minimum bagasse consumed to meet process demands
- Sufficient surplus bagasse/ trash stored to fully
utilise gasifier and GT in off-season - Off-season
- All stored bagasse consumed
7Preliminary study- whole of (Australian) industry
export capacityCrop size 37 M tonnes
8Preliminary study - site visits
- Varnamo, Sweden
- Sydkraft
- 6MWe/ 9MWth
- 22 bara, CFB
- Maui island, Hawaii
- IGT technology
- 100 tons/ day
- 21 bara, BFB
- Burlington, US
- Battelle technology
- 200 tons/ day
- 2 bara, indirect CFB
- Morwell, Australia
- HRL technology
- 5 Mwe GT
- 25 bara, CFB
9Preliminary study HRL IDGCC (brown coal)
technology
10Preliminary study some conclusions
- Approximately 100 increase in power export
- Pressurised BIG/CC appropriate to Australian
industry - Higher capital cost offset by greater efficiency
for BIG/CC installations greater than 50 MWe - All mills would have a BIG/CC capacity gt 50 MWe
- For maximum efficiency potential
- Process steam demand lt 40 SOC or
- An additional 25 fibre
- Pressurised feeding of bagasse is problematic
- Low bulk density compared with other biomass
- Bagasse binds in screw feed systems
- Large amount of additional fibre to fully utilise
capacity in off-season - Additional 66 of existing bagasse supply
- Approximately 350,000 tonnes storage for 2 M
tonne factory
11Development of the QBIG program
- Project team
- Formed prior to development of scoping study
- Team members
- Power Industry - Stanwell Corporation Ltd
- State Government Office of Energy
- RD providers SRI, University of Queensland
- Scoping study/ business case
- Critical assessment of conversion technologies
- Evaluation of power export potential and GHG
mitigation - Fully costed research plan
- Study externally reviewed
- Secured funding
- A 5m
- Power industry and State Government
12Queensland Biomass Integrated Gasification
program (QBIG)
- Initiated in 2000
- Ultimate aim of commercial demonstration of high
pressure BIGCC - Phase I Strong focus on sugar industry specific
feasibility issues - Bagasse gasification kinetics
- Pressurised feeding
- Ash characterisation
- Fuel availability
- Financial viability
- Phase II - Demonstration
13QBIG Gasification kinetics
- Bench scale reactor
- 900 C
- 25 bara
- Entrained flow
- Departure from TGA
- Computational Fluid Dynamics (CFD) model
- Implementation of char reactivity data
- Assist Phase II design
- Focus on char
- Initial char yield
- Subsequent char gasification rate
14QBIG Pressurised feeder
- Bagasse particularly difficult to feed!
- Continuous feeder developed
- Tested to 25 barg
- Minimal leakage with bagasse
- Leakage problems with bagasse/ woodchip blend
- Demonstrated at 75 of 15 MWth
commercial demonstration scale
- Design criteria
- High volume
- Continuous
- High pressure
- Sealed
15QBIG fuel availability
- Whole of cane biomass harvesting
- Factory separation
- QBIG separator
- Demonstrated at commercial scale (150 tch)
- Low cane losses (lt 1)
- High trash recovery (98)
16QBIG Financial viability
- Multiple scenarios - factory integration, fuel
and operational - Conventional steam and IG/CC compared
- Conversion of existing boiler to HRSG reduces
capex for IGCC - Steam plant dominated by fuel costs, IG/CC by
capital costs - Figures below based on 2000 2002 costs
revenues (very different now!)
17QBIG Outcomes
- Phase I
- Essentially complete
- Ash characterisation deferred to phase II
- Phase II
- Australian renewable energy target scheme
inadequate - Value of RECs lower than anticipated
- Initial projections of A40 per MWh
- Actual value dropped to A16 per MWh
- Bid at the time to increase 2 federal target to
5 rejected - Escalating capital costs
- Decision by main stakeholders not to proceed
18Integration of gasification in the Australian
sugar industry
- Major feasibility study
- Federal and Queensland state funded Sugar
Industry Renewable Energy program - Industry-wide staged introduction
- Technical and financial analysis
- Some findings include
- Confirms QBIG economic study
- Optimum mix of conventional and IG/CC power would
deliver 66 of the federal renewable target of
9500 GWh - Capex 2.8 times conventional steam - a major
impediment - High cost of trash at A15 - A25 per tonne
reduces IG/CC viability - Lapse of federal governments renewable energy
target in 2020 provides insufficient revenue
certainty for emerging technology
19Current directions whats changed?
- Mandated Renewable Energy Target
- Originally 9,500 GWh new capacity
- Extended to 45,000 GWh by 2020
- Carbon Pollution Reduction scheme
- Implementation by 2010
- Emissions reduction relative to 2000
- Long-term target 60 by 2050.
- Medium-term 5 to25 by 2020.
20Current directions
- Diversification - value adding to fibre
- Current projects at QUT - fuel and chemicals
- Flash pyrolysis for furfural production
- Biorefinery demonstration plant
- Ionic liquids for fractionation
- Value adding to lignin
- Hydrolysis of cellulose to C6 sugars
fermentation to ethanol - Direct liquefaction of bagasse
- Hydrothermal liquefaction for bagasse
fractionation - Phenolic compounds from lignin
- Levulinic acid from cellulose
- Torrefaction
- Use of catalysts to reduce residence time
- Impact of pre-processing on supply chain
logistics and costs
21Gasification technology
- Flexible power, fuels, chemicals
- Efficient
- Power export increased by factor of 2.5
- 330 L ethanol per tonne dry fibre
- 140 L diesel per tonne dry fibre
- Issues
- Lack of commercial demonstration
- Economies of scale
- Material handling
- Transport
- Large scale storage
- Feeding
22Torrefaction as a pre-process - strategic
advantage
- Coal-like energy density and handling properties
- Capitalises on decades of coal technology
development - Synergies with short and long term development
horizons - Conventional power generation (co-firing)
- Advanced cycle power generation (IG/CC,
pressurised combustion) - Coal to liquid fuel production (Fischer Tropsch
hydrocarbons and alcohols) - Emerging technologies (supercritical
gasification, direct liquefaction,
hydropyrolysis) - Low technical and commercial risk
- Engineering challenge reduced to development of
a low pressure/ temperature pre-process - Utilisation of significant existing coal RD
facilities
23The torrefaction process
- 200 - 300C
- Near atmospheric pressure
- Absence of air
- Residence time of 10 30 mins
- Volatilisation of hemicellulose component
- Feedstock thickness lt 4cm
- Heating rate
- lt50C/min
off-gas
30
10
torrefied product
dry biomass
100
70
Torrefaction
90
100
90
1.3
Energy densification 1 x
70
Energy
Mass
24Torrefied biomass
- Typically 24 MJ/kg (HHV)
- Hydrophobic (maintains 3 moisture)
- Stable in long term storage
- Friable
- 10 of the comminution energy required for
untreated biomass - Compatible with conventional coal milling
equipment - Readily pelletised
- 50 of energy required to pelletise raw biomass
- High residual lignin (bonding agent)
- Volatiles retained
- 50 to 60 volatiles retained
- Rapid combustion/ gasification
- A smokeless fuel
25Comparison with other pre-processes
- Supply chain study by Uslu (et al., 2008)
- Process efficiency
- Torrefied and then Pelletised Bagasse (TPB) - 94
- Pelletised biomass - 84
- Bio-oil (from flash pyrolysis) - 64
- Cost of biofuel production using TPB
- 86 of cost using pelletised biomass
- 63 of cost using pyrolysis
26Comparison of pelletised torrefied biomass (TOP)
with pelletised and unprocessed biomass1
- 1Kiel, J. (2007) IEA Bioenergy Task 32 workshop
Fuel storage, handling and preparation and
system analysis for biomass combustion
technologies, Berlin
27Preliminary financial evaluation
Torrefaction plant
Fischer Tropsch (FT) diesel
Mill A
Biomass to liquid fuel (BTL) plant
Mill B
55
Year round operation
Mill C
110
Maintenance season
Mill D
165
Crushing season
Mill E
220 km
28Torrefaction - material inputs
29Torrefaction - financial inputs
30Storage transport costs
31Gasification and biofuel production
- Conversion efficiencies (energy basis)
- Biomass to syngas 80
- Syngas to FT diesel 71
- Capital cost based on Boerrigter (2006)
- Assumed same as CTL1 costs after pre-processing
- CTL estimated by inflating known GTL2 costs
- Additional reactor costs
- Additional oxygen enrichment
- Operating fixed percentage of capex
- Assume long term 50 excise discount or
equivalent for renewable fuels
1CTL Coal to liquid fuels 2GTL Gas to
liquid fuels
32Diesel production costs
33Impact of pre-processing on gasification costs
- TPB has lower transport costs than bagasse for
distances greater than 100 km - Break-even (15 IRR) oil price for diesel
production - 97 US/ bbl without local TPB production and
transport - 76 US/ bbl with local TPB production and
transport - Potential for further reduction in costs
- Accessing TPB from greater distances (i.e. gt 200
km) - TPB from biomass sources other than bagasse
- Co-firing in CTL plants (e.g. SASOL)
- Integration of advanced cycle power plants (IG/CC)
34In conclusion ...
- Development of a good business case worth doing
well but can be a costly process - Ideally syndicate members should be identified
prior to preparation of the business case - Peer review prior to issue
- Robust financial analysis investigating key
drivers - Look for highest value end product
- Focus RDD on sugar industry specific issues
- Should be technically well differentiated from
other/ previous projects - Minimise technical risk - look for opportunities
to utilize proven/ commercial technology
35Acknowledgements
- Compagnie Sucrière du Sud and Queensland
University of Technology for their sponsorship - Jean Claude Autrey and Manoel Regis Leal for the
invitation to attend this meeting
36Thank you