Title: GLENDALE WATER SUPPLY IMPROVEMENT PROJECT


1
GLENDALE WATER SUPPLY IMPROVEMENT PROJECT
  • Construction Methodology
  • December 2004

2
Construction Methodology/ Sequence
  • Surface preparation
  • Foundation stabilization
  • Surface improvements
  • Site restoration

3
2006 - Surface Preparation
  • Prepare staging area
  • Prepare stockpiling area
  • Install access ramps into channel
  • Divert surface flow (two diversions)
  • Clear and grub within construction limits
  • Excavate to top of foundation and stockpile

4
Foundation Stabilization
  • Install Grout Curtain at the following locations
  • weir structure
  • fish and boat passage
  • juvenile fish bypass
  • concrete crib walls

5
Complete Phase 1 Construction
  • Verify adequacy of installed grout curtain
  • Demobilize foundation stabilization contractor
  • Winterize project site

6
2007 Construct Surface Implements
  • Construct fish and boat passage
  • Divert surface flows through fish and boat
    passage
  • Construct weir
  • Construct concrete crib walls and backfill
  • Construct juvenile fish bypass
  • Construct Intake Structure Improvements
  • Reconstruct West Riverbank
  • Demobilize and Re-Vegetate

7
Construction Timeline
  • 2006 Construction Season
  • Prepare staging and stockpile areas
  • Implement foundation stabilization
  • 2007 Construction Season
  • Construct surface improvement
  • Restore project site