Title: FFAGs for medical applications
1Status of EMMA
Rob Edgecock for the EMMA Collaboration
BNL, CERN, CI, FNAL, JAI, LPSC Grenoble, STFC,
TRIUMF
2Outline
- Introduction
- EMMA parameters
- Status
- Hardware
- Magnets
- RF
- Diagnostics
- Conclusions
3Introduction
Large acceptance and CW acceleration for
muons Now also studied for hadron therapy, ADSR,
proton drivers But unique optical features No
such machine ever built Work so far entirely
theoretical Codes not benchmarked Must build
one EMMA
4EMMA Parameters
- Electron model of muon FFAGs parameters
scaled muon ? electron - (Very important RD project for NF)
- Parameters - 10 to 20 MeV - Doublet
lattice - 42 cells - total length
394.481mm - long drift 210.000mm
- F 58.782mm -
short drift 50.000mm - D
75.699mm - RF 1.3GHz, 1 cavity every
other cell - 8 lattice configurations -
bunch charge 16-32pC - precise measurement
of beam parameters
5Aims
- Demonstrate that non-scaling optics work
- Study resonances in detail - emittance
growth vs acceleration rate -
vs tune variation -
vs parabola shape - effect of
errors - detailed probe using injector - Study longitudinal dynamics in detail -
transmission vs parameter values - emittance
growth vs parameter values - tof behaviour
effect of non-parabolic nature - effect of
moving parabola - effect of errors - Check effect of transverse dynamics
- Compare with predictions
- ..
6Status
- Funding started on 1st April 2007
- Injector built and being commissioned
- EMMA design essentially complete
- EMMA hardware see later!
- Main milestones Major components on
site 1st Aug 08 Construction complete 23rd
Jul 09 Start experimental programme 18th Sep
09 EMMA phase 1 complete 9th Jul 10
7Injector
- Need a flexible injector - injection at
any energy - small emittance -
sufficient intensity in a single
bunch Energy Recovery Linac Prototype at
DL
8 EMMA Design
9(No Transcript)
10(No Transcript)
11(No Transcript)
12Magnets
13Ring Magnets
- Should be combined function
- Implemented as quadrupoles, mounted on slides
14Ring Magnets
Prototypes built by Tesla F is OK, D being
improved Order for 84 magnets also won by
Tesla Delivery in 6 months
15Septum
Nominal angle 72o In practice 90o
Initially impossible! After F?D flip 2
solutions Best awaits tracking Stray field
not too high
16Magnet PSUs
Up to 42 F existing SRS DC power converter Up
to 42 D
8 magnets powered individually introduce
errors non-uniformity Septums existing SRS
pulsed power convert. Kickers
17RF Cavity Design
Requirements
18RF Cavity Design
Prototype cavity ordered from Niowave (Cu)
Delivery early March Power coupler from Times
Microwave
19RF Power
Cascaded power distribution
LLRF DimTel Inc assessing adapting existing
board (SNS LLRF) to EMMA
20RF Power
Power sources IOTs e2v or CPI
PSU re-use SRS PSU (large mods
required) be-spoke (small, new, low cost)
21Diagnostics
22Diagnostics
BPMs 4 82 3 89 ? need to be cheap!
Two options for readout electronics analogue
being developed in UK digital being developed
at FNAL Comparison and selection spring 08
Purpose built 4-button BPMs Simulations suggest
required precision for 25pC
23Diagnostics
BPM locations
24Diagnostics
Screens 7 2 6 15
Purpose built Probably YAG due to
charge Otherwise OTR with gated CCD cameras
(expensive!)
25Diagnostics
Wires 0 2 0 2
26Diagnostics
WCM 1 1 1 3 being developed at
FNAL lots of experience! Faraday cups 1 0
1 2 same as on ERLP Beam loss monitors 0
4 0 4 same as on ERLP Spectrometer magnet
0 0 1 1 re-use from SRS
27Conclusions
- EMMA will - prove the principle of
NS-FFAGs - demonstrate their use for NF - Funded as part of the CONFORM project
- EMMA collaboration - works well -
always constructive - Machine design is essentially complete
- Most hardware is well advanced
- Still on schedule
- First operation August 2009