Entergy Arkansas, Inc' Proposed Transmission Projects - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Entergy Arkansas, Inc' Proposed Transmission Projects

Description:

1.) Gobel - 230/115 kV Substation. 2.) Re-conductor 115kV Transmission Line from Corning to ... Thayer South: Install New 161 kV Intertie w/ AECI (Cancelled) 9 ... – PowerPoint PPT presentation

Number of Views:60
Avg rating:3.0/5.0
Slides: 24
Provided by: stuf7
Category:

less

Transcript and Presenter's Notes

Title: Entergy Arkansas, Inc' Proposed Transmission Projects


1
Entergy Arkansas, Inc.Proposed
TransmissionProjects
  • Entergy Transmission Planning Summit
  • New Orleans, LA
  • July 31, 2007

2
2007 - 2008 EAI Transmission Projects
1
1.) Hilltop New Ring Bus at Intersection of EAI
and SPA lines
2.) Dewitt Capacitor Bank
2
Carryover from 2006
2007/2008 Projects
3
2009-2010 EAI Transmission Projects
1.) Grandview 161kV Substation
2.) Dell 161kV Reactor Replacement
1
2
3.) Cabot 500/115kV Substation
3
4
2011-2012 EAI Transmission Projects
2.) Re-conductor 115kV Transmission Line from
Corning to Texas Eastern 8
2
1.) Gobel - 230/115 kV Substation
1
5
Hilltop 161 kV Ring BusBetween EAI and SPA Lines
2007
  • Scenario
  • The 161 kV transmission system in northwest
    Arkansas is generally served by generation
    located at Arkansas Nuclear One (ANO) and
    Independence SES (ISES).
  • There are also units at Table Rock, Ozark Beach,
    Norfork and Bull Shoals Dam which provide some
    support during the summer peak, but availability
    of these resources is limited by the availability
    of water on their respective sources.
  • Three major transmission lines which originate at
    Harrison East and cause undervoltages and thermal
    overloads
  • Harrison East Eureka Springs 161 kV
  • Harrison East Bull Shoals Dam 161 kV
  • Harrison East Quitman 161 kV
  • Proposed Solution
  • Build a four-breaker ring bus, Hilltop, where the
    SPA line from Dardanelle - Bull Shoals crosses
    the APL line from Harrison East - Quitman.
  • Estimated Cost 8.6 M

6
Hilltop 161 kV Ring Bus
Hilltop Install New Ring Bus
7
Thayer South Install New 161 kV Intertie w/ AECI
  • Project Cancelled
  • AECI elected to connect to an existing AECI owned
    161kV Station

8
Thayer South Install New 161 kV Intertie w/ AECI
(Cancelled)
9
Dewitt 32.4 MVAR Capacitor Bank
2008
  • Scenario
  • Loss of the Helena Industrial - Ritchie SES 115
    kV line segment causes low voltages at various
    substations
  • Loss of the Stuttgart Ricusky 230/115 kV
    autotransformer causes low voltages at various
    substations and overloads on the Woodward
    Altheimer and the Altheimer Wabbaseka 115 kV
    line segments
  • Proposed Solution
  • Install a 32.4 MVAR capacitor bank at Dewitt.
  • Correct Distribution power factor at Dewitt,
    Almyra, Marvell, Gillett, Helena Central, and Ulm
    substations.
  • Estimated Cost 880 K

10
Dewitt 32.4 MVAR Capacitor Bank
Dewitt 32.4 MVAR Capacitor Bank
11
Maumelle East Substation Install 2nd T-Line
2008
  • Scenario
  • Significant load growth in the Maumelle area
    justified removing Maumelle East from radial
    service.
  • The loss of the Maumelle East Maumelle SS line
    results in a complete outage to the Maumelle
    area.
  • Proposed Solution
  • Construct a parallel 115kV line from Maumelle SS
    to Maumelle East to establish dual line service.
  • Estimated Cost 3 M

12
Maumelle East 2nd Transmission Line
Maumelle East 2nd Line
13
Dell 161kV Reactor Replacement
2010
  • Scenario
  • The 161kV reactor at Dell failed late 2006.
  • During off-peak, low load periods, the voltage at
    Dell EHV reaches 1.05pu on the 500kV and 161kV
    systems.
  • Proposed Solution
  • The failed 161kV 50MVAR reactor at Dell will be
    replaced with 2-161kV, 30 MVAR reactors
  • Estimated Cost 1.5 M

14
Dell 161kV Reactor
Replace Dell 161kV Reactor
15
Osage Creek-Grandview
2010
  • Scenario
  • By 2010 it is estimated that approximately 227 MW
    of load will be served between Harrison East and
    Eureka Springs.
  • Nearly 110 MW of the load will be located at
    Osage Creek, at the extreme northwest end of the
    line.
  • Loss of the Harrison East Harrison South
    transmission line segment causes thermal
    overloads by as much as 7 on the Eureka Osage
    Creek (AECC) line segment and leaves over 30 MW
    at risk.
  • Loss of this line also causes Osages voltage
    drop to 73.
  • Proposed Solution
  • Construct a new switching station, Grandview, on
    the transmission line from Table Rock Dam
    Eureka Springs. Build a new line between
    Grandview and Osage Creek.
  • Estimated Cost 5.8 M

16
Osage Creek-Grandview
Grandview
17
Cabot 500/115kV Substation
2010
  • Scenario
  • For the past two summers, several stations in
    Little Rock observed voltages as low as 91 of
    nominal with no significant contingencies.
  • The loss of one of the 500/115kV transformers at
    Mabelvale in 2006 resulted in widespread low
    voltages in the Little Rock area.
  • With the loss of one 500/115kV transformer at
    Mabelvale, a loss of the second transformer (N-2)
    would cause the voltage to collapse and
    widespread outages in the Little Rock area.
  • Proposed Solution
  • Construct a 500/115kV substation near Cabot
    Northeast of Little Rock. This will provide
    voltage support to Little Rock and reduce some
    thermal contingencies.
  • Estimated Cost 19 M

18
Cabot 500/115kV Substation
Cabot EHV
19
Gobel 230/115 kV Substation
2011
  • Scenario
  • Loss of the Helena Industrial - Ritchie SES 115
    kV line segment causes
  • Low voltages at Helena Central, Barton, Marvell,
    Elaine, Gillette, Deluce, and Dewitt
  • Loss of the Stuttgart Rickusky 230/115 kV
    autotransformer causes
  • Low voltages at Almyra, Deluce, Gilette, Dewitt,
    Stuttgart North, Stuttgart Ricusky, Ulm,
    Wabbaseka, and Stuttgart Industrial
  • Overloads the Woodward Altheimer 115 kV line
    segment
  • Overloads the Altheimer Wabbaseka 115 kV line
    segment
  • Proposed Solution
  • Build a 230/115kV Substation at the crossing of
    the 115kV transmission line from Marvell to
    Elaine and the 230kV transmission line from
    Ritchie to Stuttgart Ricusky.
  • Estimated Cost 9 M

20
Gobel 230/115 kV Substation
Gobel 230/115kV Substation
21
Re-conductor Corning - Texas Eastern 8 115 kV
line
2011
  • Scenario
  • Previous construction has increased the conductor
    size on selected spans to 1590 MCM and 666 MCM,
    but a majority of the line is 336 MCM or smaller
    (e.g., 4/0 copper), and substation equipment
    limits the ampacity of the line.
  • The voltage drop from TE 8 to Corning exceeds
    22 under certain single contingency scenarios.
  • Low voltage also causes greater current to flow
    and will cause a 190 overload on the Corning to
    TE 8 line segment.
  • Proposed Solution
  • Rebuild the line segment from Corning to TE 8
    with 666 MCM, to increase the line rating to 176
    MVA.
  • Estimated Cost 3 M

22
Re-conductor Corning - Texas Eastern 8 115 kV
line
Upgrade 115kV Line
23
Transmission System Target Areas 2013 and Beyond
  • 1.) Jonesboro Area
  • Line Upgrade

1
  • 2.) Little Rock Area
  • Additional Reactive Support

2
  • 3.) Hot Springs Area
  • Line Upgrade
  • New 115kV Switching Station

3
  • 4.) El Dorado Area
  • 2 New 115kV Transmission Lines
  • Line Upgrades

4
Write a Comment
User Comments (0)
About PowerShow.com