Title: Tech Partners Brown Bag 21st Century Network Upgrade
1Tech Partners - Brown Bag21st Century Network
Upgrade
Jim Hilby Al Krug DoIT Network Services
221CN Project Breakdown
321CN Scope Expansion
- 10 Gbps backbone connections
- 12 supernode to node connections
- Production platform
- Wireless WiscWorld
- Estimated 2,200 access points
- Cisco 3750 with line power
421CN - Timeline
521CN - Completions
- Backbone Deployment
- 3 supernodes with 10 Gbps interconnections
- 13 nodes with 1 Gbps connections to core
- Building LAN Migrations
- 247 LANs
- Central Monitoring System
- HP Openview
- NOC
- 24x7
621CN Completions (cont.)
- Platform Migration
- 495 servers
- Outside Fiber (01I2E)
- 23 fiber connections for supernodes and nodes
- VPN
- Dynamic
- Static
- DATN (Digital Academic Television Network)
721CN - VPN
821CN - DATN
921CN Radial Deployment Statistics
- Switches
- 1,800 estimate
- 348 (17.7) online
- 130 (7.2) in process
- Buildings
- 180 estimate
- 20 (11.1) online
- 14 (7.7) in process
1021CN Radial Buildings Operational
- Memorial Library
- Ingraham Hall
- Weeks Hall
- Ag Engineering Bldg
- Babcock Hall
- Russell Laboratories
- Health Science Learning Center
- Van Vleck
- Elvehjem Museum
- Camp Randall Phase 1
- Field House
- Bascom Hall
- Kohl Center
- Medical Science Center (Statistics)
- Kellner Hall
- Athletics Operations
- 1301-07 University
- 45 N. Charter
1121CN Design Changes
- Building electronics design
- Layer 2 network
- Limiting cross campus VLANs
- Turned off auto-redundancy except for core
- Upgraded to Sup 720
- Reviewing production network
- Management network
1221CN Radial Design (old)
- MDF - 3750-12
- IDF - 3550-48/24
- Gig connection between switches
- Redundancy between uplinks
1321CN Radial Design (new)
- MDF - 3750-12
- IDF - 3750-48/24 3750-48/24 with line power
- Stackwise
- Either channel
1421CN Radial Equipment Deployment
- Orientation / start-up meeting
- Management relationship decision
- Design meetings
- Equipment order
- Installation
- Pre-migration meeting
- Migration
- Operation turnover email
1521CN Wireless WiscWorld
- Estimate 2,200 APs
- Complete current requests
- Deploying line powered switches in IDFs
- Augment current data wiring requests
- Deploy APs as part of radials starting Feb 05
- Retrofit early radials
1621CN - AANTS
1721CN - Security
- High priority
- Firewall Blades
- Testing of security blades
- Fix expected in November
- Re-test
- Intrusion Detection
- Modem pool
- Wireless WiscWorld
- VPN
- Physical Security
1821CN Telecommunication Rooms
- Near-term upgrades
- Goal 840 telecommunication rooms
- 319 (17.7) complete
- 109 (13.0) in process
- Full upgrades
- Goal 700 telecommunication rooms
- 27 (3.8) complete
- 16 (2.3) in process
1921CN Fiber
- Outside Plant Fiber
- Goal Install 142 single mode fiber runs by
6/30/08 - 29 (20.4) fiber installations complete
- 80 (56.3) fiber installations are approved for
project 04B3F - 33 (23.2) fiber installations will be requested
for state project in FY05-07 - Inside Plant Fiber
2021CN Data Wiring
- Cat 5e/6 upgrades
- Goal 120 buildings by 5/30/08
- 8 (6.2) buildings upgraded
- 27 (22.5) buildings in project 043BF
- 80 (66.7) buildings in FY05-07
- 5 (4.2) buildings after FY07-09
- Small cabling projects
- Lab Server rooms
2121CN Campus Coordination
- DoIT
- Campus Net Eng
- WAN Engineers
- Field Services
- NOC
- Help Desk
- Departments
- Technical Staff
- Building Management
- Police Department
- Physical Security
- FPM
- Capital Budget Admin
- SMO
- Minor Projects
- Physical Plant
- Electrical
- HVAC
- Carpentry
- System Administration
- Division of State Facilities
2221CN Related Projects
- Peterson Supernode Move
- Objective Move to 432 N. Murray
- Target March 2006
- Sterling Hall Node Move
- Objective Move to Chamberlin Hall
- Target December 2006?
- Ogg Hall Node Move
- Objective Move to new residence hall
- Target October 2007
2321CN - Links
Project overview http//www.doit.wisc.edu/network/
upgrade Project FAQ http//www.doit.wisc.edu/net
work/upgrade/faq/aants.asp Radial
Schedule http//ns.doit.wisc.edu/21cn/PublicView.h
tm Management Options http//ns.doit.wisc.edu/21
cn/ManagementOptionsOverview.htm Responsibility
Matrix http//ns.doit.wisc.edu/21cn/ResponsiblityM
atrix.htm Memo of Understanding http//ns.doit.w
isc.edu/21cn/MemorandumOfUnderstanding.htm Autho
rized Agent Training http//ns.doit.wisc.edu/21CN/
AuthorizedAgentTraining.htm EdgeConf tool
demo https//charge.doit.wisc.edu/edgeconf/cgi-bin
/switch_login.cgi netid test1, password
test1 AANTS https//aants.net.wisc.edu/
access to AANTS using your netid when the
equipment is installed
24Questions / Comments