Title: NJ Offshore Wind Park Marine Activities Overview
1NJ Offshore Wind ParkMarine Activities Overview
- Presented to
- Integrated Ocean Observing System (IOOS) Offshore
Wind Energy Meeting - Institute of Marine Coastal Sciences at Rutgers
New Brunswick, NJ - 2 February 2009
2Example Offshore Wind Park Layout
Intra-array submarine cables
Offshore transformer platform
Wind turbine array
Submarine cable to shore
OFFSHORE
Connection to existing grid at substation
ONSHORE
3Project Description
- Project Size 348 MW (116 turbines)
- Closest turbine about 15.6 highway miles
southeast of Atlantic City - Offshore Construction Start Date
- Meteorological tower 2009
- Wind park 2012
4Location of New Jersey Project
5Marine Activities Overview
- Pre-Construction
- Avian Studies
- Geophysical Investigations
- Geotechnical Investigations
- Met Tower Installation
- Wave Sensor Deployment
- Staging Port Development
- Construction
- Foundation Installation
- Sub-sea Electrical Cable Installation
- Offshore Substation Installation
- Turbine Installation
- Post-Construction
- OM Activities
- Decommissioning
6Avian StudiesOverview of Studies
- Visual Transects
- Requires moving vessel
- Conducted in all seasons
- Radar
- Requires stationary
- platform
- Conducted during
- spring and fall migration
- periods
Source www.detect-inc.com
Source www.capecodtoday.com
7Geophysical InvestigationsBathymetry, Side Scan
Imagery, and Sub-Bottom Profiles
- Met tower
- Turbine field
- Export cable route
Source www.alpineocean.com
Source http//oceanexplorer.noaa.gov
Source www.alpineocean.com
8Geotechnical InvestigationsIdentify Sea-bed Soil
Conditions
- Drilled boreholes
- Cone Penetrometer Test (CPT)
- Vibracoring
Source RAVE Brochure
Source www.fugro.com
9- Met Tower Installation
- Met Tower Designs
Cape Wind
Horns Rev
W.E.S.T.
10- Met Tower Installation
- Construction
Source www.mammoetvanoord.com
Source www.mammoetvanoord.com
Source www.mammoetvanoord.com
11Wave Sensor DeploymentRecord Current and Wave
Data
- Deployed in trawl-resistant bottom mount (TRBM)
- Serviced approximately every 90 days
Source RERL U-Mass
12Staging Port DevelopmentReceive and Pre-Assemble
Components
Scroby Sands, Source www.2004ewec.info
13Foundation InstallationHandling a Monopile
Source RPS Energy Presentation
14Foundation Installation Handling a Transition
Piece
Source www.Q7wind.nl
15Sub-sea Electrical Cable InstallationCable
Laying Vessel at Work
Source www.hornsrev.dk
16Offshore Substation InstallationLifting a
Transformer Platform
17Turbine InstallationAssembling a Tower and
Lifting a Bunny Ear
Source www.mammoetvanoord.com
18OM ActivitiesAccessing a Wind Turbine
19DecommissioningEnd of Project Life
- At the end of project life turbines will be
removed. - The removal sequence is roughly the reverse of
the construction sequence.
20Contact Information
- Kevin Pearce, Bluewater Wind
- kevin_at_bluewaterwind.com
- 201.850.3691
- Doug Pfeister, Bluewater Wind
- doug_at_bluewaterwind.com
- 646.431.8810
21Thank You