Title: 7 - Manufacturing Resource Planning
17 - Manufacturing Resource Planning
- Dr. Ron Tibben-Lembke
- pp. 222-234, 236-7, 240
2How do we
- System for organizing WIP releases
- Consider LT for each item
- Look at BOM to see what parts needed
- Release so they will arrive just as needed
- Example Figure 7.2
- Order quantity is 50 units
- LT is one week
- Ive added Net requirements and scheduled
releases rows to Figure for clarity
3Fig 7.2
6 units short
4Fig 7.2
Order 50 units week earlier
5Fig 7.2
Ending inventory
6Terminology
- Projected Available balance
- Not on-hand (that may be greater)
- Tells how many will be available (in ATP sense)
- Planned order releases ? scheduled receipts
- Only when material has been committed to their
production - Move to scheduled receipts as late as possible
- Preserves flexibility
7Figure 7.3 1605 Snow Shovel
1605 Snow Shovel
13122 Top Handle Assy
062 Nail (4)
048 Scoop-shaft connector
14127 Rivet (4)
314 scoop assembly
118 Shaft (wood)
8314 scoop assembly
314 scoop assembly
019 Blade (steel)
14127 Rivet (6)
2142 Scoop (aluminum)
913122 Top Handle Assembly
13122 Top Handle Assembly
11495 Welded Top handle bracket Assembly
457 Top handle (wood)
1118 Top handle Coupling (steel)
129 Top Handle Bracket (steel)
082 Nail (2)
10BOM Explosion
- Process of translating net requirements into
components part requirements - Take into account existing inventories
- Consider also scheduled receipts
11BOM Explosion Example
- Need to make 100 shovels
- We are responsible for handle assemblies.
1213122 Top Handle Assembly
13122 Top Handle Assembly
11495 Welded Top handle bracket Assembly
457 Top handle (wood)
1118 Top handle Coupling (steel)
129 Top Handle Bracket (steel)
082 Nail (2)
13Net Requirements
- Sch Gross Net
- Part Description Inv Rec Req Req
- Top handle assy 25 -- 100 75
- Top handle 22 25
- Nail (2 required) 4 50
- Bracket Assy 27 --
- Top bracket 15 --
- Top coupling 39 15
14Figure 7.5
- Sch Gross Net
- Part Description Inv Rec Req Req
- Top handle assy 25 -- 100 75
- Top handle 22 25 75 28
- Nail (2 required) 4 50 150 96
- Bracket Assy 27 -- 75 48
- Top bracket 15 --
- Top coupling 39 15
1513122 Top Handle Assembly
13122 Top Handle Assembly
11495 Welded Top handle bracket Assembly
457 Top handle (wood)
1118 Top handle Coupling (steel)
129 Top Handle Bracket (steel)
082 Nail (2)
16Figure 7.5
- Sch Gross Net
- Part Description Inv Rec Req Req
- Top handle assy 25 -- 100 75
- Top handle 22 25 75 28
- Nail (2 required) 4 50 150 96
- Bracket Assy 27 -- 75 48
- Top bracket 15 -- 48 33
- Top coupling 39 15 48 --
17Timing of Production
- This tells us how many of each we need
- Doesnt tell when to start
- Start as soon as possible?
- Dependent events (oh no, not that!)
- Front schedule Cutting approach (Fig. 7.6)
- Back schedule Fig. 7.7
18Fig 7.8 13122 Top Handle Assy
p. 233
19Fig 7.8 13122 Top Handle Assy-2
20Fig 7.8 13122 Top Handle Assy -3
21457 Top Handle
One handle for Each assembly
22457 Top Handle
23457 Top Handle
24082 Nail (2 required)
Two nails for Each assembly
25082 Nail (2 required)
26082 Nail (2 required)
27082 Nail (2 required)
2811495 Bracket Assembly
One bracket for Each assembly
2911495 Bracket Assembly
One bracket for Each assembly
3011495 Bracket Assembly
One bracket for Each assembly
3111495 Bracket Assembly
32129 Top Bracket
33129 Top handle bracket
341118 Top handle coupling
351118 Top handle coupling
361118 Top handle coupling
37Other considerations
- Safety stock if uncertainty in demand or supply
quantity - Dont let available go down to 0
- Safety LT if uncertainty in arrival time of
supply - Place order earlier than necessary
- Order quantities
- EOQ, Lot-For-Lot, Periodic Order quantity, more
to come in ch. 14
38Homework