Title: Earned Value Management EVM Basics
1Earned Value Management (EVM) Basics
2Industry EVM Definition
integrated
- Use of an management system
that coordinates - objectives and employs earned value methods for
program planning and control
work scope,
schedule,
and cost
- Industry Standard Guidelines for EVMS (Aug 8,
1996)
3Statutes Related to EVM
- Establish performance Standards for Federal budget
- Government Performance and Results Act of 1993
GPRA
- Federal Acquisition Streamlining Act of 1994 -
Title V (FASA V)
- Report cost, schedule and performance goals and
evaluate progress
- Information Technology Management Reform Act of
1996 (ITMRA / Clinger-Cohen
- Report performance information systems acquisition
4Office of Management Budget EVM Policy
- OMB Circular A-11 Part 7 Capital Programming
Guide
- Unified guidance to support OMB reporting to
Congress
Circular A-11 Policy
- Capital Programming Guide
- Agencies must establish cost, schedule and
performance goals for major acquisitions and then
achieve, on average, 90 of those goals - Version 2.0 provides guidance on integration of
EVM, IBRs, and risk management.
5DoD EVM Implementation Instructions
Purpose
Policy Instruction
- MAR 7, 2005 ATL Policy Memorandum directs
changes to DoDI 5000.2 regarding EVM
- Implements OMB Circular A-11
Table E3.T2 Regulatory Information Requirements
- Applies to cost and incentive contracts,
subcontracts, and intra-government work
agreements of 20M and above. - Formal EVMS Validation is required above 50M
- Discouraged for FFP, LOE, and TM contracts
- Optional for efforts less 20M
- Implement EVMS guidelines in American National
Standards Institute (ANSI)/Electronic Industries
Alliance (EIA) 748-A-1998 (R2002) - DoDI 5000.2 also directs when EVM required
- Use of a MIL-HDBK-881 Work Breakdown Structure
- Completion of Integrated Baseline Reviews
- Contract Performance Report (DI-MGMT-81466A)
- Integrated Master Schedule (DI-MGMT-81650)
6Increased Emphasis of EVM Within DoD
Jul 03, 2007 Use of Earned Value Management in
the Department of Defense
- Program management tool
- Best option available for effective management of
complex projects - Disciplined approach through an integrated system
- Critical pre-requisites to successful EVM
- Correctly imposing EVM requirements on contract
- Establishing realistic, executable Performance
Measurement Baselines - DoD Components will
- Flowdown requirements
- Comply with reporting requirements (CPR, IMS)
- Conduct IBRs/Surveillance
7Integrated Program Management
32 Criteria in ANSI/EIA-748
- Define the work - Assign responsibilities -
Define indirect procedures - Establish proper
management controls
- Understand contract status - Use data for
decision-making - Manage Risk
Organization
- Management Systems - Contract
Planning Scheduling Budgeting
Revisions and Data Maintenance
- Schedule all work - Authorize all work -
Time-phase the work - Develop control (or cost)
accounts
- Material costs - Unit/lot costs - Cost
Summarization
Accounting Considerations
8Integrated Management System
9Earned Value within the Contracting Process
GOVERNMENT
NEGOTIATION
SOURCE SELECTION
ACQUISITION
AWARD PROJECT
STRATEGY
STATUS
DEVELOP
REPORTS
RFP
PROVIDER
ESTABLISH
PROJECT
DEVELOP
PROJECT
EXECUTION
PROPOSAL
BASELINE
PERFORMANCE
MEASUREMENT
ASSESS RISK
TECH VOLUME
ASSIGN BUDGETS
10DoD EVM Application Thresholds
Thresholds
Contracts
Requirements
11DoDI 5000.2 EVM Policy for Cost Incentive
Contracts 50M (Interim)
- Comply with ANSI/EIA-748
- EVM system formally validated accepted by
cognizant contracting officer - DFAR clauses
- DFARS 252.242-7001 - Notice of EVMS - RFP
- DFARS 252.242-7002 EVMS RFP Contract
- EVM Data Requirements
- DI-MGMT-81466A - Contract Performance Report
All five formats mandatory - DI-MGMT-81650 Integrated Master Schedule
Limited tailoring options - Integrated Baseline Review begin within six
months of contract award
12DoDI 5000.2 EVM Policy for Cost Incentive
Contracts 20M and lt 50M (Interim)
- Comply with ANSI/EIA-748
- No formal EVM Validation
- DFAR clauses
- DFARS 252.242-7001 - Notice of EVMS - RFP
- DFARS 252.242-7002 EVMS RFP Contract
- Required SOW Statement In regards to DFARS
252.242-7001 and 252.242-7002, the contractor is
required to have an Earned Value Management
System that complies with ANSI/EIA-748 however,
the government will not formally accept the
contractors management system (no validation
review). - EVM Data Requirements
- DI-MGMT-81466A - Contract Performance Report
Formats 1 5 mandatory Format 2, 3, 4
optional - DI-MGMT-81650 Integrated Master Schedule
Flexibility exists for tailoring - Integrated Baseline Review begin within six
months of contract award
13EVMS Data Items
- Work Breakdown Structure - Mil-HDBK-881A
mandatory common WBS for CPR, IMS CCDRs through
WBS Level 3 - EVM Related Data Item Descriptions (DiDs)
- Contract Performance Report DI-MGMT-81466A
- Integrated Master Schedule DI-MGMT-81650
- Contract Work Breakdown Structure
DI-MGMT-81334B - Contract Funds Status Report DI-MGMT-81468A
- Contract Data Requirements List (CDRL) used to
put CPR and IMS reports on contract - EVM CDRLs can and should be tailored within
bounds of policy - Tailoring options are limited for contracts gt
50M - Most aspects are tailorable for contracts lt 50M
- Consider all risk factors when tailoring CPR and
IMS DiDs - Type of contract (determined by cost risk)
- Technology
- Schedule
- Past contractor performance
New CFSR DiD is pending approval Early CY 2007
14EVM Data Item Tailoring
- CPR Tailoring Guidance
- Format 1 2 Reporting Levels
- Reporting Frequency
- Submission Dates
- Date of first and last reports
- Format 5 variance reporting thresholds
- Fixed Number of Variances
- Percentage or Dollar Thresholds
- Specific Variances
- Contractor format
- Electronic data interchange format
- IMS Tailoring Guidance
- Degree of networking
- Reporting Frequency
- Submission Dates
- Date of first and last reports
- Frequency of schedule risk analysis
- Electronic data interchange format
See EVMIG (Earned Value Management Implementation
Guide), Sections 2.2.5.5 through 2.2.5.8 for
tailoring guidance
15- EVMS Training and References
16EVMS Tailored Training
- DAU can provide targeted training
- Tailored to specific organization needs
- Part of our Consulting/Performance Support
efforts - Potential Topics
- Integrated Baseline Review Workshop
- Program Startup Workshop
- EVMS Basics/Intermediate
- Scheduling Basics/Intermediate
- Source Selection
- For More Info, Contact Professor Kim Meyer
- 937-781-1040, kimberly.meyer_at_dau.mil
17 18DAU Acquisition Community Connection
https//acc.dau.mil/evm
19ACC Included References
- https//acc.dau.mil/evm
- DoD Policy
- OMB Recommended References
EVMIG
20EVMS TrainingACC EVMS CoP
21EVMS TrainingDAU Continuous Learning Modules
https//learn.dau.mil/html/clc/Clc1.jsp?cl
22 23Key EVM Inputs in the RFP Development Process
- Do you include EVM at all?
- May find EVM addressed in the RFP in
- Section C - Description/Specs/Work Statement
- Section I - General Provisions
- Section J - Exhibits/Attachments
- Section L - Instructions to Offerors
- Section M - Evaluation Factors for Award
24Section I - General Provisions
- New FAR Clauses July 2006
- FAR 52.234-2 Notice of EVMS Pre-Award IBR
- FAR 52-234-3 Notice of EVMS Post Award IBR
- FAR 52-234-4 EVMS The Gov will conduct an IBR
if a pre-award IBR has not been conducted. - FAR EVM clauses not tied to dollar thresholds
- DoD Interim guidance (until new DFARS approved)
- Apply existing clauses (252.242-7001 and
252.242-7002) directly on contracts gt 50M - Include the following paragraph in statement of
work for contracts gt 20M but lt 50M - In regards to DFARS 252.242-7001 and
252.242-7002, the contractor is required to have
an Earned Value Management System that complies
with ANSI/EIA-748 however, the government will
not formally accept the contractors management
system (no compliance review). - DoD Policy EVM DFAR clauses are equivalent to
the EVM FAR clauses and only the EVM DFAR clauses
will be used on DoD contract
25Section L - Instructions to Offerors
- Guidance to bidders for the assembly of their
proposals - Each offerors proposal shall include a
description of the EVMS to be used in accordance
with the appropriate RFP DFAR clauses - Compliance with Validation requires
- Reference to an Advance Agreement and a copy of
the approved EVM system description or - A plan to obtain EVM validation to include how
the system will be validated. - Compliance Only requires a written summary of
the proposed EVMS reference in sufficient detail
to show how it addresses all ANSI/EIA-748
guidelines
26Section M - Evaluation Factors for Award
- Evaluation of the proposed EVMS is normally
undertaken as part of the proposal evaluation
process to determine the probability of the
system meeting the guidelines. - For Existing Systems - evaluation may consist of
a confirmation that the referenced validation is
accurate and current. The system should be
currently in use, and surveillance should not
have identified significant, uncorrected
problems. - For EVMS (without validation) - the EVM system
description should be evaluated for completeness
against the guidelines in ANSI/EIA-748. - An on-site examination of a proposed EVMS should
not normally be required during proposal
evaluation. But if deficiencies are identified,
written communications or an on-site visit may be
required when approved by the Source Selection
Board and Procuring Activity. - DCMA should be requested to provide insight
regarding EVMS capability, quality, and past
performance.
27Work Breakdown Structure---CPR Format 1
- Gives contract type pricing arrangements
- Provides schedule and cost performance by WBS
- product -services-data
- Top contract level to lower detailed levels
- Contractor Budget EAC by WBS
- Cost of Money
- General Administrative (G A)
- Undistributed Budget (UB)
- Management Reserve (MR)
28(No Transcript)
29Functional Categories---CPR Format 2
- Gives same contract, cost of money, GA, UB, MR
and contract total budget LRE info - Costs are broken out by contractors functional
organization (Vs. WBS) - Provides schedule and cost performance status by
organizational element where is problem
occurring, e.g., - Engineering
- Manufacturing
- Subcontracts
- Best place to look at subcontract status
- Useful to compare with man-loading status of
Format 4
30(No Transcript)
31 Baseline---CPR Format 3
- Gives summary contract cost change history
- Gives summary contract schedule dates
- Gives contract budget plan
- total to date
- amount this month
- the remaining budget by month for 6 months as
government specified to contract completion - at the beginning then the end of the month
- Important to note changes
- number, amount and location
- during month, next 6 months and far term
- Used to indicate ability to meet schedule plan
32(No Transcript)
33Manpower Loading/Staffing---CPR Format 4
- Uses same Format 2 functional organization
reporting elements except for subcontracts. - Uses same Format 3 reporting time periods
- Facilitates comparison of cost schedule plan
performance with manpower loading plan
performance - Useful for identifying manpower hiring shortfalls
and growth - Useful for projection for manpower requirements
34(No Transcript)
35Problem Analysis/Explanations---CPR Format 5
- Gives contractors summary contract status
- Gives explanation of variances
- Where
- How much
- What happened
- The solution
- Impact
- schedule
- cost
- technical
- Other analysis
- Over Target Baseline (OTB)
36(No Transcript)
37Earned Value Management (EVM) Basics