FAA Project - Bidding Phase FAA Recommends.. - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

FAA Project - Bidding Phase FAA Recommends..

Description:

Verify the status of the bidders DBE contractors ... Contractor's DBE participation forms ... FAA, NDA, the Sponsor, the Consultant and Contractor all get one copy of. ... – PowerPoint PPT presentation

Number of Views:17
Avg rating:3.0/5.0
Slides: 10
Provided by: Aerona6
Learn more at: https://dot.nebraska.gov
Category:

less

Transcript and Presenter's Notes

Title: FAA Project - Bidding Phase FAA Recommends..


1
FAA Project - Bidding Phase FAA Recommends..
  • Consider how you would like to bid the project
    early on in the design.
  • Due to possible budget constraints identify some
    components as separate bid items.
  • If AIP funds are not sufficient to cover the
    entire project, a bid item could be deleted.

2
FAA also recommends...
  • A pre-bid meeting, if the complexity of the
    project warrants it.
  • FAA and NDA will let you know if they feel a
    pre-bid meeting is required.

3
Advertisement is required
  • FAA recommends
  • For larger projects 2 - 4 weeks
  • usually 3 weeks
  • For smaller projects 1 - 2 weeks
  • Just to be safe, we recommend at least 3 weeks.
    Comply with any local requirements as well.

4
Your project is ready to bid when...
  • FAA Civil Rights has approved the DBE Program and
    goal.
  • FAA Engineering Section has approved the plans
    and specifications. This approval usually takes 3
    submittals.

5
What you and your Consultant need to check at
bid opening
  • Check the bids for reasonableness of cost
  • Check the bid for improprieties and unbalanced
    bid items
  • Verify the status of the bidders DBE contractors

6
What you and your consultant need to submit to
FAA/NDA
  • Bid tabulations corrected for any discrepancies
  • Contractors DBE participation forms
  • A tentative award of contract letter, (contingent
    on FAA approval).

7
Just so you know, if only one bid is received...
  • FAA must notify the office of the Inspector
    General.
  • This could slow the project down
  • or
  • The bid could be thrown out
  • It is not likely that a bid will be thrown out

8
Once FAA approves the bids, and the DBE..
  • The Consultant prepares the contract documents.
  • He/she sends the contracts to the contractor for
    his/her signature.
  • Then the sponsor signs the contracts and a
    Sponsor Certification, NDA will provide the
    Sponsor Certification form.

9
Then everyone gets a copy!
  • FAA, NDA, the Sponsor, the Consultant and
    Contractor all get one copy of..,
  • The signed contract documents which include
    contractors proposal, bonds, insurance and
    project specifications (all bound into a booklet
    by the consultant)
  • FAA, NDA and the Sponsor get a copy of the
    Sponsor Certification.
Write a Comment
User Comments (0)
About PowerShow.com