Welcome IMAC Members ! - PowerPoint PPT Presentation

1 / 44
About This Presentation
Title:

Welcome IMAC Members !

Description:

Review designs and prototypes. Monitor quality and progress in factories ... Cool down of Magnet. Performance & Stability. Field mapping. Under construction ... – PowerPoint PPT presentation

Number of Views:143
Avg rating:3.0/5.0
Slides: 45
Provided by: chen179
Category:

less

Transcript and Presenter's Notes

Title: Welcome IMAC Members !


1
Welcome IMAC Members !
2
Report to IMAC Hesheng Chen
  • Progress of BEPCII Accelerator
  • Status of BESIII
  • Summary

3
BEPC running ended July 4 2005
  • SR running finished at 20 June 20, 2005
  • SR running 3009 hour.
  • 362 experiments, 1087 users
  • 1751 hours for test beam slow e source
  • Machine studies
  • high beam current,
  • e injection,
  • transverse feedback,
  • BPM,
  • response matrix,

4
BEPC running finished July 4, 2005
5
Milestones in the shutdown
  • Pre-alignment of half units started 17 May 2005
  • Remove old ring July 4 Aug. 5, 2005v
  • Survey network in tunnel for magnet alignment
    Aug. 6 Sept. 5, 2005 v
  • Decoration tunnel Aug. 25 Sept. 22, 2005v
  • Transformer Electricity upgrade, new water
    pipes, cabling Sept. 23, 2005 Mar. 2, 2006
    v.
  • Installation of two rings started 2 March,
  • 30 units installed until today.

6
Delays in delivery and installation of some key
devices
  • SCQ
  • delivery delayed about 6 month
  • Installation more delay
  • SCQ Valve boxes
  • delivery delayed about 4 month
  • more delay installation
  • Power Leads valve boxes of BESIII SC magnet.
  • Antechamber depressed

7
Progress of Linac
  • Tuning Phase I
  • e available at the end of Linac March 19, 2005
  • e reached 63mA _at_ 1.3GeV June 1, 2005
  • e- reaches 1.89 Gev e 1.55 GeV June 17,2005
  • Repetition rate 12.5Hz ?25Hz ? 50Hz
  • Shutdown July 4, 2005 Feb. 28, 2006
  • Phase control system installed
  • Microwave system improved
  • Vacuum system improved
  • Stability of Linac and beam
  • Tuning Phase II March 1 July 30, 2006

8
Linac commissioning (April-06)
Parameters Parameters Goal Measured
Beam energy (GeV) Beam energy (GeV) 1.89 1.89 (e-) 1.89 (e)
Beam current (mA) e 40 63
Beam current (mA) e- 500 gt 500
Repetition rate (Hz) Repetition rate (Hz) 50 25-50
Emittance (1s) ( mm?m rad ) e 0.53 0.32 0.20
Emittance (1s) ( mm?m rad ) e- 0.067 0.080 0.096
Energy spread () e ? 0.50 ?0.73_at_1.30GeV (?0.50_at_1.89Gev)
Energy spread () e- ? 0.50 lt ?0.80_at_1.30GeV lt (?0.55_at_1.89Gev)
9
Linac Tunnel and Klystron Gallery
10
Progress of Storage Ring
  • Mass production of most components finished
  • 2 superconducting RF cavities,
  • 2 RF power sources (250kW),
  • 2 superconducting quards,
  • 49 dipoles, 89 quadrupoles,
  • special magnets in IR,
  • 300 power suppliers of magnets,
  • 4 sets of injection magnet system,
  • 80 antechambers.
  • Instrumentations of beam diagnostics and control
    in good progress.
  • In progress
  • the vacuum chambers of straight sections,
  • photon absorber
  • movable mask

11
Progress of Storage Ring
  • Critical path
  • superconducting IR magnet,
  • pre-alignment
  • cryogenic system/SC devices integrating.
  • Most of the hardware are in the stage of
    installation, testing and commissioning.
  • Installation of pre-aligned magnet unit (B,Q,S
    with one girder) into the tunnel started March 2.
    30 units installed

12
Simulation of installation
13
Installation of half unit (15-17.5 tone) by air
beds
14
(No Transcript)
15
Challenges
IMAC May 2005
  • Cryogenics system critical path
  • Linde compressors and cryogenics arrived
  • Gas tanks, He gas pipes, N pipes done
  • critical path valve box, system tuning
  • SC devices critical path
  • SC Magnets production _at_BNL small delay
  • SC cavities arrived IHEP last week.
  • BESIII SC magnet winding to be finished in 10
    days. Assembling / testing? reach the
    specifications ?
  • Uncertainty in system tuning
  • Field mapping

16
IMAC report (May, 205)
  • There are apparent discrepancies between the
    schedule used by the project office and the one
    used by the group leaders.
  • The completion of the cryogenic system can not be
    accurately predicted due to the delivery of
    connection box from HIST and completion of
    transfer lines. So far, there is about 3 months
    delay.
  • The delivery of vacuum chamber and the Ti-N
    coating also encountered possible delay of about
    3 months and with no effective plan of recovery.
  • Commissioning of all three SC components, SCQ,
    SRF, SSM also will be delayed by more than 3
    months caused by the delay of completion of the
    cryogenic system. More experienced manpower is
    needed to complete the design and installation of
    the cryogenic transfer lines and smooth start up
    of the cryogenic system.
  • The time allowed for combined field measurement
    with SCQ and SSM in place appears too tight.

17
Difficulties
  • The teams of cryogenics system and SC devices
    are limited and shortage of experiences. However,
    Many helps from experts of DESY and KEK, the
    teams are shaping.
  • Poor performance of HIT Inst. of SCC delay, bad
    cooperation and poor management
  • BESIII SC magnet Wang NMR Co. in some troubles
  • We could handle other problems, such as
    mechanics, control, electronics

18
Spare Scheme of IR
  • Delay uncertainties of IR devices commissioning
  • SCQ Valve boxes later arrival and delay in
    installation
  • BESIII SC magnet
  • Possible further delay in installation,
    commissioning and filed mapping
  • A spare scheme of the IR lattice configuration
    without SCQ is designed and under preparation .
  • Two normal conducting bending magnets (70B) will
    replace the two SCQ IR magnets.
  • With this scheme, the outer ring (SR), the
    electron ring and positron ring can be
    commissioned.
  • The spare scheme is to save the time of about 3
    months for the SCQ field measurement with
    detector solenoid and the field mapping of the
    detector solenoid itself.

19
Quality Control
  • Quality control system established
  • Quality control manuals
  • Quality control forms
  • Quality controller
  • Review designs and prototypes
  • Monitor quality and progress in factories
  • Most of cases are successful, while some cases
    have problems in quality and schedule for various
    reasons.
  • In case of problem, quality is the first.
  • Over design happens some times.

20
BEPCII Summary Schedule
21
Linac Plan and Installation of Ring
22
Schedule
  • 9 Oct. 2006
  • Installation of two rings
  • Tuning and commissioning of devices and systems,
    including SCQ commissioning and field mapping
  • Alignment
  • Oct. 06 - July. 07
  • Tuning of machine SR running
  • Field mapping of SCQ BESIII SC magnet
  • BESIII assembling and tuning
  • Aug. 07 BESIII detector moved into beam line
  • Sept. 07 Starting machine-detector tuning.
  • Data taking by Autumn 2007

23
The BESIII Detector
SC magnet
Magnet yoke
TOF
Be beam pipe
MDC

CsI calorimeter
24
Draft Chamber Structure
25
(No Transcript)
26
Wiring of Draft chamber
27
MDC inner part outer part
28
Wire Tension Distribution
29
MDC electronics
  • 160 channel prototype system
  • comics ray test and test beam
  • 512 channel system final version
  • Oct. 2005 intl. review
  • Mass production under way

30
CsI crystal Calorimeter
France Sanit -Gobain Shanghai Institute of Ceramics Beijing Hamamatsu Total
Order 2040(3000) 1920 1320 5280(6240)
Arrived 1727 1920 1220 4860
Rejected 43? 7240? 20 70240?
31
Calorimeter electronics
  • FE under production
  • 3 beam test and and 384 channel prototype reach
    the performance. Noise 1000 e/crystal ?
  • Intl. review
  • On schedule

32
Installation of RPC into endcap
33
(No Transcript)
34
Mass production ---- Module test
Test result of an endcap module after install
Test result of a barrel module
35
BESIII Magnet Progress
????
??
??
??
??
36
(No Transcript)
37
  • Valve box of BESIII SC magnet
  • Power leads thermal leakage

38
(No Transcript)
39
BESIII work to be done
  • Challenge BESIII SC magnet
  • Power Leads
  • Test of Valve box
  • Cool down of Magnet
  • Performance Stability
  • Field mapping
  • Under construction
  • Structure of ECAL endcap
  • Assembling of subdetectors
  • Assembling BESIII
  • Tuning
  • Cosmic ray test

40
Cryogenics system
41
Gas tanks and pipes
42
TCF50s passed assessment
?? 150L/h 500W_at_4.5K
???? 14bar,78g/s
???????
43
Cryogenics pipes made in IHEP
???????
???????
??G10???
8??????
44
Summary
  • LINAC tuning goes smoothly with good progress.
  • Manufacture of most of components of Storage
    rings and detector goes well. Some delays and
    technical difficulties in SC components.
  • So far, no fundamental problem found in the
    machine and the detector.
  • We are in a difficult period with many problems
    in quality and schedule. Great challenges in
    next 18 month.
  • About 4 month delay in schedule so far.
  • Thank you for helps from IMAC and many Labs
Write a Comment
User Comments (0)
About PowerShow.com