Transcript and Presenter's Notes

Title: FSMAIRPORT IMPROVEMENT PROJECT UPDATES


1
FSMAIRPORT IMPROVEMENT PROJECT UPDATES
  • 2008 PACIFIC AVIATION DIRECTORS WORKSHOP

Presented by Massy Halbert
Garapan, Saipan March 31, 2008
2
FSM-AIP PROJECTS
  • Project Contractor CM
  • Yap Apron - GPPC, Inc. - LAD
  • Yap ARFF - Penta-Ocean - GMP
  • Pohnpei Runway - Penta Ocean - GMP
  • Pohnpei ARFF - Penta Ocean - GMP
  • Kosrae ARFF - Black Micro - GMP
  • Chuuk ARFF - China Jiangsu - GMP

3
YAP APRON REHABILITATION
  • Project started on 18 February 2008
  • Contract Cost is 10,298,000.00
  • Expected to be completed by 20-Aug-09
  • Contractor is GPPC, Inc. with CM Leo A. Daly

4
YAP ARFF
  • Contract with Penta-Ocean Const. approved
    amounting to 5,909,000.00
  • Contract and Bonds will be submitted to FAA
    shortly for concurrence and issuance of NTP
  • Construction expected to commence by
  • mid April 2008
  • Target completion date is April 2009
  • The CM for this project is GMP Hawaii, Inc.

5
POHNPEI RUNWAY ARFF
  • Construction contract agreement is currently
    being processed for approval at FSM Finance
  • Pre-const meeting was held on 28-Mar-08 and
    expected to start construction by mid April 2008
  • The scope of work for Runway rehabilitation has
    been revised and divided into 3 Phases due to
    funding shortage
  • The ARFF costs 12,150,000.00
  • Phase 1 of the Runway costs 22,788,000.00
  • Contract duration for ARFF is 365 cal. days
    while the Pohnpei Runway is 610 cal. days

6
POHNPEI RUNWAY ARFF
7
POHNPEI RUNWAY
8
POHNPEI RUNWAY
9
CHUUK ARFF
  • The project costs 4,899,901.52
  • Contract agreement with China Jiangsu is
    currently with FSM Finance
  • Pre-construction meeting was held on February 26,
    2008
  • Anticipated to start construction within this
    month of April with 365 calendar days contract
    duration

10
KOSRAE ARFF
  • Construction officially started on February 22,
    2008
  • Contractor is Black Micro Corp. with CM GMP
    Hawaii, Inc.
  • Contract costs 5,788,000.00 with a duration of
    365 calendar days
  • Scheduled completion date is February 20, 2009

11
EQUIPMENT FOR DOI FUNDING
  • Proposed list of airport equipment for each State
    has been forwarded to DOI for review
  • Submission of FSM request to DOI has been delayed
    as we encountered difficulties in getting price
    quotation from suppliers
  • Formal request will be submitted to DOI together
    with the required supporting documents as soon as
    the DOI confirmed that the equipment being
    requested is qualified for funding

12
CHALLENGES
  • C1. Lack of interested Bidders during the
    procurement stage of the project
  • C2. Difficulties in the availability, shipment
    and cost of major construction materials
  • C3. Compliance with Buy American Requirement
  • C4. Contract Management
  • C5. FAA bonding requirement
  • C6. Timely approval of Contract Agreement
  • C7. Timely payment of Invoices
  • C8. Unmanageable Consultant

13
RESOLUTION TO CHALLENGES
  • R1. Use of Sole Source Procurement Process as
    approved by the FAA
  • R2. Pre-construction meeting at earlier stage to
    identify potential sources and suppliers
  • R3. FAA waiver for Buy American Requirement
    provided the Contractor could submit proof of
    unavailability of materials
  • R4. Regular coordination between FAA, FSM
    National State Government, Consultant and
    Contractor
  • R5. Imposition of Retention Money in lieu of
    Payment Bond
  • R6. Sufficient funding, completeness of
    supporting documents and constant follow-up
  • R7. Sufficient funds, proper drawdown scheduling,
    record keeping of project funds
  • R8. Selection of manageable and responsible
    Consultant

14
YAP TERMINAL REHABILITATION
  • Completed on 20 Sept. 2007 amounting to
    2,063,811.00

15
YAP TERMINAL REHABILITATION
16
YAP APRON GROUNDBREAKING February 21, 2008
17
YAP APRON GROUNDBREAKING February 21, 2008
18
CHUUK ARFF PRE-CONSTRUCTION MEETING February
26,2008
19
CHUUK ARFF PRE-CONSTRUCTION MEETING February
26,2008
20
KOSRAE ARFF GROUND BREAKING February 28,2008
21
KOSRAE ARFF GROUND BREAKING February 28,2008
22
KOSRAE ARFF GROUND BREAKING February 28,2008
23
One of a Kind Temporary Shelter for Firefighting
Vehicles
24
ONLY IN YAP !
25
THANK YOU !