Title: Engineering Economic Analysis Canadian Edition
1Engineering Economic AnalysisCanadian Edition
- Chapter 9 Other Analysis Techniques
2Chapter 9. . .
- develops and uses future worth, benefit-cost
ratio, payback period, and sensitivity analysis
methods to solve engineering economic problems. - links the use of the future worth method to the
present worth and annual worth methods. - uses spreadsheets to perform sensitivity and
breakeven analyses.
3Present and Future WorthMethods
- Present Worth (PW)
- What is the present situation of future action?
- Project cash flows are converted to an equivalent
value (usually) now (see Chapter 5). - Future Worth (FW)
- What is the future situation of action now?
- Project cash flows are converted to a future
value (usually at the end of a projects life).
4Future Worth
Find the value of the cash flows at the end of
the 5th year if the rate of interest is 10
compounded annually?
5Economic Criteria
- Projects are judged against an economic
criterion.
6Economic Criteria Restated Future Worth
Techniques
7Type of Projects
- Independent
- The selection of a project is independent of the
decision to undertake or not any other project or
projects. - Mutually exclusive
- At most one project (including the status quo
option) can be selected amongst competing
alternatives.
8- Contingent (dependent)
- The selection of a project is dependent on the
selection of at least one other project.
9Problem Find FW (i10)
- FW 1,000(F/P,10,7)
- 2,000(F/P,10,6)
- 3,000(F/P,10,5)
- 2,500(F/P,10,4)
- 2,000(F/P,10,3)
- 1,500(F/P,10,2)
- 1,000(F/P,10,1)
- 500(F/P,10,0)
- FW 25,940
10FW and Independent Projects
- Select all projects with non-negative FW.
- if FW 0, accept project
- if FW FW lt 0, reject project
- if FW 0, accept project
- If all projects have a FW lt 0, select the
status quo option (invest available funds at
the prevailing (current) interest rate. - The selection of independent projects is usually
constrained by a capital budget (limited funds).
11FW and Mutually ExclusiveProjects
- The FW method (as with PW) requires that a common
period of analysis be used to determine the
best alternative. - Incorrect to compare the FW of one-week and
two-week car rentals without making period of
analysis adjustments
12Future Worth Analysis
- Future Worth Analysis answers the question
- What will the future situation be if we take a
particular course of action now? - FW P(F/P,i,n)
- FW A(F/A,i,n)
Example 9.1
13- When constructing a building, the issue is not
the dollars out of pocket,but the invested cost
at start-up.
Example 9-2
14Future and Present Worth Analysis
15- NPW (A)
- -2500 - 900(P/A,10,5) 1800(P/A,10,5)
- 200(P/F,10,5)
- 1,036
- NFW (A)
- -2500(F/P,10,5) - 900(F/A,10,5)
- 1800(F/A,10,5) 200
- 1,668
16- NPW (B)
- -3500 - 700(P/A,10,5) 1900(P/A,10,5)
- 350(P/F,10,5)
- 1,266
- NFW (B)
- -3500(F/P,10,5) - 700(F/A,10,5)
- 1900(F/A,10,5) 350
- 2,039
17- NPW (C)
- -5000 - 1000(P/A,10,5) - 100(P/G,10,5)
- (2100/(0.1-0.15))1-(1.15/1.1)5
- 977
- NFW (C)
- -5000(F/P,10,5) - 1000(F/A,10,5)
- 100(F/G,10,5) (2100/(0.1-0.15))1-
- (1.15/1.1)5(F/P,10,5)
- 1,573
18Useful Lives ? Analysis Period
- Project A has a 3-year life
- Project B has a 4-year life
- Both projects are valid
- because their Net Future
- Worth (NFW) gt 0 (i10)
- Which project is better?
19- Because projects A and B have different lives,
the FW criterion requires that they beevaluated
over a common period of analysis (12 years). - Hence, project A will be repeated 3 times (after
theinitial investment at t0) and project B
twice.
20- NFWA (12 years) 2,092.92
- NFWB(12 years) 1,476.55
- Decision Select project A
21Benefit-Cost Ratio
- An alternative is acceptable at a given MARR
provided - PW (Benefits) PW (Costs) 0
- FW (Benefits) FW (Costs) 0
- EUAB EUAC 0
- Can be restated as the benefit-cost ratio (B/C)
- B/C PW (Benefits)/PW(Costs) EUAB/EUAC
22Benefit-Cost Ratio Analysis
- If the PW of benefits - PW of costs ³ 0
- The alternative is considered acceptable.
- Restated
- Benefit-cost ratio B/C PW of benefit/PW of cost
³ 1. - Fixed input, maximize B/C.
23Example 9-3
24Economic Criteria Restated Benefit-Cost Method
25B/C and ?B/?C Ratios
- The B/C ratio and other methods such NPW, NFW,
EUAW, and IRR) lead to the same conclusion as to
the acceptability of projects - Better mutually exclusive project (2 projects)
- Best competing alternative (3 projects)
26Benefit-Cost Ratio Analysis
- If the EUAB - EUAC ³ 0
- The alternative is considered acceptable.
- Restated
- Benefit-cost ratio B/C EUAB/EUAC ³ 1
- Neither input or output fixed - use incremental
B/C.
27Example 9-4
28B/C Ratios and Competing Alternatives
- Moose County has three alternative plans for a
new road. Benefits and costs are shown below.
Expected road life is 50 years and MARR 10.
29- Based on the information on the previous slide,
find - B/C ratios
- acceptable projects
- the best project
30- Project A
- (B/C) 700 1,500 / 25,000(A/P,10,50)
- 200 / (3,200 / 2,721.5)
- 1.18 gt 1
- Project A is acceptable.
31- Project B
- (B/C) 1,000 1,800 / 35,000 (A/P,10,
- 50) 250
- (3,800 / 3,780.1)
- 1.01 gt 1
- Project B is acceptable.
32- Project C
- (B/C) 1,450 2,400 / 50,000(A/P,10,
- 50) 350
- (6,050 / 5,393)
- 1.12 gt 1
- Project C is acceptable.
33- Incremental B/C Ratios
- Compare A and B
- ?B/?C (3,800 3,200)/(3,780.1 2,721.5)
- 2,850/2,671.5
- 0.57 lt 1
- A is better.
34- Compare A and C
- ?B/?C (6,050 3,200)/(5,393 2,721.5)
- 2,850/2,671.5
- 1.07 gt 1
-
- C is better. In fact, Project C is best.
35Important Points about Payback Period
- 1. Approximate economic analysis method.
- 2. Prior to payback the effect of timing is
ignored. - 3. After payback all economic consequences are
ignored. - 4. Will not necessarily produce a recommended
alternative consistent with equivalent worth and
rate of return methods.
36Payback Characteristics
- Exclusive focus on liquidity (no concern for
profitability). - Liquidity how quickly can the investment (P) be
recovered from the projects cash flows? - All other methods of project evaluation (e.g.,
single sums) focus on profitability (not
liquidity) - Usually based on before-tax calculations
37- No time value discounting i.e., the effective
MARR 0 - A project balance has NO opportunity cost.
- Project Balance P - ?(ORi OCi), i 0, 1 .N
38Project Balance
- A projects balance at any point during the life
of a project is - For simple payback a projects un-recovered
investment (P). - Discounted payback a projects un-recovered
investment (P) the annual opportunity cost
(i.e., interest charges) of the un-recovered
investment.
39- Generally, net annual revenues (revenues less
costs) will cause a projects balance to decrease
over time. - A project balance is negative until the initial
investment has been fully recovered. - Our interest is limited to negative project
balances.
40The unrecovered investment at any point during
project life
41Liquidity Focus
- Projects A and B have the same five-year recovery
period (i.e., project balance is zero after five
years). - However, they have very different profitability
profiles (with Project A being more profitable
than Project B). - Since this method focuses ONLY on liquidity (how
fast can I recover my initial investment), you
would be indifferent between projects A and B.
42(No Transcript)
43Simple Payback(Irregular Cash Flow)
- Recovery period 3 300/(300700) 3.3 years
- Compare 3.3 years to industry threshold to
determine if project is acceptable. - If similar investments require, on average, 3
years to recover, this project would be rejected
(3.3 years gt standard)
44Payback Period
- The payback period is the period of time required
for the profit or other benefits of an investment
to equal the cost of the investment. - How many years are required to get the money back
in the following examples?
45Example 9-6
Example 9-7
46Payback Analysis
- What is wrong here?
- Payback and IRR analysis do not agree.
- With alternative A we get ourmoney back in 4
years but never make a return on the
investment. - With alternative B we get ourmoney back in 5
years and make a return on the investment of
19.
Example 9-8
47- How should we make a decision?
- Liquidity vs. profitability
- Life of project
48Discounted Payback
49- Recovery period
- 9 years 2410.6/(2410.6227.8)
- 9.91 years
- If the industry average recovery period for this
type of project is 8 years, this project is not
acceptable.
50Discounted Payback Project Balance
51Sensitivity and Break-evenAnalysis
- Economic data represent projections of
expenditures and returns. - These projections ultimately affect our
decisions. - To more fully consider our choice of a decision,
we should play a what if game to determine the
amount of change in a data point that might
change the decision.
52Projected and Actual Cash Flows may Differ
- Technological change
- changes to production costs
- Changes in the size and number of competing firms
- Introduction of new products
- substitutes or complements
53- Changes to key macroeconomic variables
- e.g., inflation, unemployment, economic growth,
exchange rate - International events
54Breakeven Analysis
Example 9-9
55Sensitivity Analysis
Example 9-10
56- This problem was solved by copying the original
NPW setup twice and then solving for the minimum
and maximum values of the Initial cost of
alternative B that would not change the decision
to select B. - Try and find the sensitivity of the EUAB that
would not change the decision to select B. - Remember to first reset the Initial cost of B to
4,000 or you will have two variables changing
and not know what is really happening.
57Sensitivity of PW to changes in project parameters
58- The sensitivity of NPW is
- Highest to changes in annual revenues (AOR)
- Smallest to changes in salvage value (SV)