DELAY AND DISRUPTION A FINANCIAL PERSPECTIVE Phillip M' Kohn - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

DELAY AND DISRUPTION A FINANCIAL PERSPECTIVE Phillip M' Kohn

Description:

... measurement systems that are compatible with normal program management techniques. ... POTENTIAL WARNING SIGNS. Internal Challenges ... – PowerPoint PPT presentation

Number of Views:65
Avg rating:3.0/5.0
Slides: 31
Provided by: pko1
Category:

less

Transcript and Presenter's Notes

Title: DELAY AND DISRUPTION A FINANCIAL PERSPECTIVE Phillip M' Kohn


1
  • DELAY AND DISRUPTIONA FINANCIAL
    PERSPECTIVEPhillip M. Kohn

2
DELAY AND DISRUPTIONA FINANCIAL
PERSPECTIVEPhillip M. Kohn
3
OVERVIEW
  • Essential elements of a DD claim
  • Delay costs
  • Disruption costs
  • Schedule issues
  • Warning signs
  • Key factors of a successful resolution

4
ESSENTIAL ELEMENTS
  • Entitlement A legal basis for recovery
  • Quantum - Identify and measure costs associated
    with the actions giving rise to the claim
  • Causation - Demonstrate linkage, cause and
    effect, between the entitlement and the costs.
  • All three elements must exist for the contractor
    to effectively and successfully recover increased
    performance costs.

5
ENTITLEMENT
  • Directed Changes
  • Is there agreement on the scope of direction?
  • Has the total impact been priced?
  • Constructive Changes
  • Any customer caused change in the scope of work
    should be identified.
  • Changes in work sequence and changes in the
    distribution of manpower are common.
  • Disrupted In-Scope Labor
  • Lost Productivity and reduced efficiency
    frequently occur.
  • Diversion of key resources can effect timely
    performance.

6
QUANTUM
  • Schedule Delay Costs (Time driven)
  • Labor Escalation
  • Material Escalation
  • Sustaining Personnel
  • Unabsorbed or extended overhead
  • Acceleration Costs
  • Overtime
  • Material expediting
  • Disruption Costs (Process driven)
  • Decreased Productivity
  • Postponement of anticipated process improvements

7
DELAY
  • Common methods of estimating schedule delay.
  • Impacts of delay.
  • The cost and schedule baseline.

8
DELAY
  • Common Methods Of Estimating Delay
  • Critical Path Method (CPM)
  • For most major programs this is already done and
    is the most common method. However, it often
    poorly structured at the outset and when
    periodically provided to the customer could be a
    obstacle to recovery.
  • Time interval analysis
  • Analyze fixed time intervals and determine what
    was accomplished. This is a more simple approach
    but less flexible.
  • Milestone analysis
  • Similar to time intervals but with a focus on
    accomplishments such as CDR, PDR or first
    production unit.
  • Line of Balance - Best suited for those projects
    that are composed of activities of a linear and
    repetitive nature.

9
DELAY
  • Impacts Of Delay
  • Labor Escalation
  • Material Escalation
  • Sustaining Personnel
  • Unabsorbed Overhead
  • Acceleration Costs
  • Overtime
  • Material expediting
  • Loss of learning, particularly when work is
    suspended

10
DELAY
  • The Cost And Schedule Baseline
  • Establishing a supportable baseline is the
    foundation of quantum methodology. What extra
    costs can be recovered are measured from this
    point.
  • The baseline is the amount of time and money that
    should have been required to perform the work
    as-planned. Not just in duration but also in
    sequence and skill level.
  • Common evidence used to support the baseline
    include the original bid, BAFO documents and
    pre-delay EACs.
  • Baseline adjustments are often needed to allow
    for negotiated adjustments or management
    challenges.

11
THE EICHLEAY FORMULA
  • Benefits Most common method accepted by BCA.
  • Drawbacks Yields poor results if work has not
    really started or is substantially complete.
  • Eichleay Corp., ASBCA No. 5183, 60-2 BCA par.
    2688 61-1 BCA par. 2894

12
DISRUPTION
  • The increased costs to perform in-scope work.
  • Impacts are often subtle, have unexpected
    results, and are seldom immediately apparent.
  • Single most common error in recovery of
    disruption costs is the failure to establish a
    causal linkage between events and the resulting
    impacts.

13
DISRUPTION
  • Common Causes
  • Work re-sequencing.
  • Software or hardware upgrades.
  • Diversion of engineers from planned activities.
  • Late GFE or GFI.
  • Diversion of test resources.
  • Diversion of supervisory or management personnel
    to deal with directed changes.
  • Incremental changes to the design baseline.
  • Excessive inspection and/or slow approval by
    customer.
  • Subcontractor issues.
  • Anything that alters the as-planned work.

14
DISRUPTION
Production Flow
Materials Components
Assembly
Test
Inspection
Acceptance
Rework
Rework
Rework
Rework
15
QUANTIFYING DISRUPTION
  • No single correct approach to measuring
    disruption.
  • Its best to work within existing performance
    measurement systems that are compatible with
    normal program management techniques.
  • Examples
  • Learning curve analysis
  • Machine hours per unit
  • Average days in production cycle
  • Lines of software code per man-week
  • Apply an objective methodology when allocating
    disruption costs to customer causes.
  • Look to non-impacted performance periods when
    possible.
  • Document and explain the actual and planned
    workflow.
  • Using Discrete Cost Accounts
  • For complex problems they are of limited use.
  • As a prerequisite people must know they are
    affected.

16
QUANTIFYING DISRUPTION
  • Information Commonly Used In Support Of
    Disruption Claims
  • Operating plans
  • Work authorization documents
  • Program evaluations
  • Statement of work
  • Production records including the support for
    standard rates and factors
  • Cost accounting records

17
SCHEDULE ISSUES
  • The Cost And Schedule Baseline
  • Defined - The amount of time and money that
    should have been required for performance as
    planned.
  • Essential characteristics - supportable and
    credible.
  • Sources - original bid, BAFO, and estimates made
    prior to significant changes.
  • Adjustments to the performance baseline to allow
    for compensated changes.
  • Final baseline must reconcile to contract award.

18
SCHEDULE ISSUES
  • Concurrent delay
  • The most common reason contractors do not prevail
    on delay claims.
  • The most common defense raised by the customer.
  • Sometimes a benefit. You cant get them but they
    cant get you.
  • Formal versus informal recognition of delay.
  • Contractors are generally required to provide
    some form of schedule information to the
    customer.
  • There is a strong tendency to avoid recognition
    of schedule slip by the contractor. This can
    limit cost recovery later on.

19
POTENTIAL WARNING SIGNS
  • Customer
  • Has customer taken a heightened interest in
    performance?
  • Extra plant visits?
  • Unscheduled status reviews?
  • Has there been a heightened level of contractual
    correspondence?
  • Has the customer started pointing out your
    deficiencies?
  • Are design, schedule or cost concessions being
    requested?
  • Is there decreased access to the buyer/user?

20
POTENTIAL WARNING SIGNS
  • Internal Challenges
  • What contracts are potentially outside your
    companies known area of expertise?
  • What contracts were priced using large blanket
    reductions in the proposal phase? Were multiple
    BAFOs requested?
  • Are scrap rates higher than planned?
  • Have testing standards or quality control become
    more stringent?
  • Are there widely divergent opinions on program
    status?

21
POTENTIAL WARNING SIGNS
  • Design And Build Changes
  • Is the change rate higher than anticipated?
  • Are there any problems with change control or
    configuration management?
  • Does the type of change indicate that program
    maturity is lacking or engineering concepts are
    poor?
  • Are changes being incorporated in a timely
    fashion?

22
POTENTIAL WARNING SIGNS
  • Estimates To Complete
  • Does the ETC assume performance that is markedly
    better than historical indicators?
  • Is the program slipping milestones but not the
    end date?
  • Are percent complete measurements based on
    percent of budget consumed?

23
SUCCESSFUL RESOLUTION
  • Key Factors
  • Recognition of contractor caused problems. Fault
    rarely lies solely with either the customer or
    the contractor.
  • Understanding what has already been communicated
    to the customer either formally or informally.
  • Isolate why overruns occurred - rates,
    inefficiency, subcontractor issues
  • Describe the important relationships among
    performing organizations and how the were
    affected by the changes.
  • Document with real examples supported by real
    data.
  • Anticipate customer defenses.
  • Timely gathering of evidence.

24
SUCCESSFUL RESOLUTION
  • Common Pitfalls In Estimating Damages
  • Estimators not knowing what happened during
    contract negotiations.
  • Leaving too much damage as indirect.
  • Not completely understanding the original plan.
  • Waiting too long to recognize a change has
    occurred.
  • Underestimating future impacts.
  • Contractor failing to recognize the importance of
    concurrent delays.
  • Communicating conflicting schedule information to
    the customer.
  • Pricing delay as if it occurred at the end of the
    project.
  • Failure to account for possible damage due to
    cost escalation.
  • Failure to account for both primary and secondary
    impacts, the ripple effect.

25
SUCCESSFUL RESOLUTION
  • Requirements Generally Needed to Prevail
  • Establish the difference between the program
    as-planned and as-performed. This may be
    needed at both a system and sub-system level and
    should include all functions areas.
  • Describe in detail the timing and nature of the
    out-of-scope work that caused in-scope work to be
    delay and/or disrupted.
  • Identify on an anecdotal basis what disruptions
    would be expected from the out-of-scope work.
  • Gather and summarize supporting documentation
    that verifies the anecdotal story.

26
SUCCESSFUL RESOLUTION
  • Typical Customer Responses
  • The claim is an attempt to recover from under
    bidding.
  • The disputed work was covered under the original
    terms of the contract.
  • The contractor failed to provide adequate notice
    that a change occurred.
  • The contractors facts are incorrect.
  • Even though GFI/GFE was provided late it was
    before the contractor really needed it.
  • The user community merely was making suggestions
    not formal changes from the customer.

27
SUCCESSFUL RESOLUTION
  • What To Expect From The DCAA
  • Primary focus on pricing as opposed to
    entitlement.
  • Requests for detailed support of damages that are
    traceable back to the program cost records.
  • Requests for the individual names of people who
    performed extra work.
  • High level of interest in labor and overhead
    rates.
  • Identification of contractor caused cost
    overruns.

28
FINAL THOUGHTS
  • Watch and learn from your customer. What has
    happened in the past will probably happen again.
  • Promptly notify the customer of changes.
  • Your company has an integrated work environment.
    Be aware of multiple impacts.
  • Price changes in a timely fashion. The causes of
    action blur over time.
  • Problem contracts only get worse if neglected.

29
QUOTE OF THE DAY
  • To know where to find the information and how to
    use it That is the secret of success.
  • Albert Einstein

30
THANK YOU
  • Questions
  • Comments
  • More Information or a presentation copy
  • phillip.kohn_at_mossadams.com
Write a Comment
User Comments (0)
About PowerShow.com