Title: MOUNTAIN VIEW POWER,INC Boise Planning
1MOUNTAIN VIEW POWER,INC Boise Planning Zoning
Commission
- Bob Looper, P.E.MVP PresidentRon Williams,
J.D.MVP VP/General Counsel
2MVP Proposal Summary
- Build small, yet efficient and clean burning
natural gas fired peaking power plants to be
located in the East Boise - Gateway Industrial
Park - Phase 1 A single 172 MW combustion turbine
unit, fired during peak generation periods using
clean burning natural gas - Phase 2 Up to 100 MW of Natural Gas Fired Power
to facilitate additional Wind Generation
facilities in Idaho
3- Treasure Valley Population
- Growth Projections
4Idaho Power Energy Surplus/Deficiency
5Idaho Power Summer Peak Loads
6Typical Summer Peak Day
7Gateway Power Plant Phase I
8Bennett Mt. 1
EAST BOISE GATEWAY POWER PLANT
9Bennett Mt. 2
EAST BOISE GATEWAY POWER PLANT
10Bennett Mt. 3
EAST BOISE GATEWAY POWER PLANT
11Bennett Mt. 4
EAST BOISE GATEWAY POWER PLANT
12Bennett Mt 5
EAST BOISE GATEWAY POWER PLANT
13Gateway Industrial Park Siting Fundamentals
- Gateway Industrial Park is well situated away
from residential development and adjacent to I-84
corridor, existing industry and Gowen Field - The Gateway Power Plant is located in the Boise
load center adjacent to Boise Bench Substation,
the largest station which serves the Treasure
Valley - MVP Proposal is classified as a Minor Source for
air emissions and requires permitting by IDEQ in
compliance with EPA Air Quality Act. Dominant
wind patterns from the West are away from
population centers.
14Gateway Power Plant Site North View
15Gateway Power Plant Site North View
16Gateway Power Plant Site South View
17Gateway Power Plant Site Transmission
18Gateway Power Plant Site - Looking South
19Gateway Power Plant Site Looking North
20Gateway Power Plant Site -- Attributes
- Industrially zoned property on undeveloped land
- Bennett Mtn. Plant as template with proven
performanceLow Noise EmissionsLow Air
EmissionsLow Visual Impact - Intermountain Gas 12 line within 2,000 feet of
site - Idaho Power 230 kV transmission line on site
- United Water 24 main water line within 2,000
feet of site
Mountain View Power, Inc.
21Gateway Power Plant Air/Noise Emissions
Mountain View Power, Inc.
- Emissions from Gateway are less than existing
surrounding uses at Gowen Field, Micron, I-84
corridor - Noise emitted from Bennett Mtn. facility was 52
dB at 400 ft. from plant - Emissions from Bennett Mtn. performed better than
maximum requirements with 1 ppm Carbon Monoxide
at full load, 20 ppm Nitrous Oxides
22(No Transcript)
23(No Transcript)
24Pollution Estimates
25GATEWAY SITE MVP Site Specifics
- New lateral to Interconnect with United Water for
fire and potable water supply - New lateral to City Sewer
- New Gas lateral to existing 12 Intermountain Gas
Pipeline
- No pre-existing environmental/hazardous issues
identified with Site Existing Conditions - Soil conditions will support conventional
foundations - ACHD Requirements for road paving to Site Parcel
from Eisenman Road
26PHASE II - PROJECT FEATURES
- Phase II to firm proposed wind generation in
Idaho - Every 1 MW of wind capacity needs 1 MW of a
firm generating resource behind it - A wind resource firmed with a gas fired peaking
resource can defer the need for future generation
such as coal fired plants
27BASE PROJECT SCHEDULE
- CUP Process 3 months
- IDEQ Air Permit 6-12 months
- Electrical Interconnection Study 6 months
- Electrical Facility Study 4-6 months
- Natural Gas Interconnection 12-18 months
- Project Design Phase 6 months
- Project Construction 12 months
28PROJECT SUMMARY
- Project will provide firm, reliable source of
peaking power to meet future growth requirements
for the Boise load center - Phase 1 Project completion possible within 18
months of issuance of regulatory permits - Proposal represents the best available technology
with the cleanest emissions in the region - MVP is a local company with a successful track
record and current experience
29PROJECT SUMMARY
- Project Cost estimated at 75-100 million for
Phase 1 and Phase 2 - Project serves as anchor tenant for future
development in the Gateway Industrial Park - Direct economic benefits to City of Boise include
ground lease payments and property taxes.
30Tons of Annual Emissions Near Gateway
31Tons of Annual Emissions in Treasure Valley