System Modelling and Simulation - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

System Modelling and Simulation

Description:

Modelling and Simulation in the Lifecycle. Investigation of ... learned from ATV. Reuse was feasible ... helped to address large parts of the problem ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 18
Provided by: joachi4
Category:

less

Transcript and Presenter's Notes

Title: System Modelling and Simulation


1
System Modelling and Simulation
  • Joachim.Fuchs_at_esa.int
  • Juan.Miro_at_esa.int
  • Software Systems Division
  • System Software and Synthesis Department
  • Technical and Quality Management Directorate

2
Presentation Outline
  • Modelling and Simulation in the project
    life-cycle
  • Enabling factors
  • Specific examples
  • Functional Engineering Simulator
  • SVF
  • AIT / EGSE
  • Harmonisation activities / Standardisation
  • Future The Virtual Spacecraft Design
  • Conclusions

3
Modelling and Simulation in the Lifecycle
4
Main successes
  • Verifying system feasibility and performance
  • Allowing design trades during system (re)design
  • Refining operability (including human-in-the-loop
    systems)
  • Demonstrating capability otherwise impossible to
    show
  • Early demonstration and testing before hardware
    is available (e.g. OBSW testing)
  • Avoidance of building hardware prototypes
  • (Sub-)System Verification and Training

5
Main challenges today
  • Integration within the system engineering (SE)
    process
  • Shorten development time to effectively support
    the space system design iterations
  • Linkage with system engineering data to configure
    the simulation and allow simulation results to
    feed-back into the System Engineering process
  • Integration of engineering models (e.g.
    thermo-structural models)
  • Increasing reuse of models between programmes
  • Distributed development of models by
    subcontractors and delivery to primes (requires
    model exchange and interoperability standards)

6
Enabling Factors
  • Clear separation between
  • Run-time infrastructure (kernel)
  • Models
  • Modelling environment
  • Reuse
  • Of models
  • Of architectures
  • For both
  • Along the life-cycle
  • Between projects
  • Standardisation of
  • Process
  • Architectures
  • Interfaces
  • Building blocks / components

7
The Functional Engineering Simulator
  • Support to early design, concept definitions,
    possibly to be used in a concurrent design
    environment by adding dynamic component to
    approaches like Concurrent Design Facility (CDF)
    and therefore contribute to the
  • Support to mission trades and verification of the
    mission concept
  • Verification of functional spacecraft design
  • Support to system trade-off analysis
  • Verification of the baseline Mission and
    Spacecraft Design
  • Mission performance by end-to-end system
    simulators
  • Enables preparation of the user community
  • Supports the System Engineering function in
    assessing system-level trade-offs

8
Functional Architecture
Generic simulator architecture
Model breakdown used in SimVis
9
Supporting tool SimVis
  • quick (days!) and flexible set-up for new
    missions
  • a growing level of detail from mission to S/C
    design

Microsoft Excel
Workbook
Project Wizard
OpenIGS
Simulation
Visualisation
Run-Time Environment
Designer
Output Data
Data Processor
10
Simulation to support Software Validation
  • Software is very close to the system functions
    and has therefore a key position in the overall
    design process.
  • Validation of the on-board software needs to be
    performed in a context that is representative of
    the satellite system in space and with ground
    interfaces.
  • The simulation represents the spacecraft hardware
    and its dynamic behaviour in space. Models
    integrated in the SVF have a high level of
    commonality with those used in the System Test
    Bench (in term of scope, functionality and
    performance).

11
Different configurations of a SVF
SW only configuration
HW configuration
12
AIT / EGSE
Simulation Infrastructure
Test Supervisor
EnvironmentModels
Spacecraft DynamicsModels
Missing Spacecraft Equipment Models
Interfaces Subject of harmonisation
Ground Models
Front-End Equipment / SCOE
Spacecraft Equipment
e.g. SCOS 2000, CGS,
MDB
13
Re-use / Lessons learned from ATV
  • Reuse was feasible
  • Operational simulator was used to produce
    environment for a SVT-Lite
  • Original HW centered solution presented problems
    of context saving
  • SW / emulator solution helped to address large
    parts of the problem
  • Synergies between simulation facilities are
    possible, BUT if not planned properly at the
    beginning, they are difficult to implement
    technically and contractually

14
Harmonisation / standardisation activities
  • European Harmonisation
  • Ground segment SW
  • Aspect relevant for simulation is the definition
    of common interfaces between EGSE and Simulator
    components, to allow consistent operation / test
    supervisor interfaces
  • Enabling conditions for tool diversity
  • System Design and Verification Tools Modelling
    and Simulation
  • Process started to harmonise future investments
    in the area of infrastructure / tools
  • Separation between simulation kernels and
    modelling tools
  • Requires definition of common interfaces
  • Standardisation
  • Simulation Portability Standard (SMP2)
  • System Modelling and Simulation (ECSS E10 part
    13)
  • Engineering Database (ECSS E10 part 9)
  • Mathematical and Analytical models (ECSS E10 part
    14)

15
Evolution of simulation in the life-cycle
16
The Future Virtual Spacecraft Design?
  • Process definition improvements being defined, to
    create virtual spacecraft to support full project
    life-cycle
  • Enlarge to mechanical domain (thermal /
    structural digital models)
  • Allow virtual (E and M) AIT/AIV
  • Enable full system design validation before
    hardware is being produced
  • Have potential impact on model philosophy
  • Start of these activities in phase B, but reuse /
    continuation in later phases
  • TRP study
  • Process definition
  • Environment prototyping
  • Demonstration with pilot project

17
Conclusion
  • The use and benefit of simulation is well
    recognised in the different areas of a space
    project
  • Within a project, there are still many instances
    of simulators being developed for the different
    facilities with limited coordination and reuse
  • Reuse is still hampered by lack of methodology
    and standards
  • involvement of different parties (prime / sub,
    customer / supplier)
  • differing requirements to the infrastructure
    (e.g. functional vs. R/T)
  • Standardisation of architectures, interfaces and
    databases should allow to address this problems
  • The concept of a virtual system design (already
    used in other domains such as aerospace) should
    allow to increase the quality and efficiency of
    the process
Write a Comment
User Comments (0)
About PowerShow.com