Title: MPUMALANGA PROVINCIAL GOVERMENT
1MPUMALANGA PROVINCIAL GOVERMENT
- CONDITIONAL GRANT REPORT FOR THIRD QUARTER ENDING
31 DECEMBER 2005
2CONDITIONAL GRANT REPORT THIRD QUARTER ENDING
31 DECEMBER 2005
- FOCUS ON THE FOLLOWING
- DATA TRENDS IN ALLOCATIONS, TRANSFERS AND ACTUAL
EXPENDITURE OF CONDITIONAL GRANTS, CAPITAL AND
INFRASTRUCTURE EXPENDITURE - ASSESSMENT OF DEPARTMENTS CAPACITY TO MONITOR
(CONSTRAINTS) AND AN INDICATION OF STATUS OF
EXEPENDITURE. - MECHANISMS TO DEAL WITH CHALLENGES OUTCOMES
OFTHESE MECHANISM - RECEIPT OF MONTHLY REPORTS.
- CERTIFIED BUSINESS PLANS FOR CONDITIONAL GRANTS
- SERVICE LEVEL AGREEMENTS
3CONDITIONAL GRANT REPORT THIRD QUARTER ENDING
31 DECEMBER 2005
- ANALYSIS INDICATE THAT
- ACTUAL EXPENDITURE, IN SOME CATEGORIES, IS
USUALLY HIGHER THAN THE AMOUNTS TRANSFERRED, BY
NATIONAL GOVERNMENT, AS CONDITIONAL GRANTS. - THERE IS AN IMPROVEMENT IN OVERALL PERFORMANCE ON
CONDITIONAL GRANTS DURING THIRD QUARTER ENDING 31
DECEMBER 2005 - DEPARTMENTS ARE HAVE STARTED STRENGTHENING THEIR
CAPACITIES TO MONITORING. - EXECUTIVE COUNCIL REVIEWS PERFORMANCE ON
CONDITIONAL GRANTS AND ISSUE INSTRUCTIONS TO
DEPRTMENTS TO IMPLEMENT CORRECTIVE MEASURES. - DEPARTMENTS HAVE INDICATED THAT POOR PERFORMING
GRANTS WILL DRASTICALLY PICK UP IN THE FOURTH
QUARTER AND THOSE THAT DEMONSTRATE A LIKELIHOOD
OF OVERSPENDING WILL BE CONTAINED WITHIN THE
ALLOCATED BUDGETS. - .
- DEPARTMENTS SUBMIT MONTHLY REPORTS ON CONDITIONAL
GRANTS AND INFRASTRUCTURE AND NONSUBMISSION
RESULTS IN TRANSFERS BEING WITHHELD. - THE TOTAL AMOUNT FOR CONDITIONAL GRANTS IS R5,087
BILLION (INCLUDING ROLLOVERS) AND AN AMOUNT OF
R3,328 BILLION HAS BEEN SPENT BY THE 31ST OF
DECEMBER 2005. THIS ACCOUNTS FOR 65 OF THE
TOTAL AMOUNT OF R5,087 BILLION. -
4CONDITIONAL GRANT REPORT THIRD QUARTER ENDING
31 DECEMBER 2005
- BUSINESS PLANS
- ALL CERTIFIED BUSINESS PLANS FOR CONDITIONAL
GRANTS WERE SUBMITTED TO NATIONAL TREASURY. - IMPLEMENTATION OF THE PROJECTS AS OUTLINED IN THE
BUSINESS PLANS REMAINS A CHALLENGE TO THE
PROVINCE
5CONDITIONAL GRANT REPORT THIRD QUARTER ENDING
31 DECEMBER 2005
- SERVICE LEVEL AGREEMENTS
- PUBLIC WORKS DEPARTMENT ASSISTS DEPARTMENTS OF
HEALTH AND EDUCATION IN MANAGING THEIR
INFRASTRUCTURE PROJECTS. - TWO SERVICE LEVEL AGREEMENTS SIGNED AMONGST
DEPARTMENTS, ON MANAGEMENT OF INFRSTRUCTURE
PROJECTS - BETWEEN DEPARTMENTS OF HEALTH AND PUBLIC WORKS.
- BETWEEN DEPARTMENTS OF EDUCATION AND PUBLIC
WORKS.
6CONDITINAL GRANT REPORT THIRD QUARTER ENDING 31
DECCEMBER 2005
- HEALTH CONDITIONAL GRANTS
TOTAL AVAILABLE 2005/2006 PERCENTAGE SPENT
R000
Comprehensive HIV AIDS Grant 90,632 63.7
Hospital Management and Quality Improvement Grant 18,582 73.9
Hospital Revitalisation Grant 93,082 49.4
Integrated Nutrition Programme Grant 11,139 71.6
Health Professions Training Development Grant 54,363 79.3
National Tertiary Services Grant 44,225 89.4
Provincial Infrastructure 55,005 73.9
Forensic Pathology Services 3,534 3.0
7CONDITIONAL GRANTS REPORT THIRD QUARTER ENDING
31 DECEMBER 2005
- HEALTH CONDITIONAL GRANTS (CONTINUED)
- Only two categories of the conditional grants
spent more than 75 of their allocations within
the 9 months of the financial year, i.e. Health
Professions Training Development and National
Tertiary Services. - Forensic Pathology Services has spent 3 of the
available amount. This so because the allocation
was only done during the adjustment budget, and
the expenditure will without any doubt pick up
the fourth quarter. - Comprehensive HIV/AIDS is in line with National
Transfer Schedule. - Hospital Management Quality Improvement Grant
is slightly below target. This resulted from
delays in delivery of e-health system. However,
all other projects under this category are on
target. - Hospital Revitalisation Grants under-spending
resulted from appointed contractors inability to
submit guarantees and their failure to commence
with projects in time hence failure to meet time
lines. - Integrated Nutrition Programmes spending was
affected by delays in crockery delivery to
hospitals. - Health Professions Training Development is
higher than what was received from national
government. Spending trends are monitored to
ensure that total spending is within allocated
budget. - National Tertiary Services Grant is also in the
similar position as Health Professions Training
Development. - Provincial Infrastructure Grants expenditure is
at acceptable target of 75. The Department
expects to have exhausted the allocated funds
(reached a 100 ) by the end of the 2005/2006
financial year.
8CONDITIONAL GRANT REPOERT THIRD QUARTER ENDING
31 DECEMBER 2005
- SOCIAL SERVICES CONDITIONAL GRANT
TOTAL AVAILABLE 2005/2006 PERCENTAGE SPENT
R000
HIV AIDS (Community Based Care) Grant 21,412 74.9
Social Assistance Administration Grant 246,139 50.2
Social Assistance Transfers Grant 3,609,491 70.7
Integrated Social Development Services Grant 38,954 80.2
9CONDITIONAL GRANT REPORT THIRD QUARTER ENDING
31 DECEMBER 2005
- SOCIAL SERVICES CONDITIONAL GRANT (CONTINUED)
- The under expenditure on Social Assistance
Administration grant results from delays in
appointment of staff and that effect has a direct
impact on expenditure for compensation of
employees and expenditure on goods and services. - Expenditure on Social Assistance Transfer grant
is slightly below target. Strict monitoring and
adherence to business plan will hopefully assist
in detecting what the reasons may be for this
trend.
10CONDITIONAL GRANT REPORT THIRD QUARTER ENDING
31 DECEMBER 2005
- EDUCATION CONDITIONAL GRANTS
- There had been challenges for the Department of
Education to comply with conditions of the
infrastructure grant that lasted up end of the
third quarter, resulting in National Treasury
withholding funds. These funds will be
transferred during the fourth quarter.
TOTAL AVAILABLE 2005/2006 PERCENTAGE SPENT
R000
HIV AIDS (Life Skills Education) Grant 10,317 78.7
National School Nutrition Programme Grant 86,947 68.9
Infrastructure Grant 185,659 19.0
11CONDITIONAL GRANT REPORT THIRD QUARTER ENDING
31 DECEMBER 2005
- LOCAL GOVERNMENT HOUSING CONDITIONAL GRANTS
- The slightly below target expenditure for
Integrated Housing Human Settlement Grant
resulted from teething problems with contractors.
The effects of corrective measures are starting
to be apparent.
TOTAL AVAILABLE 2005/2006 PERCENTAGE SPENT
R000
Integrated Housing Human Settlement Grant 312,157 65
Human Settlement Redevelopment Grant 9,123 72
Municipal Support Grant 254 100
12CONDITIONAL GRANT REPORT THIRD QUARTER ENDING
31 DECEMBER 2005
- AGRICULTURE LAND ADMINISTRATION CONDITIONAL
GRANT -
- Land Care Programmes expenditure are higher and
a stricter monitoring and control will be
necessary to ensure that it remains within
allocated amounts.
TOTAL AVAILABLE 2005/2006 PERCENTAGE SPENT
R000
Land Care Programme Grant Poverty Relief infrastructure Development 7,790 89.6
Comprehensive Agriculture Support Programme Grant 26,120 63.0
Agriculture Disaster Management Grant 17,000 15.1
Provincial Infrastructure Grant 18,566 54.9
13CONDITIONAL GRANTS REPORT THIRD QUARTER ENDING
31 DECEMBER 2005
- ROADS TRANSPORT CONDITIONAL GRANTS
- The allocated budget has already been exhausted
(100). The 2 overspending resulted from
misallocation of expenditure between conditional
grants projects and equitable share projects.
This misallocation error will be rectified before
end January 2006.
TOTAL AVAILABLE 2005/2006 PERCENTAGE SPENT
R000
Infrastructure Grant 114,213 102.0
14CONDITIONAL GRANT REPORT THIRD QUARTER ENDING
2005
- CULTURE, SPORT AND RECREATION CONDITIONAL GRANT
- The slight below target expenditure resulted from
stipends for volunteers not paid in time for
December 2005, and other activities that slowed
down in the same month.
TOTAL AVAILABLE 2005/2006 PERCENTAGE SPENT
R000
Mass Sport and Recreation Participation programme Grant 3,180 69.8
15CONDITIONAL GRANT REPORT - THIRD QUARTER ENDING
31 DECEMBER 2005
- CAPITAL BUDGET
- Department of Health was allocated R265,398M
towards payment of capital assets. R184,196M,
representing 69.4, has already been spent. - Department of Education was allocated R342,078M
towards payment for capital assets. R115,517M,
representing 33.8, has already been spent. - Department of Public Works is managing all
infrastructure projects for both Departments of
Education and Health. - CONCLUSION
-
- The Select Committee on Finance is hereby
requested to note this report on conditional
grants and capital expenditure for third quarter
ending 31 December 2005.