Title: INTERNAL SRCEATMP WORSHOP
1INTERNAL SRC-EATMP WORSHOP
2Supporting the national Safety Regulatory
Interface
National ANSPs
Inputs/co-ordination
EATMP Programmes (RVSM, 8.33, LINK 2000 ..)
Request for approval Submission of national
Safety Argument
Final approval
National ATM Safety Regulator
3Added Value of the SRC-EATMP Interface
- Duplication of efforts avoided
- Best use of scarce safety resources
- Consistency of safety regulatory approvals
- Cross fertilisation in Europe
- Support to national regulatory interfaces
- European Implementation-Total System Approach-
Regional Network
4SRC-EATMP Process (1)
- SRC DOC 6-Harmonised Interface
- Structure to organise the
- different aspects to be addressed
-
- Top-level definition of EATMP inputs
- and SRC outputs
-
- The same review cycle for all kinds
- of safety deliverables
- Review always based on the same 9 steps
5SRC-EATMP Process (2)Inputs - Outputs
- EATMP inputs into the process
- Safety Policy/Safety Plan
- Safety Deliverable
- SRC outputs from the process
6SRC-EATMP Process (3)Successive Review Cycles
INTERFACE PROCESS
7SRC-EATMP Process (4)Successive Review Cycles
8Lessons Learned from experience
- When to start ?
- When does SRC need to be involved?
- Practical and harmonised arrangements?
- EATMP procedures
- SRU/SRC procedures
- Scope of EATMP-SRC activities?
- Recommendation to PC?
9Initiation and update of safety arguments must
be undertaken according to the stages of life
cycle
Safety Argument collects evidence that safety
is maintained during all stages of life cycle
RD (Feasibility) Planning Design
Implementation Integration
Transfer to Operation Operations and
Maintenance Decommissioning
10But to which extent does this have to be done by
the SRC ...
PROJECT
EATMP PROJECT
REQUIREMENTS DETERMINATION
DESIGN AND DEVELOPMENT
INSTALLATION AND TRANSITION
REQUIREMENTS DETERMINATION
DESIGN AND DEVELOPMENT
INSTALLATION AND TRANSITION
OPERATION
OPERATION
RISK ASSESSMENT AND MITIGATION ACTIVITIES
RISK ASSESSMENT AND MITIGATION ACTIVITIES
RISK ASSESSMENT AND MITIGATION DOCUMENTATION
SAFETY ARGUMENT and related DOCUMENTATION
Risk Assessment and Mitigation Deliverables
Risk Assessment and Mitigation Deliverables
Risk Assessment and Mitigation Deliverables
Risk Assessment and Mitigation Deliverables
Risk Assessment and Mitigation Deliverables
Risk Assessment and Mitigation Deliverables
Safety Policy Safety Plan
PC
REVIEW OF THE RISK ASSESSMENT AND MITIGATION
DOCUMENTATION
REVIEW OF THE SAFETY ARGUMENT and
SAFETY ASSESSMENT DOCUMENTATION
ACCEPTANCE
SRC VIEW
11Impact Assessment to prioritise SRC/SRU
activities (level of oversight activities, SRC
working arrangements)
- This depend on several factors, such as ...
- GEOGRAPHICAL SCOPE
- RD or Operational PROGRAMME
- OPS or TECHNOLOGY DRIVEN
- ANTICIPATED SAFETY IMPACT OF THE CHANGE
(Initial FHA) - THE COMPLEXITY OF THE CHANGE
- PREVIOUS EXPERIENCE
- ...and ANTICIPATED IMPLEMENTATION SCHEDULE
12Practical Arrangements (1)
- Early Involvement of SQS
- Early Contact EATMP/SRU
- Initial Impact Assessment
- Way forward (SRU Focal Point, SRC WG or via
correspondence, ) - Presentation to SRC and inclusion in SRC Work
Programme
13Practical Arrangements (2)
- Programme Safety Policy/Plan
- scope of the programme (operations, environment,
European core safety tasks) - safety regulatory baseline (ESARRs, ICAO..)
(What) - proposed acceptable means of compliance (How)
- set of Programme safety objectives to be met
- a safety management approach
- rationale/assumptions for proposals (Why)
- set-up the generic Programme safety
responsibilities and accountabilities - Schedule (When) Resources (Who)
14Practical Arrangements (3)
- Programme Safety Documentation
- description of the associated safety activities
conducted in accordance to the Safety Plan - summary of conclusions on the achievement of
safety objectives as result of the safety
activities, as well as the identification of
actions to be taken in the light of safety
activities - presentation of evidence, argument, findings and
assumptions - identifies the safety issues, and their
resolution or implications - A listing of documents specifically referenced in
the safety deliverable.
15Practical Arrangements (4)
- Initiation of RAD early in Project
- Involvement of EATMP Project
- Criteria solely derived from applicable ESARRs
- Submission of Safety deliverables
- Initial review by SRU Formal review by SRC
(CRD-with origin to programme) - Order of magnitude- From 1,5 to 3 months
required - Configuration control/status
- Revision marks
- Overall consistency of Safety Deliverables
- Good visibility of processes and outputs
16Scope of EATMP-SRC Interface (1)
- EATMP minimum role-
- To ensure new operational concept in assumed
environment will be safe if implemented as per
Safety Objectives Requirements - Determination of Safety Objectives
- Determination of Safety Requirements
- Safety Requirements validated (i.e., a priori
feasible effective) - SRC minimum role-
- To verify that proposed operational concept in
assumed environment will be safe if implemented
as per Safety Objectives Requirements - To provide an SRC view on acceptability of
concept to PC
17Scope of EATMP-SRC Interface (2)
- EATMP complementary role-
- To collect assurance from ANSP that complementary
national implementation verification done - To complete validation of allocated SO/SR (a
posteriori feasible and effective) - To ensure national variations have been
addressed - To verify regional implementation is according
to allocated SO/SR (e.g., RVSM) - through ANSP assurance
- when required throught end to end verification
- SRC complementary role-
- To collect assurance from national (and European)
regulators that national implementation has been
verified as meeting allocated SO/SR - To provide an SRC view on acceptability of
implementation to PC
18Scope of EATMP-SRC Interface (3)
EATMP
STAKEHOLDERS
OPERATIONS ENVIRONMENT
IMPLEMENTATION OF ALLOCATED SAFETY REQUIREMENTS
FHA RESULTS SAFETY OBJECTIVES
OUTPUTS
PSSA RESULTS SAFETY REQUIREMENTS
VERIFICATION THAT ALLOCATED SAFETY REQUIREMENTS
ARE MET
SAFETY EVIDENCE
VALIDATION of SR Feasible Effective
STATEMENTS
DATA COLLECTION AND MONITORING
ALLOCATION OF SAFETY REQUIREMENTS
ONGOING SAFETY ANALYSIS
VERIFICATION SAFETY OBJ. ARE MET
19SRC Recommendation to PC (1)
- Circulated to all PC members and observers
- To be used in go/no go/delay decision
- To be used by ICAO, JAA etc..in their own
activities - To be used by national ATM regulators in national
regulatory approval processes
20SRC Recommendation to PC (2)
- Contents-
- Conclusions
- Recommendations
- Format-
- PC Action Paper
- Status-
- EUROCONTROL PC distribution list
21Conclusions
- Both EATMP and SRC have a role to play to support
States- - Increased awareness
- Core European activities
- (no duplication/inconsistency)
- Learning from past experience can help us work
more efficiently- - Harmonised SRU working Procedures
- Initiatives to improve awareness