INDEPENDENT POWER 2001 SALES - PowerPoint PPT Presentation

About This Presentation
Title:

INDEPENDENT POWER 2001 SALES

Description:

... limits on single-phase generator hookup and capacity to avoid imbalance, ... Optional scoping meeting up front. Three main components. Feasibility study ... – PowerPoint PPT presentation

Number of Views:15
Avg rating:3.0/5.0
Slides: 37
Provided by: admi1929
Category:
Tags: independent | power | sales | hook | up

less

Transcript and Presenter's Notes

Title: INDEPENDENT POWER 2001 SALES


1
Massachusetts DTE DG Interconnection
Collaborative DG Cluster Proposal November
12, 2002
2
What Is An Interconnect (Nomenclature)?
  • Basically, the interface between Distributed
    Generation (DG) equipment and the grid, called
    the Area Electrical Power System (EPS)

Point of Common Coupling (PCC)
Radial
EPS
Customer Facility
Network
Load 3
Load 2
Load 1
DG
3
DG Cluster Proposal Overview
  • Standardized Process and Requirements
  • Ensure safety and reliability
  • Follows national standards
  • Equipment must be certified or undergoes design
    review
  • For small generation lt20MW
  • Differentiating By
  • One of three generator size thresholds
  • Potential impact of generator on Electric Power
    System (EPS)
  • Type of EPS at Point Of Common Coupling (PCC)

4
Process Overview
Generator Application
gt20MW?
Yes
  • Scope of process shrinks considerably when
    expedited
  • Defines screens for certified equipment

gt2MW?
Historic Application Process
Yes
Meets Screens?
Expedited Application Process
Yes
Super Expedited Application Process
Interconnect Agreement
5
Size Threshold Categories
  • Less than 10kW
  • Accepts utility proposal
  • Three page application/agreement
  • No review/payments necessary
  • Less than 2 MW eligible for super-expedited
    process
  • Certified equipment
  • De minimis grid impact
  • No connection to transmission lines
  • 2-20MW eligible for expedited process
  • Check for distribution and transmission impact

6
10 kW To 2 MW
  • Units certified by UL or other NRTL against
    UL1741 (representing IEEE Std1547 Draft 10)
  • 2 screens for determination of no grid impact
  • Primary screen conservative, utility origin
  • 100 of units that pass are OK
  • Secondary screen - less conservative
  • 80-99 of units are OK?
  • Creates presumption of acceptance

7
Certification
  • Verifies that equipment is designed to ensure
    electrical protection safety
  • Website registry
  • UL or similar NRTL describes equipment package
    and test results
  • Posted w/ 6 week comment period
  • UL responds to any comments
  • Once certified -- no type testing and no other
    equipment can be required
  • Already UL-approved equipment is grandfathered

8
IEEE Std1547
  • Overview
  • References
  • Definitions and Acronymns
  • Technical Specs and Requirements
  • General Requirements
  • Response to Area EPS Abnormal Conditions
  • Power Quality
  • Islanding
  • Test Specifications and Requirements
  • Interconnection Test
  • Production Tests
  • Interconnection Installation Evaluation
  • Commissioning Tests
  • Periodic Interconnection Tests
  • Annexes (Informative)
  • Flicker Information
  • Interconnection Tests
  • Commissioning Tests
  • Bibliography

9
Overall Super-ExpeditedProcess Flow
SG Submits Complete Application
IP Conducts Initial Review
To Expedited Process
Passes Primary Screens?
Passes Secondary Screens?
IP Conducts Supplemental Review (If SG Agrees)
Meeting To Discuss Initial Review
No
No
No
Yes
Yes
SG Initiates
If Needed, IP SG Agree To Mods?
IP Conducts Limited IC Review
Technical Dispute Resolution
Yes
If Needed, IP SG Agree To Minor Mods?
No (IP Initiates)
Interconnect Agreement
Yes
Note SG is Small Generator IP is
Interconnection Provider
10
Basis For Screens
  • Circuit size versus DG size
  • DG contribution to fault
  • Short circuit interrupting capability limit
  • Three-wire and four-wire circuit criteria
  • Nameplate limits
  • Circuit impact
  • Fault handling, fuse desensitizing nuisance
    trip
  • Short circuit handling
  • Proper connection
  • Single phase imbalance

11
Screens Primary
  • Aggregate DG capacity limited to a low percentage
    of the peak load of a distribution circuit
    (different limits for radial vs spot network vs
    secondary grid network)
  • DG contribution to circuit fault current is
    limited
  • DG not allowed to cause grid protective devices
    to exceed 90 of their short circuit interrupting
    capability
  • In aggregate, DG cannot be gt 10MW where transient
    stability limits posted
  • Interconnection configuration-specific limits on
    single-phase generator hookup and capacity to
    avoid imbalance, overload, and possible
    neutral/grounding problems

12
Screens Secondary
  • Aggregate DG capacity limited to a higher
    percentage of the peak load of the distribution
    circuit
  • Basically the same limits on fault current
    contribution and short circuit interrupting
    impact as primary screen

13
10kW-2MW Costs
  • Application fee
  • Additional surcharge for interconnection review
  • Limited to reasonable amounts based on size
  • No other costs for interconnection under Super
    Expedited procedures

14
Dispute Resolution
  • Elements
  • Technical Master
  • Hotline
  • ADR for non-technical disputes
  • IP must initiate if SG Applicant clears secondary
    screen
  • Gen Applicant has burden if both screens failed

15
Metering
  • Only metering required for this agreement is that
    necessary to implement the interconnection

16
Timing
  • 10 days to review application
  • 15 days to review screens
  • 5 days to execute IA (Interconnect Agreement)
  • If Primary Screen failed
  • 10 days for additional review (after surcharge is
    paid)
  • 5 days to notify applicant of results
  • 5 days to send IA

17
Interconnection Agreement
  • Standard form Agreement
  • Shorter form for generators lt2MW
  • Can be pre-executed

18
Interconnection Application
  • Standard form
  • Shorter Form for generators lt2MW

19
2-20MW Interconnection
  • Includes transmission impact issues
  • Direct transmission interconnection as well as
    distribution
  • Used by all generator sizes for which lt2MW
    procedures do not apply

20
Basic Process
  • Optional scoping meeting up front
  • Three main components
  • Feasibility study
  • Impact study (if needed)
  • Facilities study (if needed)
  • Patterned after Utility proposal

21
Feasibility Study
  • Checks to see if generator has an impact
    distribution or transmission system
  • load flow (unless no export)
  • short circuit
  • grounding
  • IP shall rely to extent practical on existing
    studies
  • Gives generator developer idea of interconnection
    costs

22
Transmission Impact Study
  • Only undertaken if Feasibility Study raises
    questions of transmission impacts
  • Usually costly -- to be avoided if possible
  • If no impact study needed - generator drops from
    queue

23
Distribution Impact Study
  • Purpose
  • Identify generator design elements that protect
    distribution system
  • Assess impact of generator on distribution
  • No design review needed if
  • Certified
  • Generator meets criteria similar to 0-2MW
    secondary screens (without secondary network
    items)
  • Includes
  • Distribution load flow study
  • Equipment interrupt rating analysis
  • Protection coordination study
  • System operation impact analysis

24
Facilities Study
  • Identifies attachment facilities needed for
    interconnection including distribution system
    upgrades
  • If no facilities needed (customer sited
    generation), no study undertaken

25
2-20MW Costs
  • To be discussed
  • Limit interconnection costs to only those
    directly related to the application

26
Transmission Queue
  • To be discussed
  • FERC is scheduling a conference and possible NOPR
    on the subject

27
Interconnection Agreement/Application
  • Forms to be developed

28
Massachusetts DTE DG Interconnection
Collaborative Background
29
IEEE Std 1547 General Requirements Summary
  • Voltage regulation inside ANSI C84.1 Range A
  • Grounding coordinated with Area EPS
  • Synchronize without voltage fluctuation at PCC
    gt5 of prevailing voltages
  • Networks
  • Spot networks only for now

30
1547 General Requirements Summary (Continued)
  • DG shall not energize EPS when EPS is
    de-energized
  • DG gt 250kVA (unit or aggregate at PCC) shall have
    provisions for monitoring DG status, real power,
    reactive power
  • When required by EPS, accessible, lockable,
    visible-break isolation device (switch) located
    between DG and EPS

Isolation Switch Suitable for 70kW DG
31
1547 Abnormal Conditions Response Summary
  • Voltages outside of table below shall cause DG to
    cease to energize within clearing time
  • Detected at PCC or point of DG connection if
  • Aggregate DG capacity lt 30kW
  • Interconnect equipment certified to pass
    non-islanding test
  • Aggregate DG capacity lt 50 total local EPS
    demand AND export of power prohibited

32
1547 Abnormal Conditions Response Summary
(Continued)
  • DG lt 30 kW, frequencies shall fall in range of
    59.3 to 60.5 Hz else cease to energize within
    0.16 seconds
  • DG gt 30 kW
  • cease to energize within 0.16 seconds if gt60.5 Hz
  • cease to energize within an adjustable time delay
    if undervoltage in range of 59.8 to 57 Hz
  • cease to energize within 0.16 seconds if lt57.0 Hz
  • After a disturbance, DG reconnect only if voltage
    and frequency within range
  • Interconnection equipment shall be designed to
    coordinate with EPS reclosing practices and
    include ability to delay reconnect up to 5 minutes

33
Power Quality Summary
  • DG connected to single phase distribution shall
    not inject DC current gt0.5 DG full rating
  • The DG shall not create objectionable flicker
    for other customers on the area EPS
  • DG harmonic injection shall not exceed

Maximum Harmonic Current Distortion ( of current)
Harmonic Order (h) hlt11 11lthlt17 17lthlt23
17lthlt23 35lth Percent () 4.0 2.0 1.5 0.6 0.3
Current Distortion
Total Demand Distortion Maximum 5.0
Harmonic
34
Testing Requirements Summary
  • Five kinds of test are defined
  • Design test certifies that interconnection
    equipment meets the standard requirements
  • Production test factory test of DGs
    conformance to voltage and frequency variation
    limits
  • Interconnection installation evaluation
    basically a verification that the DG and
    interconnection design meet the standard
  • Commissioning test conducted at the facility to
    verify adjustable settings are correct and
    protective functions are operating properly
  • Periodic interconnection tests A periodic test
    of the interconnect protection system

35
Screens Primary
  • lt5 of annual peak load on radial circuits
  • lt5 of peak load (or 50kW max) on spot networks
    (inverters only)
  • Secondary grid distribution networks
  • induction generator or inverter
  • not exceeding 50 of facility minimum load
  • lt10 contribution to circuit max fault current
  • Not cause grid protective devices to exceed 90
    of their short circuit interrupting capability
  • In aggregate, cannot be gt10MW where transient
    stability limits posted
  • Phase imbalance limits if single-phase and
    connected to center tap neutral of a 240V service
  • lt20kVA if single-phase and on a shared secondary
  • Single-phase connection requirements
  • lt10 of line capacity if single phase and section
    configuration is three-phase, 4-wire or a mix

36
Screens Secondary
  • Radial circuits lt15 of line section design
    capacity
  • Spot networks lt5 of peak load on spot networks
  • Secondary grid networks
  • On any network, use reverse power protection
    except
  • if generator lt50 of min facility load or 500kW
  • Basically same limits on fault current
    contribution and short circuit interrupting
    impact as primary screen
Write a Comment
User Comments (0)
About PowerShow.com