Title: R
1RD Topics for the Phase II Upgrade of the LHC
- Eric Prebys, Fermilab
- Director, US LHC Accelerator Research Program
(LARP)
2Outline
- Limits to LHC Luminosity
- LHC Upgrade Plans and Schedule
- LARP-affiliated Upgrade Projects
- Nb3Sn Magnet Program
- PS2 Project
- Crab Cavities
3LHC Luminosity
- Because the LHC is a p-p machine, high luminosity
is needed to extend the physics reach to
reasonable fraction of the beam energy for the
physics processes of most interest Higgs, SUSY,
etc - Current plan
- come up fairly quickly to 1034 cm-2s-1
- Increase luminosity over the next decade to as
high as 1035 cm-2s-1 , assuming the detectors
show they can handle it.
4Limits to LHC Luminosity
- Brightness, limited by
- PSB injection energy
- PS
- Max tune-shift
Beam current, limited by e-cloud and other
instabilities
- b, limited by
- magnet technology
- chromatic effects
Geometric factor, related to crossing angle
see, eg, F. Zimmermann, CERN Upgrade Plans,
EPS-HEP 09, Krakow, for a thorough discussion of
luminosity factors.
5Current LHC Acceleration Sequenceand Brightness
Issues
Space Charge Limitations at Booster and PS
injection
Transition crossing in PS and SPS
Schematic ONLY. Scale and orientation not correct
6IR Layout
Separation Dipole
Final Triplet
IP
59 m
- Nominal Bunch spacing 7.5 m
- Collision spacing 3.75 m
- 2x15 parasitic collisions per IR
Implement Crossing Angle
7Crossing Angles
Luminosity effects
8Crossing Angle Considerations
- Crossing angle reduces luminosity
- However, crossing angle also reduces tune-shift
- In principle, the two effects should cancel
Piwinski Angle
Large Piwinksi Angle (LPA) Solution
9Other Option Crab Cavities
- Possibilities
- 2 or 4 cavities in global scheme
- Implications for apertures/collimation
- 8 for full local
- Main Technical question
- Space constraints -gt 800 MHz elliptical (simple)
versus 400 MHz exotic. - Critical review at CERN in September
10Without Compensation
Separation of first parasitic interaction
Nominal crossing angle with no compensation (9.5s)
G. Sterbini
11LHC Upgrade path
- Initial operation
- Ramp up to 1x1034 cm-2s-1
- Phase I upgrade
- After 2 years of operation (2013)
- Replace 70 mm triplet quads with 120 mm quads
- b goes from 50-gt30 cm
- Linac4 to increase PSB injection energy to reduce
space charge effects - Luminosity goes to 2.5x1034 cm-2s-1
- Phase II upgrade
- Second half of next decade (nominally 2020)
- Luminosity goal 1x1035
- Details still under study
- New technology for larger aperture quads (Nb3Sn)
- crab cavities?
- Improved injector chain (PS2 SPL)
No major changes to optics or IRs
Possible Significant Changes
12LHC Parameters and Options
Parameter Symbol Initial Phase I Phase II Options Phase II Options Phase II Options Phase II Options
Parameter Symbol Initial Phase I Early Sep. Full Crab Low Emit. Large Piw. Ang.
transverse emittance e mm 3.75 3.75 3.75 3.75 1.0 3.75
protons per bunch Nb 1011 1.15 1.7 1.7 1.7 1.7 4.9
bunch spacing Dt ns 25 25 25 25 25 50
beam current I A 0.58 0.86 0.86 0.86 0.86 1.22
longitudinal profile Gauss Gauss Gauss Gauss Gauss Flat
rms bunch length sz cm 7.55 7.55 7.55 7.55 7.55 11.8
beta at IP15 b m 0.55 0.3 0.08 0.08 0.1 0.25
full crossing angle qc mrad 285 410 0 0 311 381
Piwinski parameter fqcsz/(2sx) 0.64 1.26 0 0 3.2 2.0
peak luminosity L 1034 cm-2s-1 1 3.0 14.0 14.0 16.3 11.9
peak events/crossing 19 57 266 266 310 452
initial lumi lifetime tL h 22 11 2.2 2.2 2.0 4.0
Luminous region sl cm 4.5 3.3 5.3 5.3 1.6 4.2
excerpted from F. Zimmermann, LHC Upgrades,
EPS-HEP 09, Krakow, July 2009
13Common Upgrade Elements
- All require a magnet technology beyond NbTi for
the final focusing triplets - Almost certainly Nb3Sn
- All require Increased brightness, currently
limited by - Space charge painting effects of 50 MeV proton
injection at injection into PSB. - Will be addressed by Linac4 upgrade for Phase I
- Space charge and transition crossing effects in
(50 year old!) PS
Replace PS with new PS2
14PS2 Goal Double brightness to LHC
Parameter unit PS2 PS
Injection energy kinetic GeV 4.0 1.4
Extraction energy kinetic GeV 50 13/25
Normalized Trans. Emittance (RMS) pmm 3 3
Max. intensity LHC (25ns) ppb 4.0 x 1011 1.7 x 1011
Max. intensity FT ppp 1.2 x 1014 3.3 x 1013
Max. stored energy kJ 1000 70
Linear ramp rate T/s 1.5 2.2
Repetition time (50 GeV) s 2.5 1.2/2.4
Max. effective beam power kW 400 60
M. Benedikt, PS2 Internal Review, May 2008
Chosen based in tune-shift limit at injection
Chosen to be well above SPS transition
15PS2 vs Fermilab Main Injector
Parameter PS2 MI (now) MI (Project X)
Circumference (m) 1346.4 3319.42 3319.42
Injection Energy (GeV) 4 8 8
Extraction Energy (GeV) 50 120 (150 max) 120 (150 max)
gT 35i 21.8 21.8
RF Freq. (MHz) 40 53 53
Tune (x/y) 13.25/8.2 26.425/25.415 26.425/25.415
Max. protons 1e14 4.6e13 1.6e14
Cycle Time (s) 2.4 2.2 1.4
Clearly significant synergy between PS2 and MI in
Project X era
see talk by S. Nagaitsev, this conference
16New CERN machines
17Injector Upgrade
Initial
Phase I
Proton flux / Beam power
Linac4
Linac2
50 MeV
160 MeV
Phase II
PSB
SPL RCPSB
SPL
1.4 GeV
5 GeV
PS
Linac4 PSB injector (160 MeV) SPL
Superconducting Proton Linac ( 5 GeV) SPL
RCPSB injector (0.16 to 0.4-1 GeV) RCPSB Rapid
Cycling PSB (0.4-1 to 5 GeV) PS2 High Energy
PS ( 5 to 50 GeV 0.3 Hz) PS2
Superconducting PS ( 5 to 50 GeV 0.3
Hz) SPS Superconducting SPS (50 to1000
GeV) DLHC Double energy LHC (1 to 14 TeV)
26 GeV
PS2 (PS2)
40 60 GeV
Output energy
SPS
SPS
450 GeV
1 TeV
LHC
DLHC
7 TeV
14 TeV
M. Benedikt, R. Garoby, CERN DG
18US LHC Accelerator Research Program (LARP)
- Proposed in 2003 to coordinate efforts at US labs
related to the LHC accelerator (as opposed to
CMS or ATLAS) - Originally FNAL, BNL, and LBNL
- SLAC joined shortly thereafter
- Some work (AC Dipole) supported at UT Austin
- LARP Goals
- Advance International Cooperation in High Energy
Accelerators - Advance High Energy Physics
- By helping the LHC integrate luminosity as
quickly as possible - Advance U.S. Accelerator Science and Technology
- LARP includes projects related to initial
operation, but a significant part of the program
concerns the LHC upgrades
19LARP Contributions to initial LHC Operation
- Schottky detector
- Used for non-perturbative tune measurements
(chromaticities, momentum spread and transverse
emmitances) - Tune tracking
- Implement a PLL with pick-ups and quads to lock
LHC tune - Investigating generalization to chromaticity
tracking - AC dipole
- US AC dipole to drive beam
- Measure both linear and non-linear beam optics
- Luminosity monitor
- High radiation ionization detector integrated
with the LHC neutral beam absorber (TAN) at IP 1
and 5. - Personnel
- Toohig Fellowship Postdoc program
- Long Term Visitors
20Significant LARP Contributions to LHC Upgrades
- Rotatable Secondary Collimators
- Required to meet Phase I luminosity goals
- Electron Cloud Feedback for SPS
- Will be needed to handle increased intensity
after PS2 - Nb3Sn Magnet Program
- Goal demonstrate Nb3Sn as a viable magnet
technology on a time scale that will allow
accelerator quality magnets to be built for Phase
II - PS2 Activities, primarily
- Space charge effects
- Electron cloud effects
- LARP will contribute for 2012 white paper, and
then take part in further design RD - Crab Cavities?
- LARP currently steering RD
- Future depends on CERNs decisions
I will focus on these
21LARP Magnet program
- Magnet groups at FNAL, BNL, and LBNL working to
demonstrate that Nb3Sn is a viable technology for
use in the LHC Phase II upgrade. - Currently pushing all parameters
- Long Quad (LQ) 4m quad with 90 mm aperture
- High field Quad (HQ) 1m quad with 120 mm
aperture - Deliverables will be
- accelerator quality magnets (HQ-2) matched to
LHC Phase I aperture - Length 2 m
- Aperture 120 mm
- Gradient gt200 T/m
- Long magnet with detailed field quality studies
- Length 6 m
- Aperture 90 mm
- Gradient gt 220 T/m
- Accelerator physics questions
- Optical design
- Field quality requirements
- Beam loss/heat loading issues
- Radiation damage.
22Motivation for Nb3Sn
- Nb3Sn can be used to increase aperture/gradient
and/or increase heat load margin, relative to
NbTi - Very attractive, but no one has ever built an
accelerator quality magnet out of Nb3Sn
Phase I magnets
120 mm aperture
23Competing Magnet Designs
- Collar
- Traditional magnet design
- Pre-load provided by a series of collars which
hold coils in place.
- Shell
- New concept
- Pre-load produced by inflatable bladder, and
secured by insertable keys.
24LARP Technology Quadrupole (TQ) Program
- Double-layer, shell-type coil
- 90 mm aperture, 1 m length
- Two support structures
- - TQS (shell based)
- - TQC (collar based)
- Target gradient 200 T/m
TQC
TQS
Winding curing (FNAL - all coils)
Reaction potting (LBNL - all coils)
G. Sabbi, LARP Review, July 2009
25Initial TQ (90 mm x 1m) Results
TQ01 OST-MJR 54/61
TQ02 OST-RRP 54/61
- Two coil/model series using different wire design
- 30 coils fabricated, distributed production line
- 11 tests performed (FNAL, LBNL and CERN)
- Surpassed 200 T/m with 10 margin (TQS02a/c)
- All training quenches gt200 T/m in TQS02c/d
61
Stability issues at 1.9K (LHC operating point)
26Conductor Tests at Fermilab Mirror Magnet
Facility (TQM)
Smaller filament conductor (RRP 108/127)
Traditional conductor (RRP 54/61)
- Hypothesis smaller filament increases conductor
stability - Conclusion switch to new 108/127 conductor for
future magnets
27Comparing Technologies
- Collar
- Good
- Established technique with NbTi magnets
- Straightforward to scale from short prototypes to
long magnets - Alignment and heat distribution problems solved
- Bad
- As yet no design to reach the highest
gradients/apertures (excessive stress). - Difficult to replace damaged coils
- Shell
- Good
- Can achieve higher gradients/apertures than
collar design - Much easier to disassemble and replace damaged
coil - Bad
- New
- Differential contraction problems when scaling to
longer magnets - Some alignment and heat distribution problems
must be solved. - Tentative conclusion
- Pursue shell design
28HQ (120 mm x 1 m) Status
- Based entirely on shell concept
- Design and modeling complete
- Structure being procured
- Coil fabrication in process
- Complete two prototypes in 2010
29Long Quad (90 mm x 4m) Status
- 4 coils ready for (LQS01) assembly
- Shell-structure is ready
- Pre-assembly practice in progress
- Readiness review July 27
- Test prep completed
- Readiness review TBD
- Ready to test in October 2009
G. Ambrosio, LARP Review, July 2009
30Schedule of Magnet Program
- Work to finalize the magnet plan and demonstrate
the technology in the context of the Phase II
upgrades - Assume 5 year production schedule for triplets
based on Nb3Sn - Even if Phase-II is in 2020, there will have to
be overlap between production and RD
Existing Magnet Program
Future Construction Project
31PS2 Design Outline
- Coordination and basic lattice design
- Linear correction systems
- Non-linear dynamics and correction systems
- Collective effects and feedback systems
- Space charge studies
- Impedance estimates and instabilities
- e- cloud effects and vacuum system requirements
- Damping system specifications
- Collimation aspects
- Machine protection
- Instrumentation specifications and commissioning
strategy
Our Involvement
M. Benedikt and Y. Papaphilippou
32PS2 Space Charge Simulations
J. Qiang
33PS2 Electron Cloud Simulations
MI
PS2
M. Furman
- Goal develop mitigation techniques, particularly
RF feedback - LARP will contribute sections to 2012 white
paper, then participate in design RD
34Crab Cavities
- LARP steering international effort to propose a
viable crab cavity design - Includes collaborators from CERN, US, UK, and
Japan - Working toward major technology down selection
- 800 MHz elliptical vs. 400 MHz exotic
- Damping scheme
- Critical review at CERN in September
35Recent success at KEKB
- Crab Cavities enabled a peak luminosity of
- 20 years after crab cavities initially proposed
- Hopefully a bit faster next time
gt 2x design
1x1034 cm-2 s-1
Z. Doležal, EPS-HEP 09, Krakow, July 2009
36R. Calaga, LARP DOE Review, July 2009
37R. Calaga, LARP DOE Review, July 2009
38Cavity and Cryomodule Design Status
- 2 cell SRF cavity _at_800 MHz
- 3 aggressive damping schemes
- LARP, KEK, UK
- Down selection
- Multipacting, thermal, mechanical etc...
- Cryostat development underway (FNAL)
- interfaces,
- RF-cryogenic-mechanical constraints
395-6 Year Plan
CERN Review
40Things I didnt have time to talk about
- A great deal of work at CERN
- NbTi program for Phase I
- Details of accelerator physics for Phase II
- Additional injector projects for Phase I and
Phase II - Linac 4
- SPL
- Additional PS2 topics
- US Tasks outside of LARP
- Superconducting separators and feedboxes for
Phase I (APUL project) - Important LARP tasks
- Beam-beam simulation and compensation,
particularly electron lens - Crystal Collimation
- LLRF projects
- Additional instrumentation projects
41Acknowledgements
- This talk represents the work of many people, in
particular - Within LARP
- Peter Wanderer, Tom Markiewicz, GianLucca Sabbi,
Giorgio Ambrosio, Sasha Zlobin, Wolfram Fischer,
Rama Calaga, Arup Ghosh, Uli Wienands - Too many to mention from CERN, but Ive borrowed
material directly from - Frank Zimmermann, Michael Benedikt
- Thanks to the conference organizers and the
audience