Title: UAE University
1UAE University Faculty of Engineering Graduation
project II
Refinery Wastewater Treatment Plant
Advisors
Dr. Mohamed Abdul Karim
Dr. Ibrahim Ashor
Basma
Maha
Moza
Noura
2Presentation Layout
- Problem definition
- Objectives
- Process flow sheet
- Material balance
- Equipment design
- Plant cost estimation
- Process simulation
- Environmental impact
- Conclusions Recommendations
3- Refinery WW contains pollutants including
solids, oil, organic and inorganic components.
- The composition of WW was adopted from Kurkkale
Petroleum Refinery.
4Objectives
- To design a plant for treatment of refinery WW
Detailed Objectives
- Material balance calculation
- Equipment design calculation
- Cost estimation of the plant
- Process simulation using Super Pro.
- Environmental impact
5Process Flow Sheet
CPI Separator
Trickling Filter
Clarifier
DAF
Gravity Thickening
Belt filter press
6Material Balance
7Equipment Design
1. CPI Separator
- The main required parameters
- The effective surface area needed for separation
- Rise velocity of oil globule
- Number of packs
- The separator depth
81. CPI Separator
To calculate the effective surface area required
for separation
Total surface area of the plates
Projected surface area of the plates
Effective surface area Ap/1.12
91. CPI Separator
To calculate the no. of packs
Calculate WW density
Calculate horizontal surface area
Calculate no. of packs
101. CPI Separator
11Equipment Design
2. Dissolved air flotation
- The main required parameters
- Hydraulic loading
- Solid loading
- Air solid ratio
12Equipment Design
2. Dissolved air flotation
Air solid ratio 0.015 lbair/lbsolid
Hydraulic Loading 3.8 gal/min.ft2
To calculate solid loading
Calculate surface area of flotation tank
13Equipment Design
2. Dissolved air flotation
To calculate power requirements for pumps
Calculate surface area of flotation tank
142. Dissolved air flotation
152. Dissolved air flotation
16Equipment Design
3. Trickling filter
- The main required parameters
- Filter depth
- Diameter, surface area of the filter
- Hydraulic loading
- BOD loading
- Recirculation ratio
- Mean detention time
- Amount of oxygen required
- Dosing rate and rotational speed
173. Trickling filter
To Calculate the filter surface area
To Calculate the filter volume
Calculate the hydraulic and BOD loading
183. Trickling filter
To calculate the efficiency of the filter
Calculate recirculation factor
Calculate the efficiency
193. Trickling filter
20Equipment Design
4. clarifier
- The main required parameters
- Width
- Surface area
- Weir length
- detention time
214. clarifier
To Calculate the tank surface area
Surface area (ft2) WW flow rate (gpd) / average
overflow(gpd/m3)
Width (ft) Surface area(ft2)/ depth ft)
Weir length (ft) WW flow rate
Detention time (hr) clarifier volume (ft3)/ WW
flow rate (ft3/hr)
22Equipment Design
5. Gravity thickening
- The main required parameter
- Area of thickener
235. Gravity thickening
To calculate area of thickener
24Equipment Design
5. Belt filter press
- The main required parameters
- Sludge feed rate
- Hydraulic loading rate
- Solid loading rate
- Polymer dosage
- SS in the WW
- Solid recovery percentage
255. Belt filter press
Hydraulic loading rate Sludge Feed rate
Belt width
Solid loading rate Sludge flow rate S.S in
the feed density of w.w Belt width
Polymer dosage Polymer dosagepowdered
polymerdensity of ww Solid loading
belt width
The suspended solid in ww wash-water solids
Filtrate solids
Solid recovery (total solids in feed sludge
)-(SS in wastewater)
Total solids in feed sludge
261. Purchase cost of the major equipment (PCE)
For Example - Purchase cost of Trickling filter
_at_ 1990 760,000 - _at_ 1998 the PCE 284,564 X
(109/100) 310,175 - Inflation
rate (1998-2002) 10.1 ? Cost _at_ 2002 310,175
X (1.101) 341,502
27? Total purchase cost of major equipment item
(PCE)
28 Estimation of total investment cost
Total investment cost Fixed capital Working
capital
PPC PCE (1 f1 f2 f3 f4 f5 f6 f7
f8 f9)
29For refinery wastewater treatment plant, only f1,
f2, f3, f4, f8
Fixed capital PPC (1 f10 f11 f12)
30Working capital allows 5 of fixed capital
? Working capital 177,453
? Total investment required for the project
3,726,520
- Operating time allowing for plant attainment
For 95 attainment ? The operating time is 8322
hr/year
31Operating cost
Fixed operating costs costs that do not vary
with the production rate
Variable operating costs costs that are
dependent on the amount of the product produced
- Maintenance
- 2. Operating labour
- 3. Laboratory costs
- 4. Rates and any other local taxes
- 5. Insurance
- 6. Licence fees
32? Maintenance, take as 5 of the fixed capital
? Insurance cost approximated to be 1 of the
fixed capital
? Operating labour
? laboratory costs, take as 20 of the operating
labour costs
33Annual operating costs 20157201
34Direct capital cost
- Well supply
- Brine disposal
- Land
- Process equipment
- Auxiliary building
- Buildings
- Membranes
Annual operating cost
- Electricity
- Labor
- Maintenance and spares
- Insurance
- Chemicals
- Amortization
Indirect capital cost
- Freight and insurance
- Construction overhead
- Owners cost
- Contingency
Unit product cost, /m3
35Assumptions
- Interest rate i 5
- Plant life n 30 yrs.
- Plant availability 0.9
- Amortization factor a 0.08 yr-1
- Performance ratio 7.5 kg fresh water/ kg steam
- Average latent heat 2,222.35 kJ/kg
- Electric cost 0.025/kWh
- Heating steam cost 1.5/m3
- Specific chemical cost 0.025/m3
- Specific cost of operating labour 0.1/m3
- Plant capacity 32,732.64 m3/d
36Process simulation
Influent characteristic
Influent environmental properties
37Process Description
38Process simulation
Volatile organic compounds (VOC) emission
39Plant cost estimation
Process performance
- The splitting as function of degradation
40Process simulation
Process performance
- The splitting as function of degradation
41Process simulation
4. Processes Performance
Process performance
- The kg/h of the biomass as degradation
42Environmental impact
- The evaluation of the potential impacts of
suggested projects that relative to the physical,
chemical, and biological components of the total
environment - To abide with both local and international
standards
43(No Transcript)
44Health concerns
- Benzene
- It is water-soluble
- It can pass through the soil into underground
water - At relatively high exposure levels, It is
extremely toxic, even fatal to humans and other
organisms - Carcinogenic
- Phenol
- It can cause muscle pain, liver damage, weight
loss, and blood disorders - In animals, high exposure to phenols can result
in muscle tremors, severe injury to the heart,
kidneys, liver, and lungs, followed by death in
some cases
- Toluene
- It has been linked to headaches, confusion, and
memory loss - It can cause damage to the lungs, liver, and
kidneys for humans - In animals, it was found that toluene has
adversely effect the nervous system
45Piping Instrumentation
- It shows the engineering detailed of the
equipment, instruments, piping, valves and
fittings and their arrangements
46HAZOP analysis of DAF unit
47Conclusions recommendations
- A survey is essential to recognize and estimate
sources and treatment applied - Industrial wastewater plants should be designed
for industrial area such as Jabal Ali and Al
Ruwais industrial areas - Environmental agencies should conduct survey in
order to identify status of industries generating
wastewater - Environmental standards should be enforced on
industries - Environmental impact assessment should be carried
out for such industries - There is emission studies conducted on industries
such studies are valuable to identify potential
hazards
48(No Transcript)