Title: 200506 Safety Monitors
12005/06 Safety Monitors
- Presentation to Gas Transmission Workstream,
- 5 January 2006
-
2Safety Monitors background
- Define levels of storage that must be maintained
through the winter period - Introduced in 2004 to replace Top-up
- Top-up focused on maintaining security of
supply Safety Monitors focus is public safety - Requirement of National Grid Gas Safety Case
that action is taken to ensure storage stocks do
not fall below the Safety Monitor levels - these
decay as the winter progress
3Gas Safety (Management) Regulations 1996
- Requires anyone conveying gas in a network to
prepare a Safety Case and for the Safety Case to
be accepted by the HSE - The Safety Case must contain particulars which
describe arrangements for a number of items
listed in Schedule 1 - These are high level requirements which must be
described in detail in the Safety Case GS(M)R
does not define how a specific requirement is to
be met. - The relevant requirement in Schedule 1 is clause
16 - 16 - Particulars to demonstrate that the duty
holder has established adequate arrangements to
minimise the risk of a supply emergency, where a
supply emergency" means an emergency endangering
persons and arising from a loss of pressure in a
network or any part thereof
4GS(M)R Safety Monitors
- The GS(M)R Safety monitor arrangements form part
of National Grids detailed demonstration that it
has arrangements in place to minimise the risk of
a supply emergency - They address the risk posed by the possibility of
insufficient storage being available for a 1 in
50 duration winter - The arrangements have been accepted by the HSE as
discharging our responsibility in this area and
we have a legal obligation to follow those
arrangements - Any change in arrangements would constitute a
material change to the Safety Case and National
Grid would have to present a case which
demonstrated that the new arrangements were at
least as safe as the current arrangements
5Safety Monitors methodology
Concept sufficient gas held in store to support
those customers who can not be physically
isolated from the network, requirements include
isolation process of large loads All loads
categorised into two groups
- Loads protected by Isolation
- NTS Interruptibles
- LDZ Interruptibles
- NTS Power Firm
- NTS Industrial Firm
- DM (excluding priority customers)
- Loads protected by Monitor
- Priority Firm DM
- Ireland Firm
- All NDM
- gt5860 MWh NDM
- 2196-5860 MWh NDM
- 732-2196 MWh NDM
- 73-732 MWh NDM
- 0-73 MWh NDM
6Supplies assumptions (1)
- Baseload non storage supplies that are not
limited by space, includes - Beach
- Interconnector
- Grain (LNG Imports)
- 10 mcm/d supply risk to cover for supply
uncertainty, notably import assumptions
7Supplies assumptions (2)
- Storage supplies
- Long Rough
- Medium
- Includes Hornsea and Hatfield Moor
deliverabilities only - Includes Hornsea, Hatfield Moor, Hole House Farm
and Humbly Grove space (reduced at onset to
reflect start-up uncertainty) - Short 4 LNG storage sites
- Total storage supply level 110 mcm/d (1200
GWh) - Total storage space 4000 mcm ( 43,200 GWh)
8 - Supply / demand component loads protected by
monitor -
91 in 50 Firm load
Baseload supplies underpins storage requirements
(96 of supply)
101 in 50 demands by load type
111 in 50 load protected by isolation
Isolation 1300 GWh (120 mcm/d)
Monitor (Supply / Demand)
121 in 50 load protected by monitor
13Supply / demand component
- 10 mcm/d supply risk included in September
analysis to cover for supply uncertainty, notably
import assumptions - Supply risk had to be identified at time due to
UNC requirements - Supply risk located in Long not to unsettle
markets Long considered lowest risk of monitor
breach
14 - Non - supply / demand component load protected
by isolation -
15Safety Monitors Protected by Isolation
16Isolation Component
- Supply risk has a lesser impact than in supply /
demand - Isolation needs established from observed
behaviour from winter exercises (Krakatoa,
Moscow) - Improved industry response would reduce isolation
needs - Support for Isolation process is up to 48 hours
- All above isolation needs are similar
17Total Requirement for December
- Final requirement is lower than combined needs of
Supply Demand Isolation due to some reduction
for double counting i.e. Supply Demand for Day
1 and Isolation for Day 1
18 19Monitor Profile Methodology
- Storage space and duration requirements are known
for all storage types for protected by monitor
and protected by isolation - Protected by monitor is a winter long requirement
- Protected by isolation is a one off requirement
- Need to develop 2 key relationships
- Demand days and temperatures (CWVs)
- Latest dates in a winter when such temperatures
could occur
20Day Number / Temperature Relationship
Long isolation
Long supply / demand
21Calculation of Profiles
- Protected by isolation is a one off requirement
- Need to identify latest date when isolation could
occur - A different requirement is calculated for each
Day i.e. the Day 1 requirement is much
earlier in winter than say Day 62 - Protected by monitor is a winter long requirement
- Need to identify latest requirement
- Need to identify earlier needs to establish
within year profile review all previous winters
- Profiles are then combined
22Latest occurrence of cold (isolation)
23Long safety monitor profile
Monitor
Isolation