Title: HVDS Status Report P' Mantzaridis, A' Markouizos, P' Mitseas, A' Petridis, S' Potirakis, M' Tsilis,
1HVDS Status Report P. Mantzaridis, A.
Markouizos, P. Mitseas,A. Petridis, S.
Potirakis, M. Tsilis, M. VassiliouAthens
University
- ALICE TRD Meeting
Rolandseck, March 2007
2Outline
- HVDS Hardware
- Prototype system at P2
- Control Software
- Testing of the HVDS
- Installation at P2
3HVDS Hardware
- Production _at_ q-print
- 2 Anode 2 Drift HVD Cards
(delivered, 30/3) - Backplanes (7) (April 1st week)
- Aux. DCS Cards (7) (April 1st
week) - Front panel cards (7) (April 1st
week) - Transformer boards (35) (April 2nd week)
- (2 HVD cards 3 transformers)
- 40 Anode 40 Drift HVD cards
(end of April) - 4 Schroff Crates ordered (April 2nd
week) - LV Power Supplies ordered (April 1st week)
- (5V, 12V, -12V)
4HVDS Hardware (cont.)
- Connectors (delivered)
- Cables (April 2nd week)
- Internal cables (141 / crate)
- Communication cables (6 / crate)
- LV cables (4 / crate)
- Mechanical Parts (April 3rd week)
- Transformers shielding
- Cover grids for the crates
- Schroff crates - front panel customization
5LV Power Supplies
- Requirements
- Output data
- Output 1 5V 7A min
- Output 2 12V 1.5A min
- Output 3 -12V 0.7A min.
- Linear mode
6The Prototype HVDS at P2
- System is in operational state
- Safety documents submitted
- Production of blinds to close the crates
- Safety inspection
7Control Software
- Intercom Layer
- completely removed, PVSS tested
- PVSS panels
- generic panels for Channel, Card and Module
exist - new module panel under development
(April 1st week) - ISEG control
- crate tested successfully with CAN control
software and PVSS panels - implementation of updated PVSS panels
needed (April 1st week) - Local archiving in PVSS
- already exists
- Alarms
- over-current, over-voltage exist in channel
level - need to be implemented to higher levels
(April 2nd week) - over-temperature alarm need to be added
8Control Software (cont.)
- FSM
- updated HV state diagram is implemented
- mew FSM tree is under development
(April 1st week) - Logical Views
- need to be implemented (April 3rd
week) - OracleDB
- will be implemented after the sw
installation at CERN (May 1st week) - Recipes
- will be implemented after the sw
installation at CERN (May 1st week) - Integration to TRD (May 2nd week)
- Installation at CERN (May 3rd week)
9Testing of the HVDS
- test procedure
- flow-chart defined,
- software under development
(April 1st week) - testing of 22 HVD cards
(April 1st week) -
- testing of
- backplanes, aux DCS cards, front panel
cards (April 2nd week) - testing of 4040 HVD cards
- in Athens and Heidelberg
(May 2nd and 3rd week) - magnetic field test of crates at CERN (May 4th
week)
10Installation at P2
- Submission of new safety documents (May 3rd
week) - Safety inspection (May 4th
week) - Operation of 22 HVDS crates at P2 (end of
May)
11Long Term Voltage Stability Test (Athens - Jan
2007)
- ?V (FWHM) lt 30 mV
- ?V / V lt 1.6 E-5
12Control of the HVDS
Backup
13Long Term Voltage Stability Test (Athens - Jan
2007)
- ?V (FWHM) lt 30 mV
- ?V / V lt 1.6 E-5
14Integration of the HV Distribution System to the
First TRD Super Module P. Mantzaridis, A.
Markouizos, P. Mitseas,A. Petridis, S.
Potirakis, M. Tsilis, M. VassiliouAthens
University
- Workshop on the DCS for the TRD
Heidelberg, January 2007
15Outline
- Installation of the first HVDS at CERN
- Specifications of the HVDS
- Control of the HVDS
- Performance of the HVDS
- Current Status (hardware, software)
16Installation of the first HVDS at CERN (October
2006)
17Installed Hardware at CERN
- 11 Crates (positions 007_9, 007_16)
- 11 DCS Boards (with auxiliary DCS cards)
- 11 Backplanes
- supplies the Master HV to each card
- distributes the isolated LV to the
active components - enables the CAN bus communication
- 5 Anode 5 Drift Cards
- 33 isolated LV Auxiliary Power Supply Cards
- LV Power Supplies (5V, 12V)
18Specifications of the HVDS
- Anode Voltage
- dynamical range 900 1900 V
- ramp-up rate 30 V/s
- ramp-down rate 100 V/s
- voltage stability DV lt 50 mV
- voltage readout 10 Hz
- max. current 7 mA
- response time lt 50 ms
(e.g. overcurrent)
19Specs. (cont)
- Drift Voltage
- dynamical range 1450 2500 V
- ramp-up rate 30 V/s
- ramp-down rate 100 V/s
- voltage stability DV lt 50 mV
- voltage readout 10 Hz
- max. current 230 mA
- response time lt 50 ms
(e.g. overcurrent)
20Control of the HVDS
Control of the HVDS
21The TRD Overview Drawing
22Architecture of the CAN network
23HVDS Card Control Panel
24ISEG Control Panel
(G. Tsiledakis)
25HVDS Channel Control Panel (Test on the SM 1 at
CERN, 8/10/2006)
26Ramping and Status Procedures
27Error Messages
- Voltage Errors
- Over Voltage
- message max allowed voltage is exceeded
- action voltage is set to the max allowed value
- Under Voltage
- message min allowed voltage is out of range
- action voltage is set to the max allowed value
- Limits Error
- message set value is out of limits
- action limit is set to the default value
- Current Errors (Hardware Error)
- Over Current
- alarm max allowed current is exceeded or a
short-circuit occurred - Ramping Errors
- Ramping Rate
- message max allowed rate is exceeded
- action rate is set to the max allowed value
28HV State Diagram
(G. De Cataldo)
29Control of the HVDS
Performance of the HVDS
30Voltage Stability Test on the Detector at HD
(25-08-2006)
Voltage Measurements
31Current Stability Test on the Detector at HD
(26-08-2006) Operating 3 channels from one HV
Anode Card
Current Measurements
32Voltage Stability Measurements on the SM1 at CERN
(9/10/2006)
- 6 anode channels
- HV set at 1450 V
33Voltage Resolution Measurement on the SM1 at CERN
(9/10/2006)
34Long Term Voltage Stability Test (Athens - Jan
2007)
- ?V (FWHM) lt 30 mV
- ?V / V lt 1.6 E-5
35Control of the HVDS
Current Status
36Hardware
- New Schroff Crate LV Power Supply
- Two parallel orders to Q-Print
- 2 Anode 2 Drift cards for testing
purposes - 30 (10) Anode 30 (10) Drift
cards - to power 6 Supermodules
- 5 Backplanes, Auxiliary DCS cards,
- connector card, Isolated PS cards
- Define testing procedure
- Magnetic field tests of a full crate at CERN
- Installation of the 22 HV Crates at P2
- Documentation
37Software
- Archiving
- Amanda Server Manager (AliRoot)
- ORACLE Database
- Alarm Handling
- Recipes and logical views
- Integration to the TRD-DCS
- PVSS project according to the ALICE
- DCS guidelines
- Implementation of the FSM
- Installation of final software project at CERN
- Documentation