Title: CIVL202 Construction Engineering I


1
CIVL202Construction Engineering I
  • Tutorial 8
  • T1 Mon 1100 1150
  • T2 Wed 0900 0950

2
Tutorial Outline
  • Developing WBS
  • Cost control
  • Bar chart
  • Scheduling network

3
Developing WBS
  • The definition of WBS is the progressive
    hierarchical break-down of the project into
    smaller pieces to the lowest practical level to
    which cost is applied.
  • The aim of WBS is extremely useful in developing
    both cost and time (schedule) plans to monitoring
    and controlling a project.
  • We can think about that Why was Construction
    Project Management developed?

4
Developing WBS
  • In establishing the WBS, the following guidelines
    need to be considered
  • Be clearly separated from other work packages.
  • Each work package must have unique starting and
    ending dates.
  • Each work package should have its own unique
    budget.
  • Work packages should be small enough that precise
    measurement of work progress is possible.
  • Maybe these points can be comprehended in
    Construction Project completely.

5
Determining Sequence of Work packages
  • Activity is the work elements which appear in the
    schedule in their expected sequence or logical
    order.
  • The criteria of arranging the work packages
    sequence for time control
  • Location
  • After completing the structure frame of the first
    floor of a building before beginning the second.
    This is a physical constraints.
  • Material
  • The building structure isnt erected until the
    foundation of a building have reached sufficient
    strength. This is a physical constraints.

6
Determining Sequence of Work packages
  • Method of construction technology
  • This is a technology constraint. Different
    technologies have different sequences.
  • Required resources
  • If the Required resources cant be gotten, the
    sequence must be changed.

7
Cost Control Related to WBS
  • Procedure of cost control
  • Develop bid estimate.
  • If bid is accepted, develop contract budget based
    on major work items.
  • Measure actual cost on project.
  • Compare actual costs with control budget.
  • Take corrective actions ( measurement of reducing
    cost).
  • If cant complete the project, could revise
    contract budget.

8
Cost Control Related to WBS
  • Code of account is a template or guide in
    defining and cataloging the cost centers within a
    project.
  • Cost coding system utilize a numerical or
    alpha-numerical labeling which is a multi-level
    or hierarchical in nature, just to be consistent
    with WBS.

9
Cost Control Related to WBS
  • A typical cost type might define
  • (1) the project designator
  • (2)area of work
  • (3)work discipline( e.g. civil, mechanical,
    electrical, etc.)
  • (4) the trade specialty required.
  • A cost coding system need to be handled by
    computer easily.

10
Attention
  • The WBS provides a rigorous way to quantify,
    define, measure, and control the work packages of
    a given scope of work.
  • Other plans can be developed based on the WBS.
  • Procurement plan
  • Safety plan
  • Quality plan
  • ..

11
Bar Chart
  • Bar chart the representation of a project work
    item/activity as a time scaled bar whose length
    represents the planned duration of the activity.
  • Length of the bar has two meanings
  • Its physical length represents the planned
    duration of the work activity.
  • The bar provides a proportionally scaled baseline
    to plot at successive intervals the correct
    percentage complete.
  • By using different shading patters, bar chart can
    indicate monthly progress toward physical
    completion of work activities.

12
Bar Chart
  • A bar-net is a updated bar chart.
  • MS-Project-XP P3 and so on can draw the
    bar-net.

13
Scheduling Network
  • In order to develop a schedule, the logical
    sequences that relates various activity to on
    another must be developed.
  • Logical modeling rationales
  • Adjacency of contact modeling
  • Physical structure order modeling
  • Physical construction order modeling

14
Scheduling Network
  • A scheduling network of nodes and links
  • The node may represent events in time or an
    activity depending on the notation.

Activity name
A
10
The duration time
A, Node to present and event
B, Node to represent an activity
15
Scheduling Network
  • Activity on node means that a network of
    activities is shown in which nodes represent the
    activities and arrows represent the sequences or
    relationship of the activity to one another.
  • Activity on Arrow means that a network of
    activities is shown in which nodes represent
    events in time and arrows represent activities.

16
Scheduling Network
  • Dummy Activity
  • 1,Maintain logic sequence
  • 2,Maintain specific activity
  • 3,Zero duration.