Aquatic Organism Passage at RoadStream Crossings - PowerPoint PPT Presentation

1 / 76
About This Presentation
Title:

Aquatic Organism Passage at RoadStream Crossings

Description:

Aquatic Organism Passage at RoadStream Crossings – PowerPoint PPT presentation

Number of Views:18
Avg rating:3.0/5.0
Slides: 77
Provided by: aprilc5
Category:

less

Transcript and Presenter's Notes

Title: Aquatic Organism Passage at RoadStream Crossings


1
Aquatic Organism Passageat Road-Stream Crossings
  • Joint Engineers Conference
  • November 6, 2009

Presented by Jeremiah Theys, PE
2
Outline
  • AOP Background
  • Design Approach
  • Field data
  • Stream design
  • Structure design
  • Case Studies
  • Bridge
  • Open Bottom Culvert

3
Introduction
  • What is AOP?
  • Not just fish passage
  • Aquatic communities
  • Frogs
  • Salamanders
  • Insects
  • Micro organisms

4
Introduction
  • Premise
  • If the channel inside a culvert or under a
    bridge simulates the characteristics and function
    of the adjacent natural channel, it will present
    no more of an obstacle than the natural channel.

5
Introduction
  • Aquatic Organism Passage Objectives
  • Provide for species passages

6
(No Transcript)
7
Introduction
  • Aquatic Organism Passage Objectives
  • Provide for stream function and water quality

8
(No Transcript)
9
Introduction
  • Aquatic Organism Passage Objectives
  • Maximize structure life while minimizing
    maintenance

10
(No Transcript)
11
Typical Barriers
  • Road networks with culvert crossings
  • Undersized culverts
  • Hydraulically
  • Channel width/culvert width ratio
  • High velocity
  • Culvert slope
  • Channel configuration
  • Crossing located on nick points
  • Channel type changes

12
Design Team
  • Biologist
  • Geomorphologist
  • Engineer
  • Hydraulic
  • Structural
  • Geotechnical
  • Contractor

13
(No Transcript)
14
Design Approach
  • Carry natural channel through replacement
    structure
  • Initial Site Assessment
  • Stream Survey
  • Engineering Survey
  • Design
  • Construction Management

15
Site Assessment
  • Reference reach
  • A template of the channel bed, banks, floodplain
    characteristics, and geomorphic processes along a
    stable, representative reach of the channel.

16
Site Assessment
  • Define channel type

17
Stream Survey
  • Cross sectional information

18
Stream Survey
  • Long profile

19
Site Assessment
  • Reference reach
  • Bankfull widths and depths
  • Channel gradient
  • Instream features
  • Information used to determine structure width,
    channel gradient, and channel characteristics in
    the replacement structure

20
Engineer Survey
  • Topographic map with all site features

21
Channel Design
  • Based on site assessment and survey, determine
    final design elements
  • Channel restoration limits
  • Channel/structure width and depth
  • Channel/structure gradient
  • Instream features

22
Channel Design
23
Channel Design
24
Channel Design
  • Instream structures
  • Step pools
  • Cross vanes
  • J-hooks

25
Structural Design
  • Structure type
  • Closed bottom structures
  • Typically used on small channels
  • Low gradient lt2
  • Pipe-arch or concrete box culverts are most
    common

26
Structural Design
  • Structure type
  • Open bottom structures
  • Used widely
  • Gradients lt6-8
  • Steel arch culverts are most common

27
Structural Design
  • Structure type
  • Bridges
  • Used widely
  • All channel gradients
  • Steel, concrete and timber structures commonly
    used

28
Hydraulic Design
  • Verify hydraulic characteristics
  • Typically modeled using HEC-RAS
  • Structures as usually oversized and provide
    sufficient freeboard at the 100-year event

29
Structural Design
  • Foundations
  • Bridges typically used grade beam or driven pile
  • Open bottom culverts typically used footing
    w/stemwalls

30
Structural Design
31
Case Study Projects
  • Savage Creek Culvert Replacements (Clearwater NF)
  • New arch culvert on 359 Rd.
  • New timber bridge on 360 Rd.
  • Upper Main Red River Culvert Replacement (Nez
    Perce NF)
  • New arch culvert on 1166 Rd.

32
Savage Creek Arch Culvert
  • Existing culvert 71 x 47 squash pipe
  • Existing culvert deemed barrier to aquatic
    organism passage

Plunge-pool at outlet High velocities through
culvert Culvert width/channel width ratio 0.39
33
Savage Creek Arch Culvert
  • Site Characteristics
  • Bankfull Width 15
  • Rosgen C type channel
  • Step-pool channel
  • Design flows
  • 2-Year 91 cfs
  • 10-Year 156 cfs
  • 100-Year 251 cfs
  • Median grain size 3.5
  • Channel slope 4.5 upstream
  • 2.5 downstream

34
Savage Creek Arch Culvert
  • Field data
  • (Geomorphologist and Engineer surveyed)
  • Bankfull width
  • Channel classification
  • Site design criteria
  • Road geometry
  • Access
  • Survey (topographic map)

35
Savage Creek Arch Culvert
  • Preliminary Design
  • Channel width 15
  • Structure width 18
  • Structure alternatives
  • Bridge
  • Concrete culvert (open bottom)
  • Metal arch pipe (open bottom)
  • Vertical clearance ( 4)
  • Hydraulics
  • Velocities (4-6 fps _at_ bankfull)
  • Freeboard (2 at 100-year event)

36
Savage Creek Arch Culvert
  • Final Design
  • Steel structural-plate arch culvert 19 span x
    6-4 rise x 45
  • Precast concrete footings w/ stemwalls
  • Allows shaping of the channel prior to culvert
    installation
  • Geocell used under footings
  • Grade control structures (step pools)
  • 6 step pools
  • 1 rock weir
  • Raise road 2.5

37
Savage Creek Arch Culvert
38
Savage Creek Arch Culvert
39
Savage Creek Arch Culvert
40
Savage Creek Arch Culvert
41
Savage Creek Arch Culvert
42
Savage Creek Arch Culvert
43
Savage Creek Arch Culvert
  • Constructed in 2006
  • Construction Time 14 days
  • Contract allowed 19 days no more than 2 weekends
  • Engineers Estimate - 89,600

44
Savage Creek Bridge
  • Existing culvert 67 x 45 squash pipe
  • Existing culvert deemed barrier to aquatic
    organism passage
  • Plunge-pool at outlet
  • High velocities through culvert
  • Culvert width/channel width ratio 0.37

45
Savage Creek Bridge
  • Site Characteristics
  • Bankfull Width 15
  • Rosgen B type channel
  • Design flows
  • 2-Year 80 cfs
  • 10-Year 135 cfs
  • 100-Year 217 cfs
  • Median grain size 3
  • Channel slope 3 upstream
  • 2.5 downstream

46
Savage Creek Bridge
  • Field data
  • (Geomorphologist and Engineer surveyed)
  • Bankfull width
  • Channel classification
  • Site design criteria
  • Road geometry
  • Access
  • Survey (topographic map)

47
Savage Creek Bridge
  • Preliminary Design
  • Channel width 15
  • Structure alternatives
  • Bridge (concrete and timber)
  • Aesthetics
  • Road alignments
  • Hydraulics
  • Velocities (4-6 fps _at_ bankfull)
  • Freeboard (2 at 100-year event)

48
Savage Creek Bridge
49
Savage Creek Bridge
50
Savage Creek Bridge
  • Final Design
  • 43 span x 17.5 wide timber bridge
  • Skewed at 30o
  • Timber deck and curbs
  • Precast concrete grade beam foundation
  • Road alignment
  • Curve widening through bridge
  • Shift alignment on curve
  • Grade control structures (step pools)
  • 4 step pools
  • 1 rock weir

51
Savage Creek Bridge
52
Savage Creek Bridge
53
Savage Creek Bridge
54
Savage Creek Bridge
55
Savage Creek Bridge
56
Savage Creek Bridge
57
Savage Creek Bridge
58
Savage Creek Bridge
  • Constructed in 2006
  • Construction Time 17 days
  • Contract allowed 19 days no more than 2 weekends
  • Engineers Estimate - 100,600

59
Upper Main Red River Arch Culvert
  • Existing 6 corrugated metal culvert
  • Existing culvert deemed barrier to aquatic
    organism passage

Plunge-pool at outlet High velocities through
culvert Culvert width/channel width ratio 0.54
60
Upper Main Red River Arch Pipe
  • Site Characteristics
  • Bankfull Width 11
  • Rosgen E type channel
  • Design flows
  • 2-Year 36 cfs, 100-Year 123 cfs
  • Median grain size 2
  • Design
  • Channel width 11, Structure width 13
  • Steel structural-plate arch culvert 13 span x
    4-1 rise x 40
  • Fish rest stop rocks
  • Precast concrete footings w/ stemwalls
  • Allowed to close road for 3 weeks ATV detour

61
Upper Main Red River Arch Pipe
62
Upper Main Red River Arch Culvert
63
Upper Main Red River Arch Culvert
64
Upper Main Red River Arch Culvert
65
Upper Main Red River Arch Culvert
66
Upper Main Red River Arch Culvert
67
Upper Main Red River Arch Culvert
68
Upper Main Red River Arch Culvert
69
Upper Main Red River Arch Culvert
70
Upper Main Red River Arch Culvert
71
Upper Main Red River Arch Culvert
72
Upper Main Red River Arch Culvert
73
Upper Main Red River Arch Culvert
74
Upper Main Red River Arch Pipe
75
Upper Main Red River Arch Culvert
  • Constructed in 2007
  • Construction Time 8 days
  • Cost - 80,600

76
Questions???
  • Questions???
  • Reference
  • Stream Simulation An Ecological Approach to
    Providing Passage for Aquatic Organisms at
    Road-Stream Crossings
  • http//www.stream.fs.fed.us/fishxing/
Write a Comment
User Comments (0)
About PowerShow.com