Title: Decision Briefing PPBES: NOAA IT Planning
1Decision BriefingPPBESNOAA IT Planning
- Dennis Morgan
- representing the
- NOAA IT Planning Working Group
- February 20, 2007
2 Outline
- Purpose
- Issue
- Coordination
- Alternatives
- Example
- Recommendation
- Decisions Required
3Purpose
- Decision Briefing
- To set the stage for FY2010-2014 NOAA IT Planning
Execution Strategies
4Issue
- FY2009-2013 IT Planning Guidance had little
impact on development of PPBES deliverables - Program Adjustments were not influenced
- Not relevant to Programmatic IT
- Matrix external to POP process
- Complex, confusing, and burdensome process
- Result
- What we did last year did not result in any
program adjustments for IT Infrastructure (except
in the IT Services and Satellite Services
Programs) - No additional funding requested to support IT
Security CA process (except in the IT Services
and Satellite Services Programs) - Problem
- How do we get program adjustments for IT
Infrastructure into PPBES planning for
FY2010-2014?
5Coordination
- Coordination Completed
- LO/SO CIO Reps serving on IT Planning WG
- Program Planning Integration (PPI)
- CIO Council
- Goal Teams
- Coordination Planned
- Synchronize with IT Cost Accounting Working Group
- NOAA CIO CFO Councils ? Collaborative Synergy
- LO/SO CIOs working directly with AAs, DAAs, CFOs,
GTLs, and PMs
6Alternative A (Status Quo) provides a Planning
Matrix to determine IT Infrastructure costs, but
no assistance for Programmatic IT
7Alternative B uses Program Headcount and IT
portion of Fully-Loaded FTE to determine IT
Infrastructure costs, and provides a Planning
Checklist for Programmatic IT
8Alternative C uses new capability in IT Services
Program to plan for IT Infrastructure costs, and
provides a Planning Checklist for Programmatic IT
9Example Alternative C - AWIPS Program Adjustment
Planning
Programming
Budgeting
Execution
Local Forecasts and Warnings POP 1.0M
WW Program Plan 1.0M
NWS PPA 1.1M
NWS PPA 0.65M
Programmatic IT AWIPS
0.7M Appropriation
Communication
NWS Center of Excellence PPA 0.05M
IT Services POP 0.1M
Program Support Program Plan 0.1M
IT Infrastructure
10Recommendation
- Alternative C
- Uses new NOAA IT Infrastructure Optimization
capability in IT Services Program to plan for
Enterprise-wide IT Infrastructure costs and - Provides a CIO Council-approved Planning
Checklist for Programmatic IT - Benefits
- Shows NOAA CIO Council actually listened to
Feedback from the Goal Teams to build a process
that will serve both the customer and the CIO
Council, leading to more accurate planning of
NOAA's IT costs - CIO Council, EA Committee, and IT Planning WG
will be providing a valuable service to NOAA by
identifying IT Infrastructure costs since PMs
have little knowledge in these areas - PMs System Owners will be more fully-equipped
to identify requirements for new Programmatic IT
investments in new and existing systems
11Decisions Required
- Select best alternative for FY2010-2014 NOAA IT
Planning Execution Strategies - Grant approval for Working Group to partner with
PPI and Goal Teams to implement CIO Council
decision - CIO Council Chair agrees to deliver Info Briefing
to PAE and CFO Council, and submit Virtual Info
Briefing to NEP/NEC - FY2010-2014 Planning Phase begins on 3/1/07, and
POP development commences on 4/16/07
12BACKUP SLIDES
13PPBES Checklist for Programmatic IT Investments
- Developed Checklist v1 on 2/14/07 to cover
- New IT investments for existing systems
- New IT investments for new systems
- Produce Checklist v2 by 3/1/07
- Share with CIO Council by 3/6/07
- CIO Council decides by 3/13/07
- Share with Goal Teams PPI (for inclusion in
Planning Guidance) by 3/16/07 - Distribution to Program Managers System Owners
by 3/23/07
14Coordination Working Group Members
15Coordination Program Planning Integration (PPI)
- Sue Kennedy Dennis Morgan (12/21/06)
- Reviewed Working Groups Alternatives
Recommendations for FY10-14 IT Planning - Discussed modification of POP format CasaNOSA
- Discussed responsiveness to Goal Team feedback
- Dan Mamula Dennis Morgan (1/29/07)
- Discussed modification of CasaNOSA
16Coordination CIO Council
- Sue Kennedys Discussion (12/12/06)
- Review of FY0913 Planning Phase and CIO Council
Guidance - Feedback received from GTLs and PMs via online
survey - Dennis Morgans Info Briefing (1/23/07)
- PPBES NOAA IT Planning
- Approval for Working Group to coordinate with
Goal Teams (1/23/07)
17Coordination Goal Teams
- Ward Seguin (Weather Water) attended Info
Briefing (1/23/07) - Working Group met with Goal Team reps (1/25/07)
- Emily Menashes (Ecosystems)
- Adrienne Antoine (Climate)
- Ward Seguin (Weather Water)
- Ashley Chappell (Commerce Transportation)
18Feedback Goal Teams (Face-to-Face)
19Feedback Goal Teams (PPI Online Survey)
- Precede POP development
- Should work to make sure as many council and
other data calls are done before POPs are
developed. - Recommend all council data calls be done outside
the CasaNOSA POP and be completed earlier than
the CasaNOSA POP start date. - It may have been more useful to program managers
if the IT Planning Data Call was done in December
2005 - January 2006 in preparation for FY2009 POP
development. That would have been a good time of
year for the program managers to complete the
Matrix, and it would have provided the CIO
Council time to review my data and provide
comments, feedback, and suggested improvements to
each program manager and Goal Team Leads.
Instead, I was faced with competing priorities
(i.e., POP development vs. IT Planning Matrix).
Do I need to tell you where I spent most of my
time? - Integrate with POP
- CIO requests improved from last year but not in
POP....will this information connect? - CIO guidance wasn't integrated into the POP and
so caused some confusion in our program and
others.
20Feedback Goal Teams (PPI Online Survey) cont.
- Complex, confusing, and burdensome
- CIO - Very detailed and technical, so some
requests for information were over our heads. - Found the guidance from the CIO confusing and not
particularly relevant to my program. Despite the
lack of relevance to my program, the CIO Council
insisted that all programs complete their IT
matrix. - CIO data call was unreasonable. Programs depend
on line offices to maintain equipment, such as
routers. Programs had to request that information
from the LOs. The CIO already has a direct
connection to LOs, and LOs can approximately
apportion activities to programs. Programs should
not be dragged into counting pieces of IT
hardware. Why does PPI endorse requesting so much
detail in one area of activity when it is moving
to focus on the big picture in most other areas
of planning? In the future, the CIO should
collect that data through its own channels. - CIO guidance was ambiguous and confusing.
- Clear and understandable
- CIO request was clear, but not all offices use
the same definitions for terms used. - CIO Council requested IT needs and status by
Program, when the data are tracked by LO. - The CIO Council's guidance was straightforward
however, it would've been helpful if their online
guidance was linked from the PPBES website,
instead of just hanging on the NOAA/OCIO 'IT
Planning and Budgeting' webpage. Also, I noticed
that the link that was published in FY09 Planning
Guidance Memo Supplemental III was the wrong one
('.htm' was omitted). - CIO guidance was very thorough and clear.
21Feedback IT Planning WG
- Programs plan for programmatic IT and changes
that have new IT requirements - NOAA/OCIO already has guidance to facilitate the
development of Budget 1-pagers Exhibit 300s - How does Planning by Program Programming by
Goal/Sub-Goal translate to Budgeting Execution
by LO/SO? - Whos paying for IT? Programs or overhead tax
fund? - Whos using IT?
22PPBES Deliverables
NOAA CIO Council reviews/assesses and provides
input/feedback
23Importance of IT Planning Key Drivers
- All NOAA programs use IT to support their
business - IT costs are significant and need to be factored
into planning - NOAA Functional Model ? Capital Management ?
Acquire, Build, Maintain Infrastructure - The money will not be there unless planned for
via PPBES - Programs have to plan for their future IT costs
- OMBs expectation Ensure all current IT systems
are compliant with IT Security policies before
investing in new IT
24NOAA Exhibit 53 (FY08 Budget, 12/28/2006)
- OMBs goal is a 5/year government-wide reduction
in IT infrastructure costs. - If our IT planning efforts result in higher IT
infrastructure costs, DOC OMB will require NOAA
to show clearly how supporting the federal
Infrastructure Optimization Initiative (IOI)
e.g., movement toward consolidation in the areas
of desktop management/help desk,
telecommunications, and data centers increases
costs.
25(No Transcript)
26Areas Covered by FY09-13IT Planning Matrix
- Application Hosting
- Archiving
- Data Networks (LAN)
- Desktop / Seat Management and Support
- Enterprise Architecture
- Facility Management
- High Performance Computing
- IT Security
- Metadata
- NOAAnet
- Technology Refresh
- Desktops
- Laptops
- Servers
- Mainframes
- Routers
- Switches
- Storage
- Telecommunications
- Web Presence
- Workforce Collaboration
27Communication
- Improved communication with Goal/Sub-Goal Team
Leads, Goal Coordinators, and Program Managers,
and System Owners is KEY! - LO/SO CIOs must serve as Champions for the IT
Planning effort to be successful - IT Working Group members and LO/SO CIOs should
conduct briefings BEFORE the POP process starts - Brief Goal/Sub-Goal Team Leads Goal
Coordinators - Brief Program Managers
- Follow-up by attending Goal Team and Program
meetings to provide assistance, answer questions,
and collect feedback