Title: California


1
Californias Expedited Power PlantPermitting
ProcessesRoger JohnsonSiting Office Manager
  • California Energy Commission
  • March 15, 2001

2
Topics
  • Governor declares energy emergency
  • Governors Executive Orders
  • Expedited Permitting Processes
  • Emergency Permit Review Status

3
Governors Executive Orders
  • 6 Executive Orders Issued February 8
  • 1 Executive Order Issued March 7
  • Focused on power plants
  • Planning
  • Siting
  • Permitting
  • Construction
  • Operation

4
Governors EOsLicensing
  • Maintain 12-month AFC
  • Maintain 6-month AFC
  • Reestablish 4-month AFC
  • Establish emergency permit process
  • Establish 45-day amendment
  • Establish 7-day amendment

5
6-month AFC
  • Purpose - Expedite clean projects
  • Projects
  • No public health or safety concerns
  • Mitigated environmental impact
  • No significant adverse energy system impact
  • Comply with legal requirements
  • Have a contract and skilled labor
  • Address disproportionate impacts
  • Control site
  • Priority for superior projects

6
4-month AFC
  • Purpose - Peaking projects
  • Data adequate by Dec. 31, 2001
  • On line by Aug 2002
  • Projects
  • No public health or safety concerns
  • Mitigated environmental impact
  • No significant adverse energy system impact
  • Comply with legal requirements
  • Have a contract and skilled labor
  • Address disproportionate impacts
  • Control site

7
Emergency Permit
  • Who Qualifies?
  • Peaker power plant
  • On line by September 30, 2001
  • ISO Summer Reliability Contract
  • 50 MW or larger
  • No fatal flaws

8
Emergency Permit
  • Length of CEC license
  • Life of project if
  • contract with CDWR or CAISO
  • meets continuation criteria at end of contract
  • meets BACT and has permanent air emission offsets
  • compliance with all Energy Commission conditions
  • site control, and
  • project is a permanent facility.
  • 3 years with option to recertify w/o contract

9
Emergency Permit
  • Purpose - Peaking projects
  • Fatal Flaw Analysis
  • No public health or safety concerns
  • Mitigated environmental impact
  • No significant adverse energy system impact
  • Comply with legal requirements
  • Have a contract and skilled labor
  • Address disproportionate impacts
  • Control site
  • No or minimal linear facilities
  • Exempt from CEQA requirements

10
Emergency PermitSchedule
11
Emergency PermittingStatus
  • Executive Orders D22-D27 February 8
  • Process defined February 27
  • Executive Order D28 March 7
  • First two applications filed March 8

12
Emergency Power Plant Permits Under CEC Review
Note Intergen Wildflower projects were
previously known as Tejas 1, 2, 3, 4, and 5
13
More Information
  • Energy Commission
  • Roger Johnson (916) 654-5100
  • Toll free Hot Line in CA (888) 871-9673
  • www.energy.ca.gov/sitingcases/peakers
  • Air Resources Board
  • Michael Tollstrup (916) 322-6026
  • www.arb.ca.gov/energy/energy.htm
  • Department of Water Resources
  • Viju Patel (916) 952-0926