Title: US CMS
1US CMS
- U.S. CMS - Construction
- Project Overview
- Dan Green
- US CMS Program Manager
- May 19, 2003
2Outline
- Technical Status of US CMS
- Financial Status Summary
- Recent Calendar baselining the RP
3Experimental Caverns
Experiment UXC55 ready July 04
Service USC55 ready Jan 04
4CMS Tracker
All Si tracker US builds FPIX with L2 managers
for FPIX - Gobbi NW, and TOB - Incandela UCSB.
5Robotic Assembly at FNAL UCSB
- FNAL pick and place gantry
- Fully qualified for production
- Starting first final modules now at FNAL.
6TOB Module Production
v33
7Pixel Detector
- Module 00 DMILL chips with dummy sensor
- Works well at 40 MHz
- Successful operation of 2x8 chips
100m
- Translation of ROC chip into 0.25 mm
CMOS - Submission end April 03
- Superior performance
Increase number transistors per pixel from 127
(old DMILL ROC) to 251 (new DSM ROC)
150m
8FPix 5 PSI43 on VHDI
columns
TBM Trailer
TBM Header
rows
Chip 1
Chip 0
9ECAL H4 Test Beam
Rusack (U. Minn) is L2 manager
10Very Front End (VFE) Electronics
- New version of FPPA received Dec 02. Faults
corrected but noise 30 higher than spec, yield
35 (instead of 50). Very Front End analogue
electronics still a concern.
ADC and MGPA DSM Chips
- Alternative New 0.25mm (DSM) ASICS, preamplifier
(MPGA) ADC submitted Feb 03, expect packaged
chips in May. - DSM front-end expected to be substantially
cheaper, consume less power and have slightly
better performance - DECISION in mid-2003 after comparative tests of
alternative systems - Prototype of VFE cards ready to test both
versions
ADC
MGPA
ADI ADCs
FPPAs
VFE Card
11HCAL HB and HE
HB complete, install onboard electronics by Q2-04
Back-flange 18 Brackets 3 Layers of absorber
HCAL PM A. Skuja , U. Maryland
12HB ECAL Test Beam Layout
Calibrate 4 wedges 02. In May 03 use PPP to
study 40 MHz beam and HE/HB transition region. ME
will also need 40 MHz operation to verify all the
electronics chain. Then into SX5. Retain facility
in H2 for permanent monitoring and tests.
13HCAL HF Fiber Insertion
If present rate maintained fibre insertion will
be finished in November 2003 (instead of April
04)
scheduled
produced
146 Channel FE Board
AD590 Temp Sensor
Low Voltage Regulator (2 / board) CERN Developed
in rad hard process
P82B96 I2C Transceiver (change to P82B715)
Custom ASICs
QIE (6 / board) Fermilab
MC100LVELT23 LVPECL-LVTTL
Honeywell VCSEL HFE419x-521 (2/board) back side
of board
MC100LVEP111 LVPECL clock fanout chip
Gigabit Optical Link GOL (2 / board)
CERN Developed in rad hard process
CCA (3 / board) Fermilab
OP184 bi-polar OpAmp
PZT222A transistor
15EMU production status
- Chamber assembly and testing (HV leak)
- 79 complete (should finish by end of 03)
- Electronics
- On-chamber electronics almost finished
- Off-chamber electronics needs 25ns test run
- Production begins following test run verification
- Skew-clear cables complete (6340 cables)
- Electronics assembly (FAST sites)
- ME23/2 (US chambers) about 60 complete
- Russia and China in operation
- Endcap Infrastructure almost complete at SX5
- Installation begins in June 03
16CSC Arrival at CERN
The Final Assembly and Test Sites are
operational. Checkout in ISR tunnel. Loveless
U. Wisconsin is L2 manager.
17ISR Chamber Testing Site
18Installing CSCs
The support posts have been installed on YE2,
ready for CSCs to be mounted as soon as gas
distribution pipes have been laid down. Start
installation in Jun 03
19Testing Receiver, Clock, EISO, Jet/Sum Cards,
Crate Backplane - U. Wisconsin
Front Clock, EISO, and Jet/Summary Cards showing
original STC and cable to test HF data transfer
to J/S at full speed
Rear Rec. Card Loop- back Cablesfor
testing Data Sharing
- ?160 MHz TTL clock with data into 200 MHz
Memories (2 ns scale)
Trigger L2 manager is Smith U. Wisconsin.
Second round of prototypes. Trigger will supply
portable system for SX5 slice tests.
20Trigger Transition to MO
- Installation in UndergroundCounting Room
- Expect access by March 05
- Sufficient time for installationand some testing
but not forcompleting commissioningwith
detectors - Need to startcommissioning earlier
- Slice Test (on surface)
- With Both HCAL and EMU
- Verify trigger functions and interfaces by
testing with detectors on surface at CERN. - Use as substitute for commissioning completion
step. - Will check as much on surface before gaining
access to underground facilities. - Milestone (HG1018) planned for completion
November 04
21Trigger Tables
- Level-1 Trigger at low luminosity (2?1033cm-2s-1)
- Total Rate 50 kHz. Factor 3 safety, allocate
16kHz
Tables exist for 1/5 and design L. Discovery
modes covered well. We think we know how to
trigger CMS and acquire the Physics.
22CMS Data Acquisition
DAQ TDR submitted end-02 Modular design of Event
Builder
8 x (12.5 kHz DAQ units)
The single-farm design, that provides maximum
flexibility in the physics selection, works.
23US-CMS Data Acquisition
- Next major milestone - Dec. 2003
- Event Builder Preseries and DAQ slice ready
- Work focussing on
- front end drivers and links
- integration and event building software
- event manager
This system will be used for the detector slice
tests. US will build first 1/8 of DAQ. ODell
FNAL is the L2 manager.
2458 Months of Reporting
US CMS
We will complete 97 of US CMS by end of FY05.
PO struggles to retain 50 contingency.
25Financial Tracking
26Recent Events Calendar -I
- Last 6 months relevant events
- CMS Week, Sept. 21, 2002 - scheduled confirmed
for first beam in April, 2007 - AR (CMS)
- CR (LHCC)
- Oct. 1 - DOE/NSF Quarterly Status Review - no
major issues
Invent slice tests for pre-ops in ME, HCAL,
Trigger and DAQ. Minimize the time before getting
Physics results
27LHC - SUSY
Energy matters! One month at 1/10 design
luminosity extends mass reach by a lot. LHC
experiments must be ready on week one for new
Physics. That perception defines the US CMS
strategy of slice tests in SX5 of ME and HCAL
with a portable trigger from the US and with a
portable DAQ since the US supplies the first
1/8 of the DAQ a stand alone segment.
28LHC - SM Higgs
The LHC detectors are designed to find the SM
Higgs. Low mass is covered by ??, ttH(bb),
qqH(WW,??). A low mass Higgs has many
accessible decay modes ? couplings measured. Plot
is 4 months at design luminosity.
29Detector Project - Endgame
The US CMS detector deliverables will be 96
complete in FY05 and finally installed in UX5 by
FY07. The BA has evolved to reflect this fact.
The Detector Project is over by FY05. The
softer profile allows US CMS to maintain the SWC
effort at a flat level in FY02 through FY04.
30Calendar - II
- ICFA, Oct. 8 - SLHC. Plans for 10 x in Luminosity
by detectors and accelerator shown publicly. - RRB, Oct. 19 - CRRB initiated. LCG as a distinct
request. Keep in the context of CMS - single
point of contact.
31Calendar - III
- SCOP ,Oct. 24 - external review of US CMS SWC.
- ITR , Nov. 12 - LITR and MITR, joint US ATLAS/US
CMS NSF proposals. Attempt to get more funding
into SWC work.
32Calendar - IV
- CMS Week, Dec. 2 - status.
- SWC Review, Jan. 16 - LBNL. NSF guidance firms
up. NSF begins to advance the ramp-up of the RP. - P5, Jan. 28 - US LHC status. well received gt
high priority. - P5, Feb 15 - HEPAP Facilities. US LHC gets
highest priority for SLHC (LC and SNAP too)
33Calendar - V
- CMS Week, Feb. 24 - status
- JOG in Washington, Feb. 24 - Discussion of RP.
DOE cuts 2.5 M in 2004 from previous guidance. - HEPAP at LBNL, March 6 - LHC Collaboration Group
presents LHC status - LITR submitted, March 14
34Calendar - VI
- FNAL DOE Review, March 18 - US CMS status.
- P5, March 26 FNAL affirms that US CMS is a high
priority item in their research program. - FNAL PAC, March 28 - Status of US CMS and physics
reach. US CMS is a part of FNAL program.
35Calendar - VII
- LHC Collab Group at NSF, Apr. 4 - well received,
funding schedule ramp up confirmed. - MO Review, April 8 baselined. Therefore
start VCR and PAC. Scrubbed MO hard -
Nevertheless, retain 3 Tier - 2 PAC.
36Current RP Guidance from DOE/NSF
US CMS was instructed to plan scope to fit inside
this guidance.
37MO Closeout
38Issues
- The ramp up of the RP is crucial. FY03 and FY04
will either get us a good start on preparation
for Physics or we will drop the ball on Data
Challenges and the Physics TDR. - A firm commitment by NSF and DOE is absolutely
necessary if we are to plan rationally. The MO
Evaluation Group and SWC Reviews are a good start.
39Summary
- Technical Progress has been good.
- Schedule has been maintained for April 07 first
beam. - Financial progress has been steady. Scope
continues to be increased. - The Project will end in FY05 with CD4-a.