Title: Application of AOI Analysis to Control Cost and Control Strategy Design in the VISTAS Region
1Application of AOI Analysis to Control Cost and
Control Strategy Design in the VISTAS Region
- Prepared by
- Gregory Stella
- VISTAS Technical Advisor Emission Inventories
- Alpine Geophysics, LLC
- VISTAS Joint Workgroup Meeting
- Raleigh, NC
- September 6, 2006
2Application Objectives
- Identify sources of residual emissions in 2018
base case within newly identified AOIs - Create cost effectiveness curves for point source
reduction options - Use to help define possible control strategies
based on findings
3Initial Conclusions
- No incremental across the board strategy
available for VISTAS domain - Additional reductions are most beneficial if
applied with geographic and pollutant specificity - Benefits will come from remaining significant
non-reduced sources
4Eastern U.S. Class I Areas
.
.
Hercules Glade, MO
.
.
.
.
.
.
.
.
5Elevated Point Source SO2 Emissions (2002 Tons)
6Limited Geography AnalysisCounties within 200km
of SIPS
7Residence Time Difference Worst Days All Sample
Days 2000-2003 Sipsey, AL
8Limited Geography AnalysisResidence Time
Difference Worst Days
9Extinction-Weighted Back-Trajectory Residence Time
10Extinction-Weighted Back-Trajectory Residence Time
11Elevated Point Source SO2 Emissions (2002 Tons)
12Sipsey Wilderness AOI2018 Emissions (Tons)
13Sipsey Wilderness AOI2018 Emissions (
Contribution)
14Sipsey Wilderness AOI2018 Emissions (Tons)
15Sipsey Wilderness AOI2002 to 2018 Emissions
Change
16(No Transcript)
17(No Transcript)
18Control Strategy DesignCost-Effectiveness
Method
- Apply all available controls to sources within
geography of interest - Sort by marginal cost per ton to develop cost
effectiveness curve - Follow curve to point of decision
- RPG yet to be determined
19(No Transcript)
20(No Transcript)
21(No Transcript)
22(No Transcript)
23(No Transcript)
24(No Transcript)
25(No Transcript)
26(No Transcript)
27Cost Effectiveness Scenario Comparison (SIPS
SO2 Reductions)
28Four Factor Analysis
- Current VISTAS process addresses three of four
requirements of RPG - Cost of compliance
- Time necessary for compliance
- Remaining useful life of existing sources
- Does not account for energy and non-air
environmental impacts - Needs to be facility specific
29Observations
- Many ways to review the data
- Which one is right for you?
30Next Steps
- Identify AOI for each Class I area
- Review of top residual point sources in AOI of
interest - Populate Source Matrix
- Determine which have been controlled and which
are controllable - Identify which may be eligible for BART
31Next Steps
- Review of cost control equation variables
- Boiler capacity and utilization used to derive
control costs - Typically default values overestimate cost of
control - Example (FGD on industrial boiler)
- 250-500 MMBtu/hr boiler
- Actual cost 1,000-1,500 / ton red
- Defaulted cost 10,000 15,000 / ton red
32Next Steps
- Determine objectives for RPG
- Source type?
- Emission total?
- Total Cost?
- Cost per ton?
- Glide slope?
- ???
33Next Steps
- Define control strategies for each Class I area
using full suite of information necessary to make
an informed decision - Apply reductions to inventories and remodel