ME10001: - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

ME10001:

Description:

It was designed to be minimum cost, using the least amount of wood and glue (no paper was used) ... for the arch ends to use as buffer in case of glue failure. ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 15
Provided by: people7
Category:
Tags: glue | lengths | me10001

less

Transcript and Presenter's Notes

Title: ME10001:


1
ME10001 Experimentation Engineering
Skills Make--Break Bridge
2
  • OBJECTIVES
  • To design, construct and test to destruction a
    minimum cost balsa wood bridge.
  • It must withstand a load of 50N, dead-centre
    applied from above.
  • It must span a gap of 0.5m.
  • It must have a maximum deflection not exceeding
    20mm.

3
  • MATERIALS COSTINGS
  • Lengths of 6mm x 6mm balsa wood strips.
  • Paper.
  • Balsa cement glue.
  • Balsa wood - 10 per 100mm3.
  • Paper - 1 per 100mm2.
  • Balsa Cement glue - 10 per mm3.

4
  • CONSTRUCTION PROCESS
  • It was designed to be minimum cost, using the
    least amount of wood and glue (no paper was
    used).
  • Triangulated structure was considered but arching
    was less expensive (less glue and wood), so
    arching was used instead.
  • Crossed arches were used to prevent twisting and
    to increase the rigidity and strength of the
    overall structure.
  • Arches designed to take load at the end load
    points.
  • A vertical support dead-centre was used to add
    some strength to the arches and allow the bottom
    frame to take some loading.

5
  • PROBLEMS ENCOUNTERED
  • Securing the balsa wood arches was difficult, and
    so stoppers and grooves were needed. The stoppers
    also aided horizontal loading.
  • It was found that the balsa wood varied in
    twisting, bending and hardness. Some lengths were
    soft and bent a lot more than other lengths.
    Therefore, the stiffer stronger lengths were
    chosen (also increasing the need for stoppers and
    grooves).
  • As some lengths bent more than others, 2 similar
    pieces had to be chosen. This also meant that the
    degree of curvature was limited to how much the
    wood could bend before breaking. An angle of 22o
    was made between arch and horizontal support.

6
FINAL STRUCTURE DIMENSIONS The arches are
650mm long each.
35mm
100mm
600mm
This is the groove support that was used to help
ensure that the arches did not come unstuck.
There was another support for the arch ends to
use as buffer in case of glue failure.
7
COST OF BRIDGE 2 x 600mm 2 x 650mm 6 x 100mm
Balsa wood 11,646 1 x 100mm 1 x
35mm 500mm2 Glue 5,000 Overall
Price 16,646
8
TESTING
9
TESTING
10
GRAPH Force (N) against Extension (mm)
11
  • GRAPH
  • The deflection of the bridge was not greater than
    20mm, which achieved the objective.
  • The maximum load that the bridge took was 37N,
    failing the objective.
  • At point X the gradient of the curve increases
    showing that there was a redundant structure
    within the bridge. This was 1 of the arches, as
    the lengths were not quite correct 1 arch took
    the primary load and then used the 2nd arch to
    help spread the load throughout the structure.
  • The judders along the curve show slipping
    joints.
  • The sharp descents show sudden breaks within the
    structure (i.e. joints breaking, supports
    collapsing, etc).

12
  • EVALUATION
  • The arches were skew, which meant that 1
    horizontal support failed before the other as it
    was taking the majority of the load. By making
    the arches symmetrical and aligned properly, the
    loading should be equal in each support
    increasing the total possible load.
  • The central vertical supports support should have
    been above the horizontal supports, to increase
    possible loading as it snapped soon after loading
    began. Hence, giving to additional support to the
    arches.

13
  • EVALUATION
  • If the arches had been doubled-up, the bridge
    would have supported more load as the first main
    failure was 1 of the arches failing, which could
    have been prevented with doubled-up balsa wood.
  • The use of triangles within the arch structure
    would have also helped distribute the loading
    throughout the bridge, allowing a greater
    possible load with increased stiffness.

14
  • The bridge only satisfied 2 out of three of the
    objectives.
  • Maximum deflection was lt20mm.
  • It was a minimal cost bridge.
  • It did NOT withstand a load of 50N.
Write a Comment
User Comments (0)
About PowerShow.com