Title: 1 of 1
1STARDUST Project CRITICAL EVENTS READINESS
REVIEW COMET P/WILD 2 ENCOUNTER JPL Deep Space
Mission System (DSMS) Telecommunication Mission
Service Manager Steve Waldherr
JPL 303-411 AM / 301-427 PM LMA MSA 1 818
354-1275 0800 AM - 0500 PM PST 20 Nov 2003
2Deep Space Network (DSN) Readiness
- All Required Facilities and Upgrades completed
and On-line - Upgraded all 34m BWG Antenna w/ 20KW Transmitters
- Project Agreements in Place
- Project Service Level Agreement, June 2001
- No amendments for Wild II encounter
- Project Requirements/Telecommunications
- and Missions Operations Directorate Support
- Agreement (PR/TSA) for STARDUST
- (SDU_PRTSA.doc-9/25/98)
- Negotiations for Required DSN Tracking
- Completed and Coverage to be Provided
- STARDUST 80 deg in Sky from Mars
- Only 3 Hour Overlap for 10 Hour Pass
- Mission Can be Performed on 34m Net
- 70m Net Used to Give Good Margin
3Deep Space Network (DSN) Readiness
- Summary of DSMS Requirements for the Stardust
Wild II encounter - NO Special DSMS Hardware or Software required
- Support from DSMS 34 meter and 70meter subnet
- Support standard DSMS Telemetry Service
- Utilization of MCD III
- Support standard DSMS Command Service
- Support standard DSMS Tracking Service
- Two Way Doppler during the entire encounter
- Used for Radio Science to determine Coma
composition and effect on the spacecraft - Used for Navigation purpose
- Standard DSOT (AMMOS) services
4Deep Space Network (DSN) Readiness
- Summary of DSMS Requirements for the Stardust
Wild II encounter Continued - DSMS Modified Configuration Control
- December22/356-1500 through January 8/008-0400
- SFOC Configuration Control Level 2
- TCM-11
- December 22/356-1500 through December
24/358-2300 - Wild-2 Approach/Encounter
- December 31/365-0000 through January 5/005-2100
- SFOC Configuration Control Level 1
- TCM-12
- December 31/365-1500 through December 31/365-2100
- TCM-13
- January 2/002-0100 through January 2/002-0600
- TCM-14/Final Update/Encounter
- January2/002-1200 through January 3/003-0100
5Deep Space Network (DSN) Readiness
- DSMS Level 1 Support Requirement Summary
- Criticality level 1 Per DSMS 841-001 Document
- Significant one of a kind events such as
launches, encounters, and unique scientific
events. A ground system failure could
jeopardize the spacecraft, result in loss of
unique scientific data, or result in the failure
to achieve one or more mission objectives. The
DSN is at its highest level of mission readiness
when in the Level 1 posture. - DSMS Level 1 Support Times
- TCM-12
- December 31/365-1500 through December 31/365-2100
- TCM-13, TCM-14/Final Update/ Encounter
- January 2/002-0100 through January 3/003-0100
6Deep Space Network (DSN) Readiness
- DSMS Level 1 Support Requirement Summary
Continued - Additional technical expertise is onsite at the
DSCCs, NOCC, and ROSA - NISN and Carrier notification
- Telcom link analysis
- RFI analysis and spectrum protection is in place
- Critical Event Advisory Message
- Resource Management Plan
- Most reliable power source
- MERR and MRMR
7Deep Space Network (DSN) Readiness
- DSMS New Implementations
- DSS 55 in Madrid, which is a 34-meter Beam Wave
Guide was declared operational 1 November - Stardust participated in successful Demonstration
passes prior to operational date - DSS 55 being used routinely by other mission on a
daily basis since 1 November - No issue or concerns with DSS-55 support
capabilities - Other
- Alternate Assets (New Norcia/Parkes) does not
benefit Stardust and is not planned - DSMS array does not benefit Stardust and is not
planned - Goldstone Emergency Control Center (ECC) does not
benefit Stardust and will not be used
8Deep Space Network (DSN) Readiness
- DSMS Triage
- DSMS Triage Plan (DSMS 802-009) issued Oct 29
2003 - Stardust has participated in several DSMS work
shops in which several triage scenarios where
worked - DSMS Triage Plan augments the existing Standard
Operations Plan for the Deep Space Network (DSM
841-001) - DSMS Triage Plan provides special DSMS War Room
- JPL DSN Mission Event Readiness Review (MERR)
held on 13 November 2003 - Held 3 weeks earlier then standard (event minus
30 days) - 1 Advisory written, No Request For Actions (RFAs)
- Review Board complimented Project on the
robustness of mission planning for the encounter - Review Board consensus was that the DSN is
prepared and ready to support the Wild II
encounter