Title: AMS02 UPS Status
1AMS-02 UPS Status
- C.K.Ho Y.P.Chang
- J.H.Yeh C.B.Huang
- Jan. 12, 2006
2Outline
-
- Modification of Box
- Structural Analysis
- Non-Structural Fastener Containment
- UPS SOW Rev B
- Phased Schedule
- Action Item Review
- JSC Shipping Document
3RIGHT ANGLE PRINTED BOARD MOUNT DB 25 CONNECTOR
SND25F100E2G
J6
J16
4BMS
5Modification of Box
- Provide CAD file so that it can be integrated
into the payload model for evaluation - Ross Harolds preliminary assessment is that
increasing the height dimension 15 mm will not be
a problem. - Splitted inner bracket
- Stress analyses
615mm increase in height
- 15 mm increase in the UPS side wall height.
- Move BMS 4mm up
- interior height of the box --- 180 mm,
- exterior height of the box ---196 mm.
715mm increase in height
8UPS BOX
9Structural Analysis
- Y.P.Chang C.B.Huang
- UPS Box Engineering Diagram
- UPS Structural Analysis Report---ANSYS
- Bolt_Nut_Insert Stress Analysis Report--- MathCAD
10Structural Analysis
- Add 15mm in box height
- Splitted inner bracket
11Structural Analysis
- Margin of Safety of bracket structure is 6.72,
and ultimate margin of safety is 5.13. - All the margin of safety of the bolts are
positive. And the minimum margin of safety is
0.107 (Total Tension Yield) which occurred at
Joint 1.
12Joint Assembly
13Non-Structural Fastener Containment
- The screws heads will be encapsulated with Epoxy
for containment purposes. - This process has been approved by JSC Safety and
Structure and Materials.
14Non-Structural Fastener Containment
- either of the following adhesives
- Scotch-Weld 2216 B/A (epoxy w/ amine catalyst)
- EPON 828 (epoxy) with Versamid 140 catalyst
(polyamide) - Any fasteners that are exposed to Atomic Oxygen
(AO) place a piece of Teflon tape over the cured
epoxy. - Please supply adhesive Teflon tape
15Means of Containment---Bruce Sommer
- Staked Fastener
- Not Acceptable
- Fully Potted Fastener
- Acceptable
16Verification Process--- Bruce Sommer
- Include the potting of the fasteners as a line on
a TPS to be signed and stamped by appropriate
quality control personnel. - Verification photos of the potted fasteners can
be taken where possible. - Whats TPS?
17UPS SOW Rev B
- The AMS-02 project intends to release a Rev. B to
the SOW to expand the battery level thermal
testing temperature range, based upon the new
thermal analysis results, to which you have
already concurred.
18SOW 4.1.1.5 Electrical Interfaces
- The following interfaces are required between the
battery/BMS and the CAB. - Battery Charge Cabling
- Battery Discharge Cabling (to monitor electronics
and to Quench Heaters via the CAB) - There is a Charge Enable signal (AKA the
Battery Safety Warning Signal), J2 Pins W and
V, to allow charging under normal conditions, the
signal is closed (shorted, resistance lt1Ohm) when
charging is permitted, it is open (resistance
gt1MOhm) when charging should not be permitted.
19Appendix B 4.3 Overvoltage
- The battery shall be charged to 35.0 V (40 .0 V,
original) at C/10 rate, or until the
resistance across J2 Pins W and V increases above
1 MegaOhm, and held at 35.0 V for 6 hours??? - The battery electronics DO NOT inhibit the
charging of the battery and DO NOT independently
prevent overcharge. The electronics will ONLY
open the Charge Enable signal. This signal MUST
be monitored externally and charging MUST be
stopped externally when this signal goes OFF
(high impedance).
20Appendix B 4.3 Overvoltage
- The test shall be considered successful when
proper operation of the BMS Charge Enable OPEN
signal is verified.
21Appendix B 4.3 Overvoltage
22Appendix B 4.4.2 External Short Circuit
- Load change from 90 amp to 72 amp
- But according to (HS-BEA301-001E)
- A current between 7A and 80A is permitted for
approximately 800ms. - Overcurrent greater than 80A is interrupted
within 200?s maximum. - Change to 85 amp???
23Appendix B 4.4.2 External Short Circuit
- ?Grant Kokoszka of Eaves Devices?The threshold
for the immediate Protection Switch break is
80A. As I recall, 71A is the maximum attainable
current under proper conditions, and the 80A
selection was made to provide a very comfortable
margin. Our BEA301 test procedure provokes the
break with an 82/83A minimum load current
(imprecise due to use of resistive load, see note
below for technical details). - (Technical Note on 82/83A in ATP Reading
through it, the ATP may seem to suggest a
verification at 84A min (stated 86A 2A), but
this resistive setting is applied before the BMS
is placed in circuit, thereby adding resistance
and reducing current.)
244.7 Thermal Vacuum Test and Figure A
- (Rob) The higher temperatures seem a bit extreme
to me. I dont foresee a performance or safety
issue with the tests as described (Qual at 61C
and Acceptance at 51C), but it just seems a lot
higher than the maximum expected temperature per
Appendix D. Test is fine, but is it an over-test?
- (Tim) The higher temperatures are based upon
thermal analysis performed here at Jacobs
Sverdrup. - (HS-BEA301-001E) These sensors are Elmwood 3200
series thermostats, specified to close at a
temperature of 60C and open again at a
temperature of 55C.
254.7 Thermal Vacuum and Figure A
- ?Rob? The thermostats
- OPEN at 50 2.8C
- CLOSE at 60 2.8C
- ?Rob?NOTE I STRONGLY recommend NOT testing the
battery at 60C. This will put quite a stress on
the chemistry of the cells - high temperature exposure is not good, leads to
life and performance limiting degradation of the
cell materials. - The thermostats and electronics are tested here,
independent of the cells. There is little reason
to be concerned that they have failed during
transit or battery assembly. If its a real
concern, we may be able to come up with some
other test to verify operation.
26UPS Thermal Vacuum Test Profile
27Appendix B 4.2 Thermal Environment Test
- Battery shall undergo ten charge/discharge cycles
at the following temperatures. The temperatures
tested shall be 25 ºC, 0 ºC, 20 ºC and 51 ºC (40
ºC, original). signal goes OFF (high impedance).
28Appendix B 4.5 Thermal Cycle
- Place battery in a thermal chamber and raise the
temperature of the chamber to 61 ºC (50ºC
,original) in one hour .
29Appendix B 5.6 Thermal Cycle---omit ???
- Place battery in a thermal chamber and raise the
temperature of the chamber to 50ºC in one hour . - Judith 4.7 Thermal Vacuum Test, was ADDED. But
since thermal cycling is being performed, I would
recommend doing just vacuum leak checks.
304.6 Vibration
- The fully charged batteries vibrate for 15
minutes in each of the x, y and z axes. Moniter
OCV. - One D/C/D cycle. 2nd D capacity within ?5 of the
capacity in the 2nd discharge test of 3.3
31Vibration Test
- Since the UPS boxes (qty. 2) are to be vibration
tested attached to their mounting brackets, the
plan is as follows - Qualification test 1 QM 1 EM
- Acceptance test 2 FMs
- Acceptance test 1 FSM (1 QM)
32Vibration Fixture Assembly
33Main Adapter Plate
34Left Adapter Plate
35Right Adapter Plate
36Completion Phased Schedule
- Rob My schedule would be to ship
theelectronics and battery modules out on
1/27/06.
37UPS Milestone Schedule
38UPS Battery Test
- Physical, electrochemical characteristics,
charge/disch. cycle, vacuum leak test --- 22days - EDU TESTS---56days
- Qualification Tests---64days
- thermal enviroment---32days
- performance test, overvoltage, discharge
reversal, external short circuit, thermal cycle,
vibration---24days - Thermal Vacuum Test---8days
- FAT---30days 8days TVT
39Action Item Review
- 25.1 UPS TVT test at NSPO
- when?
- QU 09/13 to 09/22
- FU 11/3 to 11/15
- Test fixtures? Procedures?
- CH Lin will make the request.
- 25.2 Portable UPS tester
- Y.T.Ting, 1-Apr
405.5 Thermal Vacuum Test
- UPS should provide formal request to NSPO.
- Test schedule, interface (electrical, mechanical,
thermal), scenario should be described. - NSPO needs to go through internal reviewing
process after we get the formal request. - The available window is after May 2006.
41Action Item Review
- 25.2 Portable UPS tester
- Y.T.Ting, 1-Apr
42(No Transcript)
43(No Transcript)
44(No Transcript)
45JSC Shipping Document
46Updated UPS Weight Data
Misc. Hardware J1J2 230g Intercell Connector
200g Screw Nut 20g Adhesive 50g Flux
100g RTV566 200g Wire 100g (6.4g8m29.3g1.4m)
Total900g X 21.8kg
47Module Assembly
- Module 001 10.194 in.
- Module 002 10.193 in.
- Module 003 10.195 in.
- Module 004 10.196 in.
- Module 005 10.192 in.
-
- Nominal 10.194 0.002 in.
48bondpath
- Per Mike The ChoTherm goes under the complete
cell/flange footprint. Hence we need some sort of
bondpath to the cell brackets and cell walls (or
are the cell walls totally floating?).---copper
sheet
49Cell Module / MCB to J1/ J2 Connector
50 UPS mounting on Upper Trunnion Bridge
- UPS will be mounted on Vacuum Case Joint Upper
Trunnion Bridge of USS-02 via Outer Inner
Bracket. - Inner Bracket has 13 NUT, SELF-LKG,
PLATE(NAS1789C4M)fastened with 26
RIVET(MS20426AD3-7A). - Inner Outer Bracket will be fastened with 13
15 sets of NASA provided 1/4 inch
bolts,NAS1954CX length is TBD by NASA
51UPS mounting on Trunnion Bridge
- Outer bracket
- (NAS1291C4M nut NAS1587-4 washer) installed
on the inside of the USS beam. - The screws that pass thru the outer bracket
thread into regular nuts (NAS1291 or similar)
not nut plates.
52The Installation of the UPS
- Per Ross Harold
- a. Attach the Outer UPS Bracket to the USS
- b. Attach the Inner bracket to the UPS
- c. Lift and hold the UPS Inner Bracket in
place - d. Install screws thru USS into Inner
Bracket - e. Install screws thru Outer Bracket into
UPS boxes - Note It might be a good idea to have an
installation bracket to hold the boxes together
during installation. Another option would be to
split the inner bracket so each box could be
installed separately since they are fairly heavy
Roberts arms might get tired otherwise.