2Background
- Environmental Heavy Cost Investments Planning
(EHCIP) Project (Nov. 2003 Nov. 2005) - Investment Packages Component of the project
- Long list of the projects collected through
questionnaires - 2 widely participated workshops (April 2004 and
June 2005) from all the relevant stakeholders
including governmental organizations, NGOs,
universities, municipalities - "Project Ranking Methodology and "Project
Prioritization Manual were identified. - Screening and ranking of the projects
- Selection of the 6 demonstrative investment
projects (solid waste, waste water, air quality)
under EHCIP Project
Republic of Turkey Ministry of Environment and
Forestry
3Background EHCIP Project
Selection of 6 Demonstrative Project
Request for projects for pipeline
Response rate 50gt250 project ideas
ScreeningEU relevanceCommenced?
Project rankingmethodology
Stakeholderworkshop
Revise methodRanked list
12 projectssuitable
6 out of 12selected
Pre-appraisalof16 projects
Republic of Turkey Ministry of Environment and
Forestry
4Background EHCIP Project
Assessment of Prioritization under EHCIP Project
- The process
- Systematic
- Rational
- Stakeholder involvement
- Free from political interference
- Results The six highest ranked projects
- Air (1)
- Karabük AQ management project
- (No investment component)
- Water (2)
- Nevsehir WWTP project (2006 Program)
- Tokat WWTP project (2006 Program)
- Waste (2)
- Çanakkale SWM Project (2005 Program)
- Kusadasi SWM Project (2005 Program)
- Industrial Pollution Control (1)
- Dilovasi OID Pollution Control Project
- (under tendering through external credit)
Republic of Turkey Ministry of Environment and
Forestry
5Background
- New Prioritization Study (2006-2007)
- Questionnaires were sent to 450 municipalities
over 50.000 populations (census 2000) and about
300 applications were received. - Complementary data from Iller Bank, TurkStat,
SPO, DSI, Treasury. - The same screening and ranking criteria as
defined by EHCIP Project
Figure 1 Distribution of the project proposals
Republic of Turkey Ministry of Environment and
Forestry
6Screening and Ranking Criteria
1) National Project Prioritization List
B. Ranking Criteria
7RESULTS - Prioritized Pipeline
- After the screening, the national prioritized
pipeline is composed of totally 131 projects - 61 wastewater projects
- 52 solid waste projects
- 18 drinking water projects
- Finally, 3 separate sectoral pipelines for
- - wastewater,
- - drinking water,
- - solid waste.
Figure 2 Distribution of the ranked projects
The final pipeline is published as sectoral
ranking lists in the website of the MoEF
(www.did-cevreorman.gov.tr). Also, a Final Report
on the prioritization study is published on the
website.
8RESULTS Indicative List of Major Projects
- An indicative shortlist of the prioritized major
projects (gt10 M) is annexed to Environmental
Operational Program (OP-Env) for 2007-2009 period
with the relevant financing tables - Technical Assistance Projects are being
undertaken to prepare IPA investment packages for
the projects in the indicative list of OP-Env.
9ENVIRONMENT OPERATIONAL PROGRAM
- State of Play with EOP
- EOP sets the Program Strategy and Financial Plan
for environment sector under IPA Program for
2007-2009 Period. - Final Draft of Environment OP was submitted to
the European Commission in October 2007. - Approval of EOP is expected by the end of 2007.
10EOP PROGRAM STRATEGY
Priority Axes
Priority Axis 1 Improvement of water supply,
sewerage system and wastewater treatment
Measure 1.1 Imrpovement of water supply quality
Measure 1.2 Improvement of recieving body
quality
Priority Axis 2 Development of integrated solid
waste management
Measure 2 Increasing of waste recycling and
improvement of sanitary landfill systems
11EOP PROGRAM STRATEGY
Priority Axes
Priority 3 Technical Assistance
Measure 3.1 Enhancing the management of
Environment Operational Program
Measure 3.2 Enhancing the planning capacities of
the Final Beneficiaries
12EOP FINANCIAL TABLE FOR 2007-2009
13EOP INDICATIVE LIST OF MAJOR PROJECTS
14INDICATIVE MAJOR PROJECTS
- Priority 1
- 12 Wastewater Projects
- 4 Drinking Water Projects
- Priority 2
- - 10 Solid Waste Projects
15 Republic of Turkey Ministry of Environment and
Forestry
Thank you for your attention