Assembly of Modules to Cylinders - PowerPoint PPT Presentation

About This Presentation
Title:

Assembly of Modules to Cylinders

Description:

Procedure II: Apply Thermal Grease. A rectangular mask covers cooling block (maintains thickness of grease joint) ... Grease squeezed out of reservoir by piston lever. ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 32
Provided by: viehh
Category:

less

Transcript and Presenter's Notes

Title: Assembly of Modules to Cylinders


1
Assembly of Modules to Cylinders
  • Georg Viehhauser

2
Assembly at Oxford and KEK
  • Barrels come to Oxford/KEK from RAL with all the
    services mounted and tested.
  • Modules are only items left to be added at
    Oxford/KEK to complete cylinders
  • Limited space ? high precision during mounting
    required.
  • Tasks
  • Mechanical location fixing of module,
  • Thermal mechanical connection to cooling
    system,
  • Alignment connection of dogleg.
  • After mounting performance has to be verified.
  • Use all final (or very close to it) ATLAS SCT
    components (power supplies, off-detector
    electronics, DCS, cooling).
  • Compare performance to checks after module
    assembly.
  • System studies.
  • After passing final acceptance checks Barrels
    are shipped to CERN for final 4-barrel assembly.

3
Transport
  • Transport from RAL to Oxford/KEK all services,
    but no modules.
  • Transport from Oxford/KEK to CERN with modules.
  • RAL ? Oxford ? CERN B3, B5, B6, all road.
  • RAL ? KEK ? CERN B4, by plane.
  • Environment Temperature humidity controlled,
    ESD, mechanically isolated.

4
Transport Box
  • Two box design
  • Inner box
  • Al protective frame with conductive plastic
    panels,
  • Central part stays around barrels all time (even
    during assembly),
  • Wrapped air-tight during transport.
  • Outer box
  • Steel structure and panels,
  • Handling points for shipping.
  • Mechanical coupling through wire rope isolators.
  • Plane transports might need different setup.

B3 inner box
Box assembly
5
Service Cages
  • All services, which will later be fanned out on
    the thermal enclosure, have to be stored safely
    for assembly and transport (LMTs, capillaries,
    readout fibres, DCS sensor wires).
  • Storage assembly has to
  • satisfy ESD and grounding requirements for
    checks,
  • provide temporary connections for services during
    assembly checks,
  • clear adjacent barrels for 4-barrel assembly.

6
Oxford Assembly Area- Heavy Lab
7
Module Reception - Storage
  • 1500 modules will be shipped from all over the
    world to Oxford
  • Shipping box, which
  • protects during transport,
  • provides safe environment for module checks
    (thermal and electrical connections, so that
    module can be checked without opening),
  • has mechanical fiducials to align module for
    module mounting.
  • Each module gets tested at Oxford after reception
    (same tests as at module production site).
  • Storage in shipping box in humidity statically
    controlled area (up to 400 modules).
  • Modules will be kept in shipping box until
    immediately before mounting.

Position fiducials
Module
Connector
8
Barrel Reception
  • Barrels will be delivered to tent outside of the
    heavy lab.
  • After removal of outer box transfer to lifting
    cart.
  • Wheel into clean room, lift to cold room floor
    level and move into cold room.
  • Remove ends of inner transport box, install cable
    and fibre supports, connect barrel DCS sensors.
  • Preassembly checks
  • Verify DCS sensor operation.
  • Connect cooling system and operate cooling system
    (cold). Verify operation.
  • Confirm harness integrity.

9
Assembly Overview
  1. Mount modules make thermal and electrical
    connections.
  2. Verify performance after mounting.
  3. After completion of barrel final acceptance test
  • Tight schedules require parallel operation of 1.
    and 2. on two assembly stations.
  • But switch between them is complex.
  • ? Do assembly in groups of 96 modules. First 16
    rows of lower modules (166 96), which then get
    checked. Then mount upper modules and check them
    out.

10
Module Mounting
  • High 3d-precision during insertion required ?
    robot.
  • Additional operations
  • Align dogleg to pigtail.
  • Apply thermal grease on cooling block.
  • Mate pigtail and dogleg connector.
  • Mount module cooling block clip.
  • Done by hand with tools held by a tooling frame.
  • Done row-by-row (first lower, than upper)
  • First 1. 2., then module insertion, then 3.
    4.

11
Tooling support and alignment
  • Tooling frame with vertical and horizontal
    travel, attached to front of transport box.
  • Positioning of tools by stages, aligned by hand
    with small lasers.
  • Alignment of robot automatically. Survey of
    brackets on barrel with laser sensors.
    Coordinates kept in database for retrieval during
    mounting.

Tooling frame
12
Procedure I Align Dogleg
Alignment rods
Template
Connector
Position fiducials
  • Remove tab with circuit board from module box
    (module stays covered).
  • Transfer pigtail connector position to template
    using position fiducials.
  • Position template using alignment rods onto
    barrel.
  • Adjust dogleg position (align to module mounting
    bushes) and fix.

13
Procedure II Apply Thermal Grease
  • A rectangular mask covers cooling block
    (maintains thickness of grease joint).
  • Opening of mask just slightly smaller than
    cooling block surface.
  • Back of cooling block supported from tool.
  • Grease squeezed out of reservoir by piston lever.
  • Applicator moves over mask, scrapes off excess
    grease.

14
Procedure III Mount Module
  • Done by robot (one program)
  • Pick up module from box
  • Survey module optically verify correct pickup,
    envelope.
  • Insert module (robot knows where to put it).
  • Drive in screws (limited torque).

Module box
Control by touch-screen
15
Procedure IV Apply Clips
  • Same tool used for clip removal.

16
Procedure V Electrical Connection
  • Template aligns connectors on pigtail and
    dogleg.
  • Pliers force connectors together.
  • Same template also used for disconnecting.

17
Clearances
  • Exposed wirebonds on modules demand great care.
  • All components and module (3-point constrained)
    must satisfy space envelope as given in SCT
    drawings.
  • Clearances during insertion 1-2mm on each side
    (depending on barrel).


18
Fault recovery
  • Care has been taken to isolate robot from
    external faults.
  • Separate UPS.
  • Compressed air?
  • Emergency stop button for operator.
  • Recovery software will return the module into box
    after retracing approach path.
  • Ongoing task more failure modes will show during
    shake-down before B3 arrival and will be taken
    care of.

19
Dismounting Modules
  • Reverse procedures of mounting.
  • Disconnect electrically.
  • Remove cooling block clips.
  • Remove module requires splitting of grease
    layer between module and cooling block. Support
    splitting mechanically.
  • Return module into module shipping box.

20
Time estimates
  • Estimated times for assembly
  • 5h for 6 modules (1 row of lower or upper
    modules) 45min/module
  • 96 modules in 80h 1 week (5d) of 2 daily shifts
    (8h) each.
  • ? During established assembly mount modules on
    one barrel for one week, while testing the other,
    then swap.

21
Manpower
  • Assembly
  • 2 ATLAS assembly techs
  • Up to 1 tech from electronics workshop
  • 2 staff from Oxford, 1 staff from UCL.
  • Testing
  • 1 postdoc and 1 grad student from Oxford.
  • Additional manpower from Oxford and other SCT
    collaborators can be found for limited periods.

22
Mechanical QA
23
Cooling System
  • Evaporative system (cooling capacity ?).
  • Drives up to 16 cooling loops (B6 2).
  • Two operation modes
  • C3F8 about -15 (cold) as in ATLAS.
  • C4F10 about 10 (warm).
  • Control as in ATLAS
  • Mass flows pressure drops adjusted so that
    cooling power exceeds heat load of detector at
    any time.
  • Heaters after the detector controlled by simple
    T-feedback so that remaining liquid evaporates.
  • No sophisticated control structures, just
    monitoring (? DCS).

Compressor
Storage
Condensor
24
Electrical QA
  • Repeat measurements as at production sites and
    after reception (allows for direct comparison).

25
DCS
  • Similar system as in ATLAS
  • Sensor readout (all SCT barrel sensors, system
    status and environment) using ELMBs.
  • Control and monitoring of power supplies (14
    crates) through ELMB-based crate controllers.
  • Distributed PVSS system.
  • Hardware interlock of cooling loop temperature
    through IBOXs, interlock matrix and interlock
    card in PS crates.
  • Additional interlocks for personal safety.

IBOXs
ELMBs
Environment sensors
26
Off-Detector Electronics
  • Optical readout (control data).
  • One 9U VME crate with VME CPU, up to 14 RODs and
    TIM.
  • One ROD reads 48 modules.
  • For assembly checks need 4 RODs.
  • Only for final acceptance test
  • B3 8 RODs
  • B5 12 RODs
  • B6 14 RODs
  • Read out histograms from ROD memory for various
    characterisation checks.

CPU
SCTLV2 PS
REV C Rod
Rev B ROD
TIM
27
Power supplies
  • Supply HV and LV.
  • Crate holds also controller (ELMB-based,
    connected through CAN bus to DCS) and interlock
    card.
  • One crate supplies 48 modules.
  • Assembly checks need 2(4) crates.
  • Final acceptance tests need 8 (B3), 12 (B5) and
    14 (B6) crates.

Interlock card
Controller
LV cards
HV cards
28
Power, ESD and Grounding
  • Power to critical components (power supplies
    etc.) backed up by UPS.
  • Special care has been taken to provide clean
    ground to allow meaningful electrical checks of
    assembled barrels.
  • All items in the cold room conductive and
    grounded, standard ESD procedures followed.

29
Status I
  • Transport infrastructure
  • B3 inner transport box complete and at RAL. Outer
    box needs finishing design and construction.
  • B3 service cages mechanical parts are ready.
    Mock assembly under way. Electrical components to
    be delivered soon.
  • Heavy Lab infrastructure
  • Clean room ready, used for power supply tests.
    Ready to receive and store modules.
  • Still to be done reception tools (lifting cart
    etc.)
  • Cold room service supports being installed.
    After that clean close.
  • Power cables ordered. To be delivered in May.
  • Readout fibres ordered. To be delivered in May.
  • Cooling system Pipework being installed.

30
Status II
  • Tooling
  • Most tools have been built and are being tested
    in the cold room.
  • Robot routinely mounting modules. Now
    programming recovery procedures.
  • Wait for sector prototype to practise procedures
    in realistic environment.
  • Read out and power supplies
  • Power supplies 1 crate with cards in Oxford,
    ironing out problems with ELMB crate controller.
  • DCS Environment monitoring operating, working on
    power supply control and monitoring.
  • Off-detector electronics crate with CPU, TIME
    and 2 RODs in Oxford. Reads out optically one
    module on bench (SCTLV2 power supplies). Standard
    checks working.

31
Schedule
  • Until arrival of B3 (expect end of June)
  • Finish all remaining transport infrastructure.
  • Finish all the remaining tasks to build
    infrastructure (cooling system, cables, cold
    room, etc.).
  • Test mounting procedures with sector prototype.
    Shake down procedures. Train technicians.
  • Get power supplies with control software and
    off-detector electronics with DAQ software
    working.
  • Start receiving modules.
  • After B3 arrival
  • Barrel reception checks.
  • Start mounting (production ramps up from 6
    modules /wk to 96 modules/wk)
Write a Comment
User Comments (0)
About PowerShow.com