Title: NERC Operating Manual Updates


1
NERC Operating Manual Updates
Spring - 2000
2
NERC Operating Manual Updates
For Board of Trustees approval February 7 8,
2000
For implementation February 15, 2000
3
NERC Operating Manual Updates
For Board of Trustees approval February 7 8,
2000
For implementation February 15, 2000
4
Policy 10 Interconnected Operation
  • To be approved by the BOT February 2001 and
    Implemented 2002
  • Providing 7 Questions are addressed

5
This change has been approved by the Security
Committee for interim implementation. The Board
is not requested to approve this change for now.
It will be posted for public comment as part of
other changes to Policy 1 planned for 2000.
6
For Board of Trustees approval February 7 8,
2000
Note Only changes are in Section F.
Only section F is being revised. Most of these
changes set new Requirements for reporting
Inadvertent Interchange balances and dispute
resolution. This is in response to difficulties
during the past few years in balancing the
Eastern and Western Interconnection Inadvertent
balances each month.
7
To ensure that all ties are metered.
8
Section 4 is an enhancement of requirements that
were in Appendix 1F.
9
To address problem of after-the-fact corrections.
10
No change in payback philosophy. Some changes for
clarity.
11
New.
12
Revised to a function of L10.
13
Provides for other payback methods.
14
New (highlighted)
15
Security Committee revision calendar day
changed to business day to avoid weekend
due-dates
Section 6.2 (highlighted) and subparts are new
Requirements.
16
Security Committee revision calendar day
changed to business day to avoid weekend
due-dates
Section 6.2 (highlighted) and subparts are new
Requirements.
17
Security Committee revision calendar day
changed to business day to avoid weekend
due-dates
Section 6.2 (highlighted) and subparts are new
Requirements.
18
For implementationFebruary 15, 2000
For Board of Trustees approval February 7 8,
2000
Sections A D are new. E has been revised. F is
unchanged. Purpose of these revisions is to set
reporting requirements and provide method for
resolving inadvertent balance disputes. These
disputes have contributed to the Eastern and
Western Interconnection inadvertent balance
reconciliation delays.
19
New.
20
New.
21
New.
22
New.
23
New.
24
30 days provides arbitrator time to prepare a
report
New.
25
Section E has been revised for clarity. New
(highlighted)
26
(No Transcript)
27
/ 5
/ 5
28
For Board of Trustees approval February 7 8,
2000
For implementationFebruary 15, 2000
29
(No Transcript)
30
The details of how to do this were moved to
the Compliance Template. Removed items that were
simply definitions or administrative matters
covered in other documents, such as the
Compliance Template and Certification
Bulletin. Removed all references to system
personnel. This Policy is focused on system
operators.
31
Only change is use of term Operating Authority.
32
The SOS will review these Guides and either
change to Standards, include in Appendix 8B1, or
eliminate in next version.
33
This Section has been greatly simplified. The
Certification specs have been moved to the
Certification Bulletin. Can be found
at ftp//www.nerc.com/pub/sys/all_updl/oc/sos/bu
lletin.pdf
34
For Board of Trustees approval February 7 8,
2000
For implementation February 15, 2000
Requirement 7B2 is new, and the only change in
this Policy. It was recommended by the System
Operator Subcommittee and Security Coordinator
Subcommittee.
Note Only changes are in Section B.
Security Committee Revision (marked text)
35
Help us!! Were not con- nec- ted!
36
Oops!! Theyre gone!
Eastern
Interconnection
37
I'm out'ta here!
AND SO AM I !