Optical Qualification and Plans for PFM - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Optical Qualification and Plans for PFM

Description:

Peak Strehl not reached within nominal focussing range of OGSE, PSF FWHM ~ 30% too wide. ... test, but confirms the focussing requirements for best performance ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 21
Provided by: norber2
Category:

less

Transcript and Presenter's Notes

Title: Optical Qualification and Plans for PFM


1
Optical Qualification and Plans for PFM
  • N. Geis
  • MPE

2
FPFPU Alignment
  • Alignment precision achieved for CQM
    (PACS-KT-PR-014)
  • Alignment made at KT, at ambient, with VIS light.
  • All offsets refer to TEL focus/LOS Meas REQ
  • Alignment Cube ? OB lt 0.3 mm position 0.5 mm
  • (for satellite alignment) lt 0.4 angle 1
  • OB ? detector arrays (VIS) lt 0.3 mm position 0.5
    mm
  • (internal alignment) lt 5 angle 1
  • ( linear resolution limit at Lyot stop)
  • M2 ? ext. Alignment Mirr lt 0.3 mm position 0.5
    mm
  • (to transfer alignment to MPE OGSE) lt 0.3
    angle 0.5
  • except 4, all requirements are met gt Repeat
    for PFM.
  • 5 angle could be improved to 3, but IIDA/B
    requirement of 1 unlikely to be
    verifiable/achievable

3
FPFPU Alignment
  • Alignment precision achieved for CQM (ILT tests)
  • Descoped program allowed neither characterization
    of OGSE, nor of CQM.
  • Measurement precision achievable with test
    equipment is lt 0.2 mm position lt 0.3 angle
  • ? OGSE suitable for verifying at the PFM
    requirements level.
  • 1) Test Optics ? Cryostat OB not done
  • 2) Test Optics ? FPFPU done (see next
    slide)
  • by evaluation from 1) and 2) ?
  • 3) FPFPU ? Cryostat OB not done (missing 1...)

Full PFM verification program should suffice to
demonstrate PFM alignment at requirements
level. However
4
FPFPU Alignment
  • Caveats
  • Known dimensional problems in OGSE, affecting the
    internal calibration path.For CQM, ad-hoc
    (large) alignment corrections had to be
    applied.For PFM tests, tracking and fixing of
    problem may be necessary. gt Manufacturing
    changes in OGSE and re-alignment ( 2 month
    effort).
  • Stability of Test Cryostat 1. Unexpectedly large
    shift (4mm) in LOS to external ( point) sources
    on cool-down of test cryostat.2. After warm-up
    a residual LOS shift of 0.43 mm remained.
    (This effect may be responsible in part for 1 mm
    boresight shift observed between VIS and IR
    cooldowns -- other contribution mechanical
    distortion of chopper assy, defocus see 3.)3.
    Tilting the cryostat shifts the external LOS by 2
    mm (caused by hardware failure?).4. Possible
    defocusing of external sources by 10 mm (reason
    unclear)
  • Either - fix these shifts by hardware mod.
    (unlikely) (1-2 month delay of OGSE test program)
    - characterise effect (repeatability) -- may not
    be repeatable (1 month / cool-down)- modify test
    cryostat to allow monitoring/compensation of
    internal alignment during ILT measurements.
    (1-2 month delay of OGSE test program)

5
FPFPU Optical Performance
  • FPFPU Itself
  • The Good
  • Fairly sharp images, in photometry and
    spectroscopy modes, close to expectations (see
    presentation by E. Sturm). Peak Strehl not
    reached within nominal focussing range of OGSE,
    PSF FWHM 30 too wide.
  • ? optical system basic performance qualitatively
    verified, however focus mismatch between OGSE
    focus and PACS focus, reason unknown.
  • Reduction of PSF peak height should be easily
    noticeable in the 105 mm photometer band when
    defocussing by 3 mm. (informal test, but
    confirms the focussing requirements for best
    performance claimed by PACS in the IID-B)
  • Further details are still under analysis, but no
    show stoppers have been flagged in the imaging
    area as yet.

6
FPFPU Optical Performance
  • FPFPU Itself
  • The Ugly
  • Grating Ghosts
  • Full Scans of the spectrometer section during CQM
    ILTs showed unexpected deviations from expected
    SED (see next slide)
  • Bumps of 10-50 of total power over an
    extended wavelength range in 1st order.
  • Extremely strong spikes at the long-wavelength
    end of each order.
  • This added signal which moreover seems to vary
    for different pixels may prevent proper
    calibration of astronomical spectra
    (line-continuum ratio, e.g.).
  • gt Non sequential ray trace model for
    spectrometer section in progress to identify
    causes.

7
Representative Spectrum from ILT
H20 features
2nd order leak 0th order ghost
3rd order leak 0th order ghost
2 pass ghost
200
8
l-l Plot of Ghost Responses in 1st Order
0 t h o r d e r
Ghost 1st order 3pass
Ghost 1st order 2pass
Normal Signal
Ghost 2nd order 2pass
Leak 2nd order
9
l-l Plot of Ghost Responses in 2nd Order
107
Ghost 2nd order 2pass
0 t h o r d e r
Lambda Seen um
Normal Signal
Ghost 3rd order 2pass
Leak 3rd order
65
106
70
Lambda Set um
10
l-l Plot of Ghost Responses in 3rd Order
75
0 t h o r d e r
Lambda Seen um
Ghost 3rd order 2pass
Normal Signal
Ghost 4th order 2pass
Leak 4th order
50
74
53
Lambda Set um
11
FPFPU Optical Performance
  • Grating Ghosts Ongoing Work
  • Preliminary results of a simplified optical model
    of the Collimator-Grating assembly using
    non-sequential raytracing
  • Leakage from next higher order affects the long
    wavelength end of each operating order this is
    normal and can be explained/expected from the
    tail of the filter blocking curves.
  • The high temperature of the telescope background
    enhances the effect such that it becomes
    important over a 510mm wavelength range.
  • Interesting ray paths to detector array
    identified (see following slides).
  • The observed sharp spectral spikes at longest
    wavelength, and some surrounding extended signal
    are caused by 0th order ( direct mirror)
    reflection from the grating, ghosting into the
    beam path via Collimator 1 mirror (see following
    slides).
  • A broad, 10-50 excess near 170-180mm is caused
    by a double pass of the grating in 2nd order
    (Ghost-l 105 mm) supported by Collimator 2
    acting as a retro-reflector. The signal is strong
    because of the short wavelength involved. Bounded
    on one side by blocking filter curve, on other
    side by falling off the mirrors.

12
Beam Path of 0th Order Ghost, Simple Baffle
Coll 2
Coll 1
Input Slit
Det.
Baffle
Grating
13
Beam Path of 2nd Order 2pass Leak, Mechanism
14
Beam Path of 2nd Order 2pass Leak, simple baffle
Coll 2
Coll 1
Input Slit
Det.
Black baffle
Grating
15
2 (Preliminary) Baffles in place
Coll 2
Coll 1
Input Slit
Det.
Black baffle
Black baffle
Grating
16
l-l Plot of Ghost Responses in 1st Order
0 t h o r d e r
Ghost 1st order 3pass
Ghost 1st order 2pass
Normal Signal
Ghost 2nd order 2pass
Leak 2nd order
17
l-l Plot of Ghosts, 1st Order, with Baffles
Ghost 1st order 2pass
Normal Signal
Ghost 2nd order 2pass
Leak 2nd order
18
Ghost Responses Magnitude
19
FPFPU Optical Performance
  • Grating Ghosts Several identified Possible
    fixes
  • Mounting of additional baffles in
    Collimator-Grating area. This means Modification
    of FPU !
  • Simple blocking baffles
  • Try to find positions for baffle(s) which
    maximise suppression of unwanted beam paths,
    while minimising vignetting for normal beam.
  • Trade-off necessary.
  • Some losses expected (5-10), mostly at long
    wavelength.
  • Can block most, but not all rogue paths.
  • Minor modification of FPU, qualification of
    design change could be handled by
    analysis/similarity.
  • Needs to happen very soon, since all PFM parts
    have already been manufactured, black-painting
    run imminent.

20
Summary
  • Consequences for PFM Programme
  • Spectrometer Ghosts need to be fixed, fix ready
    to be implemented soonest Feb. 2005.Manufacturing
    /assembly of PFM collimator section will have to
    be delayed.However, overall PFM M/I schedule is
    probably not affected yet.
  • Proper re-alignment and characterisation/calibrati
    on of OGSE and test cryostat, including hardware
    modifications, will take 5 months (no margin),
    worst case 8 months, starting mid Jan.
    2005.Still compatible with PFM schedule.
  • Schedule extremely tight - no margin. For the PFM
    there will be a full performance characterisation.
Write a Comment
User Comments (0)
About PowerShow.com