Title: Optical Qualification and Plans for PFM
1Optical Qualification and Plans for PFM
2FPFPU Alignment
- Alignment precision achieved for CQM
(PACS-KT-PR-014) - Alignment made at KT, at ambient, with VIS light.
- All offsets refer to TEL focus/LOS Meas REQ
-
- Alignment Cube ? OB lt 0.3 mm position 0.5 mm
- (for satellite alignment) lt 0.4 angle 1
- OB ? detector arrays (VIS) lt 0.3 mm position 0.5
mm - (internal alignment) lt 5 angle 1
- ( linear resolution limit at Lyot stop)
- M2 ? ext. Alignment Mirr lt 0.3 mm position 0.5
mm - (to transfer alignment to MPE OGSE) lt 0.3
angle 0.5 - except 4, all requirements are met gt Repeat
for PFM. - 5 angle could be improved to 3, but IIDA/B
requirement of 1 unlikely to be
verifiable/achievable
3FPFPU Alignment
- Alignment precision achieved for CQM (ILT tests)
- Descoped program allowed neither characterization
of OGSE, nor of CQM. - Measurement precision achievable with test
equipment is lt 0.2 mm position lt 0.3 angle - ? OGSE suitable for verifying at the PFM
requirements level. -
- 1) Test Optics ? Cryostat OB not done
- 2) Test Optics ? FPFPU done (see next
slide) - by evaluation from 1) and 2) ?
- 3) FPFPU ? Cryostat OB not done (missing 1...)
Full PFM verification program should suffice to
demonstrate PFM alignment at requirements
level. However
4FPFPU Alignment
- Caveats
- Known dimensional problems in OGSE, affecting the
internal calibration path.For CQM, ad-hoc
(large) alignment corrections had to be
applied.For PFM tests, tracking and fixing of
problem may be necessary. gt Manufacturing
changes in OGSE and re-alignment ( 2 month
effort). - Stability of Test Cryostat 1. Unexpectedly large
shift (4mm) in LOS to external ( point) sources
on cool-down of test cryostat.2. After warm-up
a residual LOS shift of 0.43 mm remained.
(This effect may be responsible in part for 1 mm
boresight shift observed between VIS and IR
cooldowns -- other contribution mechanical
distortion of chopper assy, defocus see 3.)3.
Tilting the cryostat shifts the external LOS by 2
mm (caused by hardware failure?).4. Possible
defocusing of external sources by 10 mm (reason
unclear) - Either - fix these shifts by hardware mod.
(unlikely) (1-2 month delay of OGSE test program)
- characterise effect (repeatability) -- may not
be repeatable (1 month / cool-down)- modify test
cryostat to allow monitoring/compensation of
internal alignment during ILT measurements.
(1-2 month delay of OGSE test program)
5FPFPU Optical Performance
- FPFPU Itself
- The Good
- Fairly sharp images, in photometry and
spectroscopy modes, close to expectations (see
presentation by E. Sturm). Peak Strehl not
reached within nominal focussing range of OGSE,
PSF FWHM 30 too wide. - ? optical system basic performance qualitatively
verified, however focus mismatch between OGSE
focus and PACS focus, reason unknown. - Reduction of PSF peak height should be easily
noticeable in the 105 mm photometer band when
defocussing by 3 mm. (informal test, but
confirms the focussing requirements for best
performance claimed by PACS in the IID-B) - Further details are still under analysis, but no
show stoppers have been flagged in the imaging
area as yet.
6FPFPU Optical Performance
- FPFPU Itself
- The Ugly
- Grating Ghosts
- Full Scans of the spectrometer section during CQM
ILTs showed unexpected deviations from expected
SED (see next slide) - Bumps of 10-50 of total power over an
extended wavelength range in 1st order. - Extremely strong spikes at the long-wavelength
end of each order. - This added signal which moreover seems to vary
for different pixels may prevent proper
calibration of astronomical spectra
(line-continuum ratio, e.g.). - gt Non sequential ray trace model for
spectrometer section in progress to identify
causes.
7Representative Spectrum from ILT
H20 features
2nd order leak 0th order ghost
3rd order leak 0th order ghost
2 pass ghost
200
8l-l Plot of Ghost Responses in 1st Order
0 t h o r d e r
Ghost 1st order 3pass
Ghost 1st order 2pass
Normal Signal
Ghost 2nd order 2pass
Leak 2nd order
9l-l Plot of Ghost Responses in 2nd Order
107
Ghost 2nd order 2pass
0 t h o r d e r
Lambda Seen um
Normal Signal
Ghost 3rd order 2pass
Leak 3rd order
65
106
70
Lambda Set um
10l-l Plot of Ghost Responses in 3rd Order
75
0 t h o r d e r
Lambda Seen um
Ghost 3rd order 2pass
Normal Signal
Ghost 4th order 2pass
Leak 4th order
50
74
53
Lambda Set um
11FPFPU Optical Performance
- Grating Ghosts Ongoing Work
- Preliminary results of a simplified optical model
of the Collimator-Grating assembly using
non-sequential raytracing - Leakage from next higher order affects the long
wavelength end of each operating order this is
normal and can be explained/expected from the
tail of the filter blocking curves. - The high temperature of the telescope background
enhances the effect such that it becomes
important over a 510mm wavelength range. - Interesting ray paths to detector array
identified (see following slides). - The observed sharp spectral spikes at longest
wavelength, and some surrounding extended signal
are caused by 0th order ( direct mirror)
reflection from the grating, ghosting into the
beam path via Collimator 1 mirror (see following
slides). - A broad, 10-50 excess near 170-180mm is caused
by a double pass of the grating in 2nd order
(Ghost-l 105 mm) supported by Collimator 2
acting as a retro-reflector. The signal is strong
because of the short wavelength involved. Bounded
on one side by blocking filter curve, on other
side by falling off the mirrors. -
12Beam Path of 0th Order Ghost, Simple Baffle
Coll 2
Coll 1
Input Slit
Det.
Baffle
Grating
13Beam Path of 2nd Order 2pass Leak, Mechanism
14Beam Path of 2nd Order 2pass Leak, simple baffle
Coll 2
Coll 1
Input Slit
Det.
Black baffle
Grating
152 (Preliminary) Baffles in place
Coll 2
Coll 1
Input Slit
Det.
Black baffle
Black baffle
Grating
16l-l Plot of Ghost Responses in 1st Order
0 t h o r d e r
Ghost 1st order 3pass
Ghost 1st order 2pass
Normal Signal
Ghost 2nd order 2pass
Leak 2nd order
17l-l Plot of Ghosts, 1st Order, with Baffles
Ghost 1st order 2pass
Normal Signal
Ghost 2nd order 2pass
Leak 2nd order
18Ghost Responses Magnitude
19FPFPU Optical Performance
- Grating Ghosts Several identified Possible
fixes - Mounting of additional baffles in
Collimator-Grating area. This means Modification
of FPU ! - Simple blocking baffles
- Try to find positions for baffle(s) which
maximise suppression of unwanted beam paths,
while minimising vignetting for normal beam. - Trade-off necessary.
- Some losses expected (5-10), mostly at long
wavelength. - Can block most, but not all rogue paths.
- Minor modification of FPU, qualification of
design change could be handled by
analysis/similarity. - Needs to happen very soon, since all PFM parts
have already been manufactured, black-painting
run imminent.
20Summary
- Consequences for PFM Programme
- Spectrometer Ghosts need to be fixed, fix ready
to be implemented soonest Feb. 2005.Manufacturing
/assembly of PFM collimator section will have to
be delayed.However, overall PFM M/I schedule is
probably not affected yet. - Proper re-alignment and characterisation/calibrati
on of OGSE and test cryostat, including hardware
modifications, will take 5 months (no margin),
worst case 8 months, starting mid Jan.
2005.Still compatible with PFM schedule. - Schedule extremely tight - no margin. For the PFM
there will be a full performance characterisation.