Title: County of Ventura


1
County of Ventura Public Works Agency Water
and Sanitation Department
Reddy Pakala, Director February 19, 2009 El Rio
Municipal Advisory Council
2
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)
3
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)EL RIO PROJECT
FUNDING RECAP REVENUE FUNDING SOURCE
Estimated Additional Expenditures For Individual

11,200,000 Property Owners in the Unincorporated
Area (9,000/parcel X 1,300 parcels)

TOTAL 50.0 MILLION
4
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)
  • Estimated cost of the public sewer collection
    system is approximately 38 million.
  • To date, the County has secured approximately
    17.0 million in local, State, and Federal grants
    for the construction of the El Rio Sewer
    Collection System.
  • Estimated project cost is for the public sewer
    system, and does not include the cost of
    constructing private sewer laterals, City of
    Oxnard Sewer Connection Fee, or abandonment of
    existing septic systems.
  • Phases 1, 2, 3, 4, 5, 6 and 7 were developed
    based upon the following criteria
  • Available grant amount
  • Grant eligibility criteria
  • Time schedule for a given grant
  • Phase 5A is planned to be constructed using a low
    interest State loan.
  • The County is applying for funding through the
    American Recovery and Reinvestment Act of 2009
    (Economic Stimulus Bill) for construction of
    Phases 5B, 5C, and 5D.

5
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)
  • CONSTRUCTION PHASES UPDATES
  • Phase I, Strickland Tract Area - Construction
    was completed in December 2005. Funded by a
    2.5 million State Water Resources Control Board
    (SWRCB) Proposition 13 grant and 818,618 from
    local funding (Montgomery Lift Station). 100 of
    properties connected in Phase 1.
  • Phase 2 - Construction was completed in June
    2007. Funded by a 2.5 million SWRCB
    Proposition 13 grant and 637,000 from local
    funding. Over 90 of properties connected in
    Phases 2 and 4. Fifteen properties still to be
    connected.
  • Phase 3 - Freeway Corridor This project
    connected the El Rio sewer system to the City of
    Oxnard sewer system. Construction was completed
    in August 2007. Funded by a 1.458 million SWRCB
    Small Communities Grant and 300,539 from local
    funding.
  • Phase 4 - Portion of South Central
    Construction connects Phases 2 and 3.
    Construction was completed in June 2007. Funded
    by a 652,000 U.S. EPA grant and 938,478 from
    local funding.
  • Phase 5 - Phase 5 is planned to be constructed
    in four phases, 5A, 5B, 5C, and 5D. Phase 5A
    construction began in late September 2008, and is
    scheduled to be completed in February 2010.
    Funding is from the SWRCB Clean Water State
    Revolving Fund (SRF) Financing Program.
    Construction for Phase 5B, 5C and 5D is scheduled
    to start in September 2009.
  • If we do not get Stimulus Plan funds, we will use
    SRF loan to construct Phases 5B, 5C, and 5D.
  • Phase 6 - Construction began in May 2008, and
    was completed in December 2008 Homeowners will
    be asked to connect to the sewer system after
    the sewer trunk line within Simon Way is
    completed in July 2009 as part of Phase 5A
    beginning in August 2009. Funding is from a
    2.155 million grant from the SWRCB Prop. 50
    Consolidated Grant Program.
  • Phase 7 - Construction began in June 2008, and
    scheduled to be completed in May 2009. Funding
    is from a 1.921 million grant from the SWRCB
    Prop. 50 Integrated Regional Water Management
    (IWRM) Implementation Grant. Homeowners will be
    asked to connect beginning November 2009, after
    Phase 6 property owners are connected.
  • Phase 7A Construction began in December 2008
    and scheduled to be completed in May 2009.
    Funding is from a 1.1317million grant from the
    SWRCB Prop. 50 IWRM Implementation Grant.
    Homeowners will be asked to connect in August
    2009 along with Phase 6 property owners

6
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)
  • The current State loan program is for a term of
    20 years, and an interest rate of approximately
    2.6.
  • County Staff and District 5 Board of Supervisor
    have worked with the State Water Resources
    Control Board (SWRCB) to extend the term of the
    State loan from 20 to 30 years, and to reduce the
    State loan interest rate down to zero percent
    based on the median income levels of a
    disadvantaged community.
  • The County requested a 30-year loan and a lower
    interest rate for disadvantaged communities in
    California. The SWRCB is reviewing our request.
    A decision is expected by the end of 2009.

7
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)
  • The County is requesting funding for Phases 5B,
    5C, and 5D from the Economic Stimulus Plan
    funding Bill.
  • The County will pursue Prop. 84 grants for the
    construction of Phase 5D of the El Rio Sewer
    System if funds are not secured from the Economic
    Stimulus Bill.
  • Any grants secured by the County for the El Rio
    Sewer Project will reduce the loan amount for
    Phase 5 construction.
  • The construction schedule is dependent upon state
    approval for funding and construction-related
    issues.

8
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)
  • Tentative Property Owners Meeting Schedules

9
(No Transcript)
10
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT (EL RIO SEWER PROJECT RESIDENTIAL
PROPERTIES)Estimated Total Costs per MEF
Total one-time cost of approximately 25,000 per
MEF (1 2 3 4)
Plus Recurring OM costs. Currently 37/MEF/Month
(Reviewed annually) 5
OR One-time cost of approximately 9,000 per MEF
(1 2 3), and installment payments of
approximately 90 per MEF per month for 20
years. Plus Recurring
OM costs. Currently 37/MEF/Month (Reviewed
annually) 5

? Meter Equivalency Factor (MEF) ?? County
secured a grant of up to 5,000 maximum for
low-income property owners that occupy their
homes in Phases 1,2,3, 4,5A, 6 and 7 County will
apply for available grant funding for Phases 5B,
5c, and 5D
11
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)Lateral Line
Grant up to 5,000 for Very Low Income Property
Owners
  • .
  • The grant is for private property lateral line
    construction, and is for very low-income
    property owners who reside in their own home on
    the the property. Refer to table at right for
    total gross annual household income, depending on
    how many persons reside in the home (adults and
    children). Total household income on the chart
    is the upper amount of annul gross household
    income.
  • Verification of your gross income must be
    included, for example a copy of your 2008 Federal
    and State Income Tax Returns, Form 1099, W-2 Form
    (s), or other verifiable gross income
    documentation.
  • To be eligible for a grant, and before sewer
    service can begin, you must either pay the Sewer
    Connection Fees or make arrangements to make
    installment payments for 15 or 20 years, and
    obtain a County of Ventura Building and Safety
    permit to connect to the sewer system, construct
    the lateral, and abandon the septic tank within
    90 days of notification of the completion of the
    sewer collection
  • system.
  • The property must be connected to new sewer
    system and property owners must provide
    construction cost invoices before the grant
    amount can be awarded. The plumbing permit is an
    eligible expense

12
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)
  • Those property owners who do not connect to the
    new sewer system within the approved schedule for
    each phase of the project, the Los Angeles
    Regional Water Quality Control Board (LARWQCB)
    will send a Notice of Violation to the individual
    property owners.
  • A copy of the letter from the LARWQCB Executive
    Officer sent to the few property owners in Phase
    2 that have not connected is included.
  • Property owners are subject to penalties of up to
    5,000 for each day in which the violation occurs
    (sewer discharge to septic systems).

13
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)Sample Los
Angeles Regional Water Quality Control Board
LetterPage 1
14
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)Sample Los
Angeles Regional Water Quality Control Board
LetterPage 2
15
FOREBAY GROUNDWATER CONTAMINANT ELIMINATION
PROJECT(EL RIO SEWER PROJECT)
If you have additional questions, or would like
further information, please
call
  • For general information,
  • please call
  • Bill Lykins
  • Staff Services Specialist
  • Ventura County
  • Water and Sanitation Department
  • (805) 378-3011
  • Monday through Friday
  • 800 a.m. 500 p.m.
  • For technical information,
  • please call
  • Cefe Munoz
  • Project Manager
  • Ventura County
  • Water and Sanitation Department
  • (805) 378-3020
  • Monday through Friday,
  • 800 a.m. 500 p.m.